Riddell v. Peck-Williamson Heating & Ventilating Co.

69 P. 241, 27 Mont. 44, 1902 Mont. LEXIS 83
CourtMontana Supreme Court
DecidedJune 23, 1902
DocketNo. 1,419
StatusPublished
Cited by25 cases

This text of 69 P. 241 (Riddell v. Peck-Williamson Heating & Ventilating Co.) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Riddell v. Peck-Williamson Heating & Ventilating Co., 69 P. 241, 27 Mont. 44, 1902 Mont. LEXIS 83 (Mo. 1902).

Opinion

MB. JUSTICE PIGOTT

delivered the opinion of the court.

• This action was brought on a contract to recover judgment for $9,312.96, besides interest. The plaintiffs recovered a judgment for $9,743.67, with costs. From it and an order refusing a new trial, the defendant prosecutes these appeals.

[54]*54■Riddell and Suiter were eo-partners. Suiter, in bis own name, but for tbe benefit of the firm, on August 5, 1895, entered into a contract with the executive board of the state agricultural college for the erection by him of ceidain buildings. Thereafter the defendant (a corporation) and the executive board miada a contract by which the defendant agreed to install a heating and ventilating plant in the buildings. Subsequently, and on August 15-, 1896, Suiter, in his own namej but for the partnership', entered into a contract, which was reduced-to writing, and subscribed by the parties as follows:

“Bozeman, Mont., August 15th, 1896. Agreement entered into this date by and between Charles Suiter, of Helena, Montana, general contractor for furnishing the material and building the buildings for the Montana State Agricultural College, Bozeman, Montana, the party of the first part, and the Peck-Williamson Heating and Ventilating Company, Cincinnati, Ohio, party of the second part. - The party of the first part agrees to furnish all the extra material and do all the extra labor that is now not contracted for in general contract for buildings that is necessary toi install the heating, ventilating, and sanitary apparatus of the party of the second part in the Montana State Agricultural College Buildings, Bozeman, Montana. All material and labor party of the first part furnishes party of the second' part to be paid for by party of the second part according to the following schedule of prices:” the remainder of the instrument being devoted to the rules for measi-uring the work, the description of the material to be used, and the schedule of prices. The contract does not expressly provide when payment shall be made.

Prior to June 22, 1897, the plaintiffs had performed labor and furnished material under the terms of the contract, which, according to the schedule of prices, amounted to $9,312.96, and which entered into and became parts of the buildings, and cannot be removed. Prom that day they ceased work, and have never done anything further under .the contract. They abandoned it because the defendant refused to> pay for the labor and material already per[55]*55formed and furnished, and were unable to proceed for lack of funds. They left undone work amounting to- $2,227.67. Their second amended complaint purports to state two causes of action. The first cause of action is based upon the written contract. They allege performance thereunder to- the extent of $0,312.96, and refusal by the defendant to pay, and .aver that at the time the written contract was signed there was an oral agreement that payments should be made as the labor and material were done and furnished and measured in the buildings and approved by the architect or by.the defendant; that a local.usage or custom to that effect was in existence, and that the written contract was made with reference thereto, and with the intention that the usage and custom ivere to control its interpretation. In the second cause of action the plaintiffs counted upon the furnishing of the material and upon the doing of the labor mentioned at the request of the defendant, and alleged the value thereof to be $9,312.96; in short, a quantum meruit and valebat count.

1. Can the action be maintained upon the special contract ? The defendant contends that it was prematurely brought. Upon its face the contract is entire, and the consideration single. The intention of the parties, as disclosed and evidenced by the terms of their engagement reduced to writing, ivas that the defendant should not become indebted to Suiter unless and until he furnished all the material and did all the labor specified in the contract. There was in the contract no time expressly appointed for payment, but the law made the price due and payable upon complete performance by Suiter or his firm. Substantial performance by Suiter of his promises ivas a condition precedent to the company’s liability under the express contract to pay the whole or any part of the consideration. (Franklin v. Schultz, 23 Mont. 165, 57 Pac. 1037.) The fixing of prices upon the different items did not operate as a severance (Isaacs v. McAndrew, 1 Mont. 437) ; it ivas a mere means of ascertaining the total compensation to be paid in the event Suiter executed the undertaking.

The plaintiffs alleged that at the time the written contract [56]*56was made an oral agreement was entered into that payments should be made, in conformity with a usage and custom, as the work was done and the material furnished and measured to the approval of the architect or of the defendant, and that the contract was made with reference to such usage and custom, and with the intention that the interpretation of the contract should be controlled thereby. We doubt whether the evidence was sufficient to establish either such alleged oral agreement or such alleged usage or custom. For the purposes of these appeals, let the sufficiency of the evidence be assumed; let it be assumed that the oral agreement accompanied the making of the written contract,' and that such a custom as the one pleaded then existed; and let it further be assumed that, the customj and oral agreement being proved, payments as the work progressed was a condition precedent to plaintiffs’ obligation to complete the terms of the written contract This evidence tended to prove a severance sub modo or an apportionment; and, if payments were to be made according to- custom or as orally agreed, then a cause of action accrued as soon as the defendant failed to make a payment when it should have been made. Default in making such payment would have entitled the plaintiffs, if they continued to perform under the contract, to recover judgment for the price of the Work already done; or such default would have warranted them; in treating the special contract as at an end, and authorized them to maintain an action on the implied promise of the defendant to pay the reasonable worth of the labor done and material furnished. They could, at their option, have pursued either course. Was the evidence admissible over the objections interposed by the defendant? Its competency was seasonably challenged by objections and motions to strike on the ground that the plaintiffs- sought thereby to alter or contradict the terms of the written contract; to the overruling of these the defendant reserved exceptions. Section 3132 of the Code of Civil Procedure, which declares a common-law rule (Gaffney Mercantile Co. v. Hophins, 21 Mont. 13, 52 Pac. 561), provides that: “When the terms of an agreement have been reduced to writing by the parties, it is to be considered as containing all those terms, and therefore there [57]*57pan be between the parties and their representatives, or successors in interest, no; evidence of the terms of the agreement other than the contents of the writing, except in the following cases: (1) Where a-mistake or imjperfection of the writing is put in issue by the pleadings. (2) Where the validity of the agreement is the fact in dispute. But this section does not exclude other evidence of the circumstances under which the agreement Avas made, or to Avhich it relates, as defined in Section 3136, or to explain an extrinsic ambiguity, or to establish illegality or fraud.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Western Plumbing of Bozeman v. Garrison
556 P.2d 520 (Montana Supreme Court, 1976)
Figgins v. Stevenson
517 P.2d 735 (Montana Supreme Court, 1973)
Heckman and Shell v. Wilson
487 P.2d 1141 (Montana Supreme Court, 1971)
Davison v. Casebolt
461 P.2d 2 (Montana Supreme Court, 1969)
Lake v. Emigh
190 P.2d 550 (Montana Supreme Court, 1948)
Brown v. Homestake Exploration Co.
39 P.2d 168 (Montana Supreme Court, 1934)
Continental Oil Co. v. Bell
21 P.2d 65 (Montana Supreme Court, 1933)
Mahas v. Kasiska
276 P. 315 (Idaho Supreme Court, 1928)
Clifton, Applegate & Toole v. Big Lake Drain District No. 1
267 P. 207 (Montana Supreme Court, 1928)
Swan v. Le Clair
251 P. 155 (Montana Supreme Court, 1926)
Schreiner v. Deep Creek Stock Ass'n
217 P. 663 (Montana Supreme Court, 1923)
Jeffers v. Montana Power Co.
217 P. 652 (Montana Supreme Court, 1923)
Cook v. Northern Pacific Ry. Co.
203 P. 512 (Montana Supreme Court, 1921)
Clarke v. Johnson
187 P. 510 (Nevada Supreme Court, 1920)
Roberts v. Sinnott
177 P. 252 (Montana Supreme Court, 1918)
De Young v. Benepe
176 P. 609 (Montana Supreme Court, 1918)
Waite v. Shoemaker & Co.
146 P. 736 (Montana Supreme Court, 1915)
Noell v. Tennessee Eastern Power Co.
130 Tenn. 245 (Tennessee Supreme Court, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
69 P. 241, 27 Mont. 44, 1902 Mont. LEXIS 83, Counsel Stack Legal Research, https://law.counselstack.com/opinion/riddell-v-peck-williamson-heating-ventilating-co-mont-1902.