Richard Harkleroad v. Frontier Building and Development, Inc.

CourtCourt of Appeals of Tennessee
DecidedApril 23, 2015
DocketE2013-00664-COA-R3-CV
StatusPublished

This text of Richard Harkleroad v. Frontier Building and Development, Inc. (Richard Harkleroad v. Frontier Building and Development, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Richard Harkleroad v. Frontier Building and Development, Inc., (Tenn. Ct. App. 2015).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE January 15, 2015 Session

RICHARD HARKLEROAD, ET AL. v. FRONTIER BUILDING AND DEVELOPMENT, INC.

Appeal from the Circuit Court for Knox County No. 227212 Harold Wimberly, Jr., Judge

No. E2013-00664-COA-R3-CV-FILED-APRIL 23, 2015

This appeal concerns an alleged breach of contract. Richard and Shannon Harkleroad (“the Harkleroads”) sued Frontier Building and Development, Inc. (“Frontier”) alleging faulty construction of their residence. Frontier filed a counterclaim alleging non- payment. The Circuit Court for Knox County (“the Trial Court”) found that the Harkleroads were entitled to recovery in the amount of $10,000 for construction defects to their porches and driveway. Regarding Frontier’s counterclaim, the Trial Court found that Frontier had performed work in addition to that required in the original contract and awarded Frontier $4,103.75 for this work. The Trial Court awarded neither side attorney’s fees under their contract. The Harkleroads appeal. We reverse the Trial Court as to its award of damages to Frontier and remand this case for the Trial Court to award reasonable attorney’s fees under the contract to the Harkleroads. Otherwise, we affirm the judgment of the Trial Court.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Circuit Court Affirmed, in part, and, Reversed, in part; Case Remanded

D. MICHAEL SWINEY, J., delivered the opinion of the court, in which CHARLES D. SUSANO, JR., C.J., and THOMAS R. FRIERSON, II, J., joined.

Margaret W. Vinsant, Knoxville, Tennessee, for the appellants, Richard and Shannon Harkleroad.

R. Deno Cole, Knoxville, Tennessee, for the appellee, Frontier Building and Development, Inc.1 1 Frontier filed no brief on appeal. Indeed, Frontier filed a motion to dispense with oral argument, informing this Court that the two sole stockholders and principals of Frontier had retained counsel to file a petition for Chapter 7 bankruptcy. The corporation itself, however, is not under bankruptcy protection. OPINION

Background

In October 2011, the Harkleroads sued Frontier in the General Sessions Court for Knox County for breach of contract related to Frontier’s construction work on the Harkleroads’ residence.2 The Harkleroads non-suited the case and refiled in March 2012. In April 2012, Frontier filed a counterclaim for breach of contract against the Harkleroads. The General Sessions Court heard the matter in May 2012, after which both parties appealed to the Trial Court for a de novo hearing. This case was tried in January 2013.

The Harkleroads entered into a contract (“the Contract”) with Frontier in February 2008. Under the Contract, Frontier was to build a home for the Harkleroads. The Contract was a “cost-plus” contract, with the final price to consist of the actual labor and material costs plus 15% above the actual cost of the project. Shawn Roderiques and Christian Johnson, the owners of Frontier, signed the Contract for Frontier.

Richard Harkleroad testified. Mr. Harkleroad stated that he and his wife chose Frontier to build their home because they had seen the quality of Frontier’s other work. Frontier estimated the cost of construction to be $527,275.00. The parties agreed that this figure was not set in stone. The Harkleroads visited the property regularly during the construction. The parties had a practice of making changes verbally or by email. The parties never executed any formal change orders during construction.

By October 2008, the project was running over the estimated cost by about $40,000. The Harkleroads made efforts to cut costs by, among other things, undertaking to do the landscaping and sodding themselves. Frontier did not do the landscaping in the front and backyards as was originally planned.

After moving into the house, the Harkleroads began experiencing water and flooding problems. In December 2008, the roof began leaking around the chimney causing damage in the master bedroom on the main floor and the den in the basement. The roof around the chimney was repaired by Frontier and K.C. Construction in April 2009. Additional water issues emerged. According to Mr. Harkleroad, the grading of the backyard sloping caused water problems around the back of the house. Photographs of the affected area were admitted into evidence.

Frontier has closed its operations following an unsuccessful development project. According to Frontier, this appeal is moot. We denied Frontier’s motion and now proceed to decide this appeal. 2 The record contains no transcript. We draw the background facts of this case from a Statement of Evidence. -2- In response to the Harkleroads’ request for help, Frontier installed a French drain in the backyard at no cost to the Harkleroads. This reduced the level of flooding but did not completely resolve the problem. The Harkleroads completed their final walkthrough of the home in December 2008. Mr. Harkleroad shook hands with Mr. Roderiques and Mr. Johnson and thanked them for their work. While Article 10.1 of the Contract provided a one-year builder’s warranty, Mr. Harkleroad testified that he never received any written warranty.

Shannon Harkleroad testified. The Harkleroads’ home was substantially completed in November 2008. The family moved into the house in December 2008. Mrs. Harkleroad testified that Frontier returned to the house to effect repairs multiple times through July 2009. According to Mrs. Harkleroad, a number of problems never were fixed by Frontier. In February 2010, the Harkleroads sent Frontier a letter detailing the various outstanding issues. No reply from Frontier was forthcoming. The Harkleroads had not submitted payment on the 2009 invoice from Frontier for work it did repairing the interior water damage. By the time this case was filed, there were three main problem areas with the home: the grading of the backyard, the driveway, and the front and back porches. In September 2011, in response to a letter from the Harkleroads outlining their problems, Frontier responded by denying liability or defects. Mrs. Harkleroad testified to the nature of the defects. The top layer of the driveway was disintegrating. Grout and mortar were breaking off the porches. According to Mrs. Harkleroad, she and her husband performed some landscaping but did not grade the property at any point.

Ronald Corum (“Mr. Corum”), a professional engineer, testified for the Harkleroads. Mr. Corum was qualified as an expert witness. Mr. Corum had conducted evaluations of the Harkleroads’ home. According to Mr. Corum, the porches were deteriorating and much of the grout was missing. Mr. Corum also testified to the spalling on the driveway.3 Mr. Corum did not believe that the Harkleroads were responsible for this spalling, although Mr. Corum could not say definitively what had caused the spalling. Mr. Corum testified that the driveway needed to be replaced. Regarding the grading issue, Mr. Corum testified that the grading sloped toward the house in excess of building code requirements. Mr. Corum stated that a rough grade always should be completed, and that the Harkleroads’ flooding problems mainly were a result of improper grading.

Daniel Tate Rice (“Mr. Rice”), the owner of Grand Master Concrete, testified for the Harkleroads. Mr. Rice inspected the Harkleroads’ home. According to

3 “Spalling” refers to the chipping or crumbling of rock or concrete. -3- Mr. Rice, the costs for repairs were as follows: $10,575.00 to tear out and re-do the front porch; $5,625.00 to remove the pavers and grout and finish the back porch; $7,394.00 to repair the water drainage issue; and, $17,040.00 to remove and re-pour the driveway.

Hunter Birtsch (“Mr. Birtsch”), a sales account manager for Ready Mix USA who was present when the concrete was delivered to the Harkleroads’ property, testified for Frontier. Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bogan v. Bogan
60 S.W.3d 721 (Tennessee Supreme Court, 2001)
Southern Constructors, Inc. v. Loudon County Board of Education
58 S.W.3d 706 (Tennessee Supreme Court, 2001)
Business Men's Assurance Co. of America v. Graham
891 S.W.2d 438 (Missouri Court of Appeals, 1994)
GSB Contractors, Inc. v. Hess
179 S.W.3d 535 (Court of Appeals of Tennessee, 2005)
McClain v. Kimbrough Const. Co., Inc.
806 S.W.2d 194 (Court of Appeals of Tennessee, 1990)
Loftis v. Finch
491 S.W.2d 370 (Court of Appeals of Tennessee, 1972)
Buice v. Scruggs Equipment Co.
267 S.W.2d 119 (Court of Appeals of Tennessee, 1953)
Town of Fifield v. State Farm Mutual Automobile Insurance Co.
349 N.W.2d 684 (Wisconsin Supreme Court, 1984)
Beaty v. McGraw
15 S.W.3d 819 (Court of Appeals of Tennessee, 1998)
Sholodge Franchise Systems, Inc. v. McKibbon Bros., Inc.
919 S.W.2d 36 (Court of Appeals of Tennessee, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
Richard Harkleroad v. Frontier Building and Development, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/richard-harkleroad-v-frontier-building-and-develop-tennctapp-2015.