Richards v. Harman

617 S.E.2d 556, 217 W. Va. 206, 2005 W. Va. LEXIS 53
CourtWest Virginia Supreme Court
DecidedJune 10, 2005
Docket31942
StatusPublished
Cited by8 cases

This text of 617 S.E.2d 556 (Richards v. Harman) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Richards v. Harman, 617 S.E.2d 556, 217 W. Va. 206, 2005 W. Va. LEXIS 53 (W. Va. 2005).

Opinion

Justice MAYNARD delivered the Opinion of the Court.

MAYNARD, Justice:

This case is before this Court upon appeal of a final order of the Circuit Court of Tucker County entered on February 4, 2004. In that order, the circuit court refused a Petition to Discharge a Mechanic’s Lien filed by the appellants and petitioners below, Steven W. Richards, Cortland Properties, Inc., Northpoint Residential Construction, Inc., and Mid-Lake Properties, II, Inc. (hereinafter “appellants”). The appel-lee and respondent below, Robert June Har-man d/b/a Harman Equipment Sales (hereinafter “appellee”) filed the mechanic’s lien on October 22, 2003, seeking payment in the amount of $221,901.75, which included $3,000.00 for work performed on August 17, 2003, and almost $219,000.00 for work performed in the late 1980s.

In this appeal, the appellants contend that the circuit court erred by finding that the appellee has a valid mechanic’s lien in the amount of $219,000.00 for the work he performed in the 1980s. This Court has before it the petition for appeal, the entire record, and the briefs and argument of counsel. For the reasons set forth below, the final order is affirmed, in part, and reversed, in part, and this case is remanded for further proceedings consistent with this opinion.

I.

FACTS

In the late 1980s, the appellants developed a subdivision known as Northpoint in Canaan Valley, West Virginia. The appellee was hired to construct roadways, water lines, and sewage systems. The appellants made several cash payments to the appellee for his work, but eventually reached a point where they had to execute promissory notes for the remaining balance. 1

Over the years thereafter, the appellee occasionally performed additional work at Northpoint. He submitted bills for his work which were paid by the' appellants. The appellants say that the appellee never made a demand for payment of the promissory notes, nor did his billing statements indicate that any past due balance was being carried forward.

On August 17, 2003, the appellee repaired a water line adjacent to a lot in Section A of Northpoint. He submitted a bill to the appellants for $3,000.00. Upon not receiving payment, the appellee filed a Notice of Mechanic’s Lien in the county clerk’s office on October 22, 2003. The mechanic’s lien was filed for the amount of $221,901.75, with interest accruing at the rate of 1.5% per month. This amount included $3,000.00 for the work performed on August 17, 2003, and almost $219,000.00, for the unpaid balance on the promissory notes.

On December 19, 2003, the appellants filed a Petition to Discharge the Mechanic’s Lien in the Circuit Court of Tucker County. On January 26, 2004, the circuit court held a hearing during which appellant Steven Richards and the appellee testified. Thereafter, the circuit court refused the Petition to Dis *209 charge the Mechanic’s Lien. The court found that the appellee had performed work and other services to improve ten lots of real estate in Northpoint; that the appellants had failed to pay the appellee for the improvements to the lots; and that the appellee had a valid mechanic’s lien. The court further found that the lien covered all the work performed by the appellee at Northpoint since all of the work was of the same or similar type and was based on an ongoing contractual relationship between the parties. The final order was entered on February 4, 2004, and this appeal followed. 2

II.

STANDARD OF REVIEW

The ease sub judice clearly involves a question of law and an interpretation of our statutes regarding mechanics’ liens, W.Va. Code §§ 38-2-1 to -39. Accordingly, we will apply a de novo standard of review. See Syllabus Point 1, Chrystal R.M. v. Charlie A.L., 194 W.Va. 138, 459 S.E.2d 415 (1995) (“Where the issue on an appeal from the circuit court is clearly a question of law or involving an interpretation of a statute, we apply a de novo standard of review.”).

III.

DISCUSSION

As set forth above, the issue presented in this appeal is whether the appellee has a valid mechanic’s lien for work he performed in the 1980s. W.Va.Code § 38-2-1 (1991) clearly establishes that,

Every person, firm or corporation who erects, builds, constructs, alters, removes or repairs any building or other structure, or other improvement appurtenant to any such building or other structure, or who alters or improves the real property whereon the same stands, or to which it may have been removed, or who provides services for any of the foregoing, under and by virtue of a contract with the owner for such erection, building, construction, alteration, removal or repair, either for an agreed lump sum or upon any other basis of settlement and payment, shall have a lien upon such building or other structure or improvement appurtenant thereto, and upon the interest of the owner thereof in the real property whereon the same stands, or to which it may have been removed, to secure the payment of such contract price or other compensation therefor.

However,

the lien created and authorized by section one [§ 38-2-1] of this article shall be discharged from and after one hundred days from the completion of the contract ... unless, within the respective period[ ], the claimant of any such lien shall have perfected and preserved the same, as hereinafter provided in this article.

W.Va.Code § 38-2-7 (2002). 3

In this case, there is no dispute that the appellee timely preserved a mechanic’s lien for the repair work he performed in August 2003. The appellants contend, however, the lien cannot relate back to the infrastructure work the appellee completed in 1989. In that regard, the appellants argue that the lien could only relate back if work had been performed continuously by the appellee and that is not .the case here. Instead, the appellants say that the appellee completed his original contract work in 1989, and it was only a repair that brought him back to Northpoint in 2003. Accordingly, the appellants maintain that there was no continuing contract for any additional work to be completed and, therefore, no basis to relate the lien back to the work the appellee performed in the 1980s.

■The appellee responds by stating that the lien should relate back based on W.Va.Code § 38-2-16 (1991) which provides:

*210 For the purposes of this article, all materials furnished, all work done, and all services provided by any one person, firm or corporation, upon any one building or the improvements appurtenant thereto, or upon the real property whereon the same stands, or to which it may have been removed, shall be deemed and considered one contract, whether or not all of such material was bought at one time, or under one general agreement

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
617 S.E.2d 556, 217 W. Va. 206, 2005 W. Va. LEXIS 53, Counsel Stack Legal Research, https://law.counselstack.com/opinion/richards-v-harman-wva-2005.