Richmond MacHinery Co. v. Bennett

229 P. 1098, 48 Nev. 286, 1924 Nev. LEXIS 30
CourtNevada Supreme Court
DecidedNovember 3, 1924
Docket2636
StatusPublished
Cited by4 cases

This text of 229 P. 1098 (Richmond MacHinery Co. v. Bennett) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Richmond MacHinery Co. v. Bennett, 229 P. 1098, 48 Nev. 286, 1924 Nev. LEXIS 30 (Neb. 1924).

Opinions

It was duty of court to order consolidation. All liens should be disposed of in one action. Law contemplates all claimants shall be brought in and their rights determined in one proceeding. Rev. Laws, 2224; Lonkey v. Well, 16 Nev. 277; Daly v. Lahontan Mines Co., 39 Nev. 29.

Lien must be filed not later than fifty days after delivery of material. Rev. Laws, 2217. Period runs from date when last item is actually delivered, regardless of anything else. 27 Cyc. 140; Beatty v. Mills, 45 P. 468.

Complaint and lien notice conveyed impression material was delivered in September when in truth it was delivered in June, plainly violating Rev. Laws, 2217, and misleading plaintiffs to their prejudice.

Though lien law should be liberally construed, being creature of statute, compliance with its terms is required. Daly v. Lahontan Mines Co., supra. Lien cannot be enforced if statement therein is untruthful. Santa Monica v. Hege, 51 P. 555. *Page 288

Respondent claimed as materialman in lien notice, complaint, and in testimony, and cannot claim as contractor for first time in this court. One who delivers or installs material for another is materialman. Caulfield v. Polk, 46 N.E. 932; Pubh v. Moxley, 128 P. 1039. Lien statutes should be liberally construed. Substantial compliance only is required. Aim is to do justice to all. Lamb v. Mining Co., 37 Nev. 9; Ferro v. Bargo Co., 37 Nev. 135.

Consolidation of liens is in discretion of court. Rev. Laws, 2224; Lonkey v. Wells, Elliott v. Ivers, and Daly v. Lahontan M. Co., cited, do not present question of consolidation, and are not applicable.

Pulley in question was not carried in stock, but was stripped from another engine as an accommodation to appellants, and on special agreement that it should be replaced by one from factory and charged for at costs of replacement, freight, etc. It does not lie in mouth of appellants now to deny terms of special contract made at their solicitation and for their accommodation. Contract was not completed until new pulley was received and installed and bills and charges known. Allegation not denied is admitted. Even finding of fact will not prevail against admission in answer. Nosler v. Haynes, 2 Nev. 56.

Time runs either from last physical delivery or date of completion of contract, depending upon whether one is materialman or contractor. Respondent was original contractor dealing directly with owner, and was entitled to fifty days after completion of contract. Salt Lake Hdw. Co. v. Chainman etc. Co., 128 Fed. 509.

Special contracts may be entered into, disassociated from actual delivery, which govern the date from which the time begins to run. Marble v. Jones Co., 28 N.W. 309; Gordon Hdw. Co. v. San Francisco etc. Co., 65 P. 125.

Owner having knowledge of improvement being made must post notice of nonresponsibility and cannot rely on *Page 289 provision of recorded lease or contract with occupant to protect him. Rev. Laws, 2221; Ah Louis v. Harwood, 74 P. 741; Pac. Sash and Door Co. v. Bumiller, 124 P. 230. Method prescribed is exclusive. Rosina v. Trowbridge, 20 Nev. 105; Gould v. Wise,18 Nev. 253.

OPINION
This is an appeal from a judgment foreclosing a mechanic's lien and from an order denying a motion for a new trial.

1. The first error assigned is that the lien statement was not filed within the time provided by law. The defendants were engaged in operating a mill, and while so engaged found it necessary to procure a friction clutch pulley. Their representatives went to Salt Lake City and called at plaintiff's place of business to procure the pulley. The plaintiff had none in stock, and informed them that it would take from 60 to 90 days to get one from the factory. Defendants were anxious to get the pulley at once, and induced the plaintiff to take one from an engine equipped with such a pulley and to order another from the factory to replace the one so taken, with the understanding that upon its arrival it should be placed upon the engine in lieu of the one taken off and shipped to defendants, and that defendants would pay plaintiff the price of the new pulley, plus the expense of transportation and installation. With this understanding the defendants received the pulley so taken off the engine in June, 1920. The plaintiff received the new pulley, and had it placed on the engine September 15, 1920, at which time the defendants were charged with the pulley and all expenses as agreed. The lien statement was filed within the 50-day period provided by statute from September 15, but not within 50 days after the pulley taken from the engine was received by the defendants; hence the contention made.

The section (2217, Rev. Laws), pursuant to which *Page 290 the lien statement was filed, reads: "* * * Every person claiming the benefit of this chapter shall, not earlier than ten days after the completion of his contract, or the delivery of material by him, or the performance of his labor, as the case may be, and not later than fifty days after filing of the owner or other person as aforesaid of the affidavit hereinbefore provided for, or within fifty days after the performance of any labor in a mining claim, file for record" with the county recorder his lien statement.

2. On the part of the plaintiff it is contended that the time in which to file the lien did not begin to run until the completion of the contract under which the pulley was taken from the engine (which was on September 15), and hence the lien statement was filed within the time limit provided by the statute. We think the contention of the plaintiff should be sustained. The statute clearly contemplates one of three contingencies upon which a lien statement may be filed: (1) The completion of the contract; (2) the delivery of the material; and (3) the performance of labor. In the instant case, in the very nature of things, the plaintiff could not be in a position to file its lien statement until after the new pulley had been received and put upon the engine, for, until that was done, it could not tell what the expense would be. If we are to give the lien statute a liberal construction, as we must, there is no escaping this view. Certainly no lien statement could have been filed until the amount due was ascertainable, and, in the circumstances of this case, that was utterly impossible until the pulley taken off the engine had been replaced. A case sustaining this view is that of Marble v. Jones etc., 19 Neb. 732,28 N.W. 309. That was a case in which a contractor went to a lumber dealer and took several pieces of lumber with the understanding that he might return them, but if he decided to keep them he would notify the company to that effect, when he could be charged with them. At the end of several days he decided to keep the lumber, so notified the company, and directed that he be charged with them, which was done on the day it received word so *Page 291 to do. The lien statement was filed within the time allowed by statute from the date of the charge, but not within the time allowed from the date the lumber was taken. The court held that the lien was filed within time, saying:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nichols v. Levy
32 P.2d 120 (Nevada Supreme Court, 1934)
Holtzman v. Bennett
229 P. 1095 (Nevada Supreme Court, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
229 P. 1098, 48 Nev. 286, 1924 Nev. LEXIS 30, Counsel Stack Legal Research, https://law.counselstack.com/opinion/richmond-machinery-co-v-bennett-nev-1924.