Rio Grande Silvery Minnow v. Keys

356 F. Supp. 2d 1222, 2002 U.S. Dist. LEXIS 27750, 2002 WL 32810341
District Court, D. New Mexico·Decided September 23, 2002·No. CIV. 99-1320 JP/RLP-ACE·Published·Cited by 2 cases

Opinion

MEMORANDUM OPINION AND FINDINGS OF FACT AND CONCLUSIONS OF LAW

PARKER, Chief District Judge.

The Endangered Species Act — Congres sional Mandates and the Sole Exception

Congress enacted the Endangered Species Act (“ESA”) in order to conserve endangered and threatened species and the ecosystems on which they depend. The ESA prohibits federal agencies from pursuing actions that “jeopardize the continued existence of any endangered species” or that result in the “take” of any endangered species. The words “jeopardize,” “jeopardy,” and “take” are statutory terms of art used in the ESA. The Supreme Court has emphasized that the language of the ESA “admits of no exception” to the requirement to give endangered species the highest priority. See TVA v. Hill, 437 U.S. 153, 173, 98 S.Ct. 2279, 57 L.Ed.2d 117 (1978). The ESA requires federal agencies “to afford first priority to the declared national policy of saving endangered species” and “to halt and reverse the trend toward species extinction, whatever the cost.” Id. at 184, 185, 98 S.Ct. 2279 (emphasis added). In enacting the ESA, Congress required the federal courts to give greater protection to endangered species over human interests. Also, Congress did not allow federal courts to apply the ESA differently in different regions of the nation. Congress’ mandate, expressed in the ESA, to protect endangered species applies equally in wet and in desert regions of the United States.

Concerned about the broad ramifications of the ESA after the Supreme Court’s ruling in TVA v. Hill, Congress amended the ESA to create a single exception to the stringent requirements of the ESA. The amendment established the Endangered Species Committee (commonly known as “the God Squad”). The God Squad is composed of six high-level members from the Executive branch of the federal government and presidential appointees: (1) the Secretary of Agriculture, (2) the Secretary of the Army, (3) the Chairman of the Council of Economic Advisors, (4) the Administrator of the Environmental Protection Agency, (5) the Secretary of the Interior, (6) the Administrator of the National Oceanic and Atmospheric Administration, and (7) a presidential appointee from each affected state. 16 U.S.C. § 1536(e)(3). The God Squad is authorized to balance the interests of the public and the interests of the endangered species. If the God Squad determines that the public interests outweigh the interests of the endangered species, then it can grant a federal agency an exemption from following the mandates of the ESA. 16 U.S.C. § 1536(e)-(h). *1225 In amending the ESA, Congress specifically and exclusively delegated this balancing power to the God Squad, not to the federal courts. The lower federal courts, therefore, must continue to apply the ESA as interpreted by the Supreme Court, i.e., they must continue to give the highest priority to protecting endangered species “whatever the cost.”.

In order for the God Squad to grant an exemption from the ESA’s prohibition against “jeopardy” and “take” of an endangered species, someone must apply to the Secretary of the Interior, The following are authorized to seek an exemption: “A federal agency, the Governor of the State in which an agency action will occur, if any, or a permit or license applicant.” 16 U.S.C. § 1536(g). Congress did not grant the federal courts the ability to seek such an exemption. By asking this Court to uphold a jeopardy determination with no reasonable and prudent alternative, the Federal Defendants are, in effect, asking this Court to perform the function of the God Squad. Congress has determined that, if the Federal Defendants or other authorized persons want an exemption, they must petition the God Squad, and neither the Federal Defendants nor others authorized by statute have done so.

Background of the Current Crisis

The Fish and Wildlife Service (“FWS”) issued its first Biological Opinion (“BO”) on June 29, 2001. Rejecting the Plaintiffs’ challenge, this Court upheld that BO in an April 19, 2002 Memorandum Opinion and Order. This Court found that although the BO said the silvery minnow was in jeopardy, the BO set forth a sufficient Reasonable and Prudent Alternative (“RPA”) to protect the minnow. This Court concluded, therefore, that in issuing the June 29, 2001 BO, FWS had not been arbitrary and capricious. The Bureau of Reclamation (“BOR”) then operated under the terms of the June 29, 2001 BO.

In early 2002, the BOR became aware of the strong possibility of severe drought conditions throughout 2002. This was confirmed during April 2002 when the levels of snowpack that supplied water to the Rio Grande basin were determined to be far lower than normal. Hence, as early as the spring of this year, the BOR knew or should have known that it would be unable to meet the June 29, 2001 BO flow requirements for the remainder of the year. Likewise, as early as April 2002, the BOR knew or should have known that it would have to reinitiate consultation with FWS and that a jeopardy opinion without a reasonable and prudent alternative might result. Nonetheless, the BOR delayed until August 2002 to request reinitiation of consultation. But, during the four or five month interim, the BOR had already released from the upstream reservoirs and delivered nearly all of the 2002 contracted water under the San Juan-Chama Project (“SJCP”) and the Middle Rio Grande Project (“MRGP”).

If the BOR had earlier alerted FWS to BOR’s predicament, which belatedly (only a little over a week ago) resulted in a finding by FWS of jeopardy to the silvery minnow with no reasonable and prudent alternative, the BOR, FWS, or others authorized by law could have applied quite a while ago for a God Squad exemption. The BOR still has not pursued the Con-gressionally-preseribed procedure for obtaining an exemption from the ESA. Instead, it has, in substance, turned to this Court for an exemption, which this Court is powerless to grant.

The actions and inactions of the BOR resulted in a crisis that was then thrust upon this Court a few days ago. This Court had to make very difficult choices with limited ESA options on an emergency basis. The Court believes this crisis situation could have been avoided if the Federal *1226 Defendants, especially the BOR, had properly performed their statutory duties.

An important justification for affirming the June 29, 2001 BO was that it provided for reinitiation of consultation should drought conditions occur. This Court reasonably understood and expected that, when faced with severe drought, BOR would quickly request reinitiation of consultation which would result in a proposed action and an RPA that would avoid jeopardy to the silvery minnow, most likely by BOR using its full discretion to provide more, not less, water releases for the benefit of the silvery minnow. The Court did not expect that BOR would continue to insist that it lacked legal authority to restrict contract deliveries.

Free access — add to your briefcase to read the full text and ask questions with AI

Rio Grande Silvery Minnow v. Keys, 356 F. Supp. 2d 1222, 2002 U.S. Dist. LEXIS 27750, 2002 WL 32810341 (D.N.M. 2002).

356 F. Supp. 2d 1222 (Rio Grande Silvery Minnow v. Keys) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Forest Guardians v. United States Bureau of Reclamation
462 F. Supp. 2d 1177 (D. New Mexico, 2006)
Rio Grande Silvery Minnow v. Keys
469 F. Supp. 2d 1003 (D. New Mexico, 2005)