Rieth-Riley Construction Co. v. Department of Transportation

357 N.W.2d 62, 136 Mich. App. 425
CourtMichigan Court of Appeals
DecidedAugust 6, 1984
DocketDocket 67999
StatusPublished
Cited by25 cases

This text of 357 N.W.2d 62 (Rieth-Riley Construction Co. v. Department of Transportation) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rieth-Riley Construction Co. v. Department of Transportation, 357 N.W.2d 62, 136 Mich. App. 425 (Mich. Ct. App. 1984).

Opinion

M. J. Kelly, J.

In August, 1979, M & B Contracting Corporation entered into a contract with defendant, Michigan Department of Transportation (MDOT), for the construction of 6.1 miles of grading and drainage structures in Kalkaska and Missaukee Counties with a 24-foot bituminous aggregate surface. M & B in turn entered into a subcontract with plaintiff, Rieth-Riley Construction Co., Inc., which provided that the subcontractor was to provide certain materials, including bituminous base course, to M & B for use in the project. The contract between MDOT and M & B contained price adjustments, or escalator clauses, for two asphalt cement items, but not for bituminous base course.

The purpose for the inclusion of such escalator clauses dates back to 1974 when MDOT included such provisions in its highway construction contracts to compensate contractors and subcontractors for the increased costs of acquiring materials and fuel during the course of construction. The clauses are solely a cost reimbursement measure that reflect the changes in the cost of material from the time of bidding to the time of performance. Its inclusion benefits MDOT insofar as it stabilizes and reduces bids which would otherwise likely be substantially higher because of the contractor’s cost uncertainties for acquiring material and fuel.

MDOT admitted that the omission of the bituminous base course from the table of escalated items was unintentional. In fact, defendant circulated a memorandum to the Michigan Asphalt Paving *428 Association, of which plaintiff was a member, indicating that cost adjustment clauses would be applied to bituminous materials.

In the subcontract between plaintiff and M & B, an escalator clause was not included for certain bituminous base course. Plaintiff alleges that when it formulated its bid it relied upon the past practices of MDOT and upon the representations made by the MDOT personnel. During performance of the contract between plaintiff and M & B, the price of bituminous base course increased significantly and thereafter plaintiff sought additional payment of approximately $65,000. MDOT, in refusing to provide a price adjustment for the bituminous base course supplied by plaintiff, relied upon the unambiguous language contained in the MDOT and M & B contract which had no provision for an escalator clause for this material.

Plaintiff instituted suit against the MDOT in the Court of Claims, seeking recovery as a third-party beneficiary of the M & B and MDOT contract. Plaintiff alleged that, although the escalator clause for the bituminous base course was not part of the written contract, the inclusion of the clause was contemplated pursuant to the representations made by defendant and by custom in the industry. Plaintiff also claimed that it should recover on an unjust enrichment theory.

Defendant filed a motion for summary judgment pursuant to GCR 1963, 117.2(1). The issue turns on whether plaintiff’s complaint stated a claim for which relief could be granted. Plaintiff apparently had made no claim against M & B for the bituminous base cost increase. The explanation for its conduct in this regard is immaterial as it is not before this Court and was not addressed below.

Following oral argument, the trial court granted *429 defendant’s motion for summary judgment. Thereafter plaintiff filed a motion to amend its complaint. In a written opinion and order, the trial court denied plaintiffs motion as the allegations set forth in the amended complaint were essentially the same as those set forth in the original complaint.

Plaintiff appeals as of right, contending (1) that the trial court erred in granting defendant’s motion for summary judgment and (2) that error was committed when the trial court would not permit plaintiff to amend its complaint.

It is well settled that a motion for summary judgment under GCR 1963, 117.2(1) is decided with reference to the pleadings alone, accepting every well-pleaded fact as true. Anderson v Kemper Ins Co, 128 Mich App 249, 252; 340 NW2d 87 (1983). We believe that the trial court did not err in granting defendant’s motion for summary judgment.

A reading of plaintiffs original complaint reveals that it is seeking recovery under the M & BMDOT contract as a third-party beneficiary and on an unjust enrichment theory. Plaintiff was not, is not, and did not claim to be a party to that contract.

Third-party beneficiary law in Michigan is controlled by statute. MCL 600.1405; MSA 27A.1405 provides in pertinent part:

"Any person for whose benefit a promise is made by way of contract, as hereinafter defined, has the same right to enforce said promise that he would have had if the said promise had been made directly to him as the promisee.
"(1) A promise shall be construed to have been made for the benefit of a person whenever the promisor of *430 said promise has undertaken to give or to do or refrain from doing something directly to or for said person.”

The question then is whether MDOT undertook to do "something directly to or for” plaintiff such that plaintiff can be properly considered a party "for whose benefit a promise is made”.

This Court and the Supreme Court have applied the third-party beneficiary statute in a variety of contexts. There appears to be no case with facts closely analogous providing a clear-cut answer to whether plaintiff is a third-party beneficiary. The law, however, clearly states that an objective standard is to be used which discerns the parties’ intentions from the contract itself. Therefore the parties’ motives and subjective intentions are not relevant in determining whether plaintiff is a third-party beneficiary. Guardian Depositors Corp v Brown, 290 Mich 433; 287 NW 798 (1939); Jachim v Coussens, 88 Mich App 648; 278 NW2d 708 (1979); Local 80 Sheet Metal Workers International Ass’n, AFL-CIO v Tishman Construction Corp, 103 Mich App 784; 303 NW2d 893 (1981). Not everyone who benefits in some way from a contract can be classified as a third-party beneficiary so as to be able to stand in the promisee’s shoes and recover under the contract. In Greenlees v Owen Ames Kimball Co, 340 Mich 670, 676; 66 NW2d 227 (1954), the Supreme Court quoted approvingly from 12 Am Jur, Contracts, § 282, p 834:

"The principle that one not a party or' privy to a contract but who is the beneficiary thereof is entitled to maintain an action for its breach is not so far extended as to give to a third person who is only indirectly and incidentally benefited by the contract the right to sue upon it. An incidental beneficiary has no rights under the contract. A third person cannot maintain an action upon a simple contract merely because he would receive *431 a benefit from its performance or because he is injured by the breach thereof. Where the contract is primarily for the benefit of the parties thereto, the mere fact that a third person would be incidentally benefited does not give him a right to sue for its breach.”

In

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Robert Murray v. Chesapeake Energy Corp
Michigan Court of Appeals, 2020
Patrick J McCourt v. Kenneth C Fowler
Michigan Court of Appeals, 2015
First Security Savings Bank v. Aitken
573 N.W.2d 307 (Michigan Court of Appeals, 1998)
Dynamic Construction Co. v. Barton Malow Co.
543 N.W.2d 31 (Michigan Court of Appeals, 1995)
Roberts v. General Motors Corp.
643 A.2d 956 (Supreme Court of New Hampshire, 1994)
Schafer Oil Co. v. Universal Underwriters Insurance
820 F. Supp. 321 (E.D. Michigan, 1993)
Paul v. Bogle
484 N.W.2d 728 (Michigan Court of Appeals, 1992)
Allstate Insurance v. Keillor
476 N.W.2d 453 (Michigan Court of Appeals, 1991)
Downriver Internists v. Harris Corp.
929 F.2d 1147 (Sixth Circuit, 1991)
Downriver Internists v. Harris Corporation
929 F.2d 1147 (Sixth Circuit, 1991)
Cochran v. Ernst & Young
758 F. Supp. 1548 (E.D. Michigan, 1991)
Grand Blanc Landfill, Inc v. Swanson Environmental, Inc
463 N.W.2d 234 (Michigan Court of Appeals, 1990)
Rhodes v. United Jewish Charities of Detroit
459 N.W.2d 44 (Michigan Court of Appeals, 1990)
Alden State Bank v. Old Kent Bank-Grand Traverse
446 N.W.2d 599 (Michigan Court of Appeals, 1989)
L Loyer Construction Co. v. City of Novi
446 N.W.2d 364 (Michigan Court of Appeals, 1989)
Kathleen Taggart v. United States
880 F.2d 867 (Sixth Circuit, 1989)
Smith v. First National Bank & Trust Co.
440 N.W.2d 915 (Michigan Court of Appeals, 1989)
77th District Judge v. State
438 N.W.2d 333 (Michigan Court of Appeals, 1989)
Stillman v. Goldfarb
431 N.W.2d 247 (Michigan Court of Appeals, 1988)
Frick v. Patrick
419 N.W.2d 55 (Michigan Court of Appeals, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
357 N.W.2d 62, 136 Mich. App. 425, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rieth-riley-construction-co-v-department-of-transportation-michctapp-1984.