Rio Grande Silvery Minnow v. Keys

355 F.3d 1215, 2004 WL 25310
CourtCourt of Appeals for the Tenth Circuit
DecidedJanuary 5, 2004
DocketNos. 02-2254, 02-2295, 02-2255, 02-2304, 02-2267
StatusPublished
Cited by21 cases

This text of 355 F.3d 1215 (Rio Grande Silvery Minnow v. Keys) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rio Grande Silvery Minnow v. Keys, 355 F.3d 1215, 2004 WL 25310 (10th Cir. 2004).

Opinion

JOHN C. PORFILIO, Senior Circuit Judge.

This matter arises upon the court’s own initiative. Papers filed in response to the petition for rehearing en banc have suggested this appeal has been mooted by events occurring after the entry of the opinion. We have obtained the viewpoints of Appellants and Appellees on this issue and have concluded the appeal is moot. Although the petition for en banc rehearing is still pending, we further conclude the appeal should be dismissed, and the panel opinion should be vacated.

[1219]*1219We must begin our analysis by recalling the limited issue present in this appeal. The panel reviewed a preliminary injunction certified to us by the district court under Fed.R.Civ.P. 54(b). The injunctive provisions of the court’s order mandated:

7. The Bureau of Reclamation must provide sufficient flows of water for the remainder of 2002 to maintain a flow of 50 cfs at San Acacia Diversion Dam, and to maintain a flow in the Albuquerque Reach from Angostura Diversion Dam to Isleta Diversion Dam, but is not required to pass flows through the Isleta Reach.
8. If necessary to meet these flow requirements for the remainder of 2002, the Bureau of Reclamation must release water from Heron Reservoir in 2002.
9. The Federal Government must compensate those, if any, whose contractual rights to water are reduced in order to meet the aforementioned flow requirements.
10. The Bureau of Reclamation and Fish and Wildlife Service must keep in place all other (non-flow) elements of the Reasonable and Prudent Alternative stated in the Fish and Wildlife Service June 29, 2001 Biological Opinion.
11. In order to help protect the survival and recovery of the silvery minnow, the Bureau of Reclamation and the Fish and Wildlife Service must, to the extent reasonably possible, comply with the actions that are identified in the June 29, 2001 Biological Opinion and in the September 12, 2002 Biological Opinion under the headings of “Reasonable and Prudent Measures” and “Conservation Recommendations.”
12. The Bureau of Reclamation and Fish and Wildlife Service must reinitiate consultation immediately to plan for the various contingencies that may arise during the rest of 2002 and during 2003 based on the different amounts of water that may be available in the Rio Grande Basin.
13. Beginning January 2003, the Bureau of Reclamation must comply with the flow requirements of the June 29, 2001 Biological Opinion until a new Biological Opinion is issued that contains a Reasonable and Prudent Alternative that avoids jeopardy, if possible.
14. If necessary to meet flow requirements in 2003 either under the June 29, 2001 Biological Opinion or under a new Biological Opinion resulting from reiniti-ation of consultation, the Bureau of Reclamation must reduce contract deliveries under the San Juan-Chama Project and/or the Middle Rio Grande Project, and /or must restrict diversions by the Middle Rio Grande Conservancy District under the Middle Rio Grande Project, consistent with the Bureau of Reclamation’s legal authority as determined in the Court’s April 19, 2002 Memorandum Opinion and Order.

As of today, the parties agree all provisions of the injunction have either been met or were never invoked. Most importantly, we are informed that between the entry of the injunctive order and December 31, 2003, the Bureau of Reclamation has not had to comply with paragraph 14 of the district court’s order by.reducing delivery of allocated water to any contract user.

Thus, for all practical purposes, none of the provisions of the injunction remain. This court then faces the question of what relief we can afford by either affirming or reversing the preliminary injunction on en banc review, if granted. The answer is none.

The climatological circumstances that occurred during the appeal and the passage of time have rendered the injunction superfluous. No water has been diverted, [1220]*1220and the order requiring diversion expired on December 31, 2003. Thus, the injunc-tive order from which this appeal was taken no longer provides the court with a live controversy to review. Therefore, this appeal is moot. Church of Scientology v. United States, 506 U.S. 9, 12, 113 S.Ct. 447, 121 L.Ed.2d 313 (1992) (appeal becomes moot if the appellate court can fashion no meaningful relief); Jones v. Temmer, 57 F.3d 921, 922 (10th Cir.1995) (appeal becomes moot when the issue upon which the case is based ceases to exist). In its supplemental brief, the Government concedes the point.

The Government further concedes “[t]he limited exception to the mootness doctrine for disputes capable of repetition, yet evading review does not apply in this case.” It states although the legal issue of the discretionary authority of the Bureau of Reclamation may arise again, “it is not clear that the question whether Reclamation has discretion to use Project water for endangered species purposes” will evade judicial review, citing Beattie v. United States, 949 F.2d 1092, 1094 n. 2 (10th Cir.1991). The Government correctly points out if the district court’s conclusion that the Bureau of Reclamation has discretion under the contracts is embodied in a final order, that analysis will once again be subject to review, and sufficient time for the appellate process to run will be available.

Having concluded the appeal is moot, we must next decide whether the panel opinion should be vacated. The parties do not agree upon an answer.

While the Government asserts the panel opinion must be vacated, it also urges us to order the district court to vacate its order and dismiss the entire ease. Appellees, however, argue against vacating the panel opinion and strongly contest vacating the injunctive order and dismissal of the case. We shall examine these positions separately-

Whether any opinion should be vacated on the basis of mootness is an equitable question. U.S. Bancorp Mortgage Co. v. Bonner Mall Partnership, 513 U.S. 18, 26, 115 S.Ct. 386, 130 L.Ed.2d 233 (1994). Following this concept, we have held that when the party seeking relief is the cause of the mootness, vacatur will not be granted. 19 Solid Waste Dept. Mechanics v. City of Albuquerque, 76 F.3d 1142, 1144-45 (10th Cir.1996); Oklahoma Radio Associates v. F.D.I.C., 3 F.3d 1436 (10th Cir.1993); Martinez v. Winner, 800 F.2d 230 (10th Cir.1986). We have also held when appellants voluntarily contribute to the cause of mootness, vacatur will be denied. In re Western Pac. Airlines, Inc., 181 F.3d 1191, 1197-98 (10th Cir. 1999).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Calvary Albuquerque v. Rubio
Tenth Circuit, 2025
Schell v. OXY USA Inc.
814 F.3d 1107 (Tenth Circuit, 2016)
Schell v. OXY USA
Tenth Circuit, 2015
Fleming v. Gutierrez
785 F.3d 442 (Tenth Circuit, 2015)
Front Range Equine Rescue v. Vilsack
782 F.3d 565 (Tenth Circuit, 2015)
Rio Grande Silvery Minnow v. Bureau of Reclamation
601 F.3d 1096 (Tenth Circuit, 2010)
Chihuahuan Grasslands Alliance v. Kempthorne
545 F.3d 884 (Tenth Circuit, 2008)
MacArthur v. San Juan County
391 F. Supp. 2d 895 (D. Utah, 2005)
Klamath Irrigation District v. United States
67 Fed. Cl. 504 (Federal Claims, 2005)
Suarez-Tejeda v. United States
85 F. App'x 711 (Tenth Circuit, 2004)
Rio Grande Silvery Minnow v. Keys, III
355 F.3d 1215 (Tenth Circuit, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
355 F.3d 1215, 2004 WL 25310, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rio-grande-silvery-minnow-v-keys-ca10-2004.