Rhee, N. v. Brugman, A.

CourtSuperior Court of Pennsylvania
DecidedMay 17, 2023
Docket1303 EDA 2022
StatusUnpublished

This text of Rhee, N. v. Brugman, A. (Rhee, N. v. Brugman, A.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rhee, N. v. Brugman, A., (Pa. Ct. App. 2023).

Opinion

J-A28028-22

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37

NORMA RHEE AND HOON RHEE, H/W : IN THE SUPERIOR COURT OF : PENNSYLVANIA : v. : : : ADAM BRUGMAN AND 754 DARIEN : STREET, LLC, 754 DARIEN STREET, : LLC : No. 1303 EDA 2022 : : v. : : : EVOLVE BUILD, INC. AND PEDRO : PALMER CONSTRUCTION, INC. : : : APPEAL OF: 754 DARIEN STREET, : LLC :

Appeal from the Order Entered April 22, 2022 In the Court of Common Pleas of Philadelphia County Civil Division at No(s): 210600757

BEFORE: PANELLA, P.J., LAZARUS, J., and SULLIVAN, J.

MEMORANDUM BY LAZARUS, J.: FILED MAY 17, 2023

754 Darien Street, LLC (“Darien”), appeals from the order, entered in

the Court of Common Pleas of Philadelphia County, denying its motion to

compel arbitration. Upon careful review, we affirm.

This case stems from a contract entered into on May 27, 2019

(“Agreement”) between Darien, a real estate holding limited liability company,

and appellee/contractor, Evolve Build, LLC (“Evolve”) with respect to the

construction of a single-family home at 754 South Darien Street, Philadelphia. J-A28028-22

After disputes arose between the parties,1 Darien issued a 14-day notice of

default pursuant to section 13 of the Agreement.2 On January 1, 2020, Darien

terminated the Agreement. Thereafter, on June 19, 2020, Evolve filed a

mechanic’s lien claim in the Philadelphia Court of Common Pleas, claiming an

amount due from Darien of $72,129.20.

____________________________________________

1 Darien contends that Evolve breached the Agreement by, inter alia: (1) failing to provide proper documentation in support of its requests for payment by Darien; (2) not constructing the project to specifications or in a workmanlike manner; (3) failing to pay for work and materials; (4) failing to provide Darien with a budget; and (5) causing Darien to incur added repair expenses. See Brief of Appellant, at 9-11. Evolve asserts that Darien was “habitually tardy in satisfying [Evolve’s] payment applications as they came due,” as a result of which, Evolve threatened to suspend work until Darien became current in its obligations, as provided under the Agreement. Brief of Appellee, at 2.

2 Section 13 of the Agreement provides, in relevant part:

If the Contractor defaults or persistently fails or neglects to carry out the Work in accordance with the Construction Documents or fails to perform any provision of the Contract, after fourteen (14) calendar days written notice from Owners specifying the defaults, the Owners may make good such deficiencies and may deduct the actual cost of construction and materials only from the payment then or thereafter due the Contractor, or at [its] option, may terminate the Contract and take possession of the site and of all materials thereon, and may finish the work by whatever commercially reasonable methods, and if the unpaid balance of the Contract Price exceeds the direct cost of construction and materials only for finishing the Work, such excess shall be paid to the Contractor, but if such direct cost of construction and materials exceeds such unpaid balance, the Contractor shall pay the difference to the Owners. Owners’ remedy under this Article is exclusive for any failure to perform by Contractor.

Agreement, 5/27/19, at § 13.

-2- J-A28028-22

On September 20, 2021, Norma and Hoon Rhee (“Rhees”), owners of

752 South Darien Street, filed a second amended complaint bringing various

claims against Darien and Adam Brugman stemming from Darien’s

development of 754 South Darien Street, which is adjacent to the Rhees’

property. The Rhees alleged that their property had sustained damages—

including cracking, holes, water infiltration, and mold—as a result of the work

being performed on the neighboring property.

On August 31, 2021, Darien filed a joinder complaint, seeking to add

Evolve and Pedro Palmer Construction, Inc. as third-party defendants. Evolve

filed preliminary objections, arguing, inter alia, that the case must be

transferred to arbitration pursuant to the Agreement. Darien did not respond

to Evolve’s preliminary objections, but rather, filed an amended joinder

complaint on November 8, 2021, to which Evolve also preliminarily objected

on the basis of the arbitration clause. On December 20, 2021, Darien filed a

second amended joinder complaint. Evolve again filed preliminary objections

raising, inter alia, the arbitration clause. On February 3, 2022, Darien filed a

response to Evolve’s preliminary objections. On February 17, 2022, the trial

court entered an order sustaining Evolve’s preliminary objections to the

second amended joinder complaint and dismissing that complaint, with

prejudice, as to Evolve.3

3The trial court’s order did not set forth the rationale for its decision and, because the order was not a final, appealable order, did not file a Pa.R.A.P. 1925(a) opinion.

-3- J-A28028-22

On March 4, 2022, Darien filed a petition seeking to compel Evolve to

submit to arbitration pursuant to the Agreement. Evolve filed a response on

March 24, 2022, in which it asserted that: (1) Darien had waived its

arbitration claims and (2) Darien’s claims are precluded by the doctrine of res

judicata. On April 21, 2022, the trial court dismissed the petition, but did not

specify the grounds on which it denied relief. Darien filed a timely notice of

appeal, followed by a court-ordered Pa.R.A.P. 1925(b) concise statement of

errors complained of on appeal. Darien raises the following claims for our

review:

1. Did the court err by denying [Darien’s] petition to compel arbitration where 42 Pa.C.S.[A.] § 7304(a) requires the court to order the parties to proceed with arbitration where, as here, a valid agreement to arbitrate has been shown and the party opposing the petition has refused to arbitrate?

2. Did the court err in concluding that there was not a valid agreement to arbitrate [] between the parties?

3. Did the court err when it failed to determine that Evolve [] refused to arbitrate the matter where, inter alia, Evolve specifically raised the issue as to the validity of a binding arbitration agreement that required the court to refer the matter to arbitration in its preliminary objections to [] Darien’s joinder complaint?

4. Did the court err in concluding that [] Darien did not have a valid claim against Evolve that could be subjected to arbitration?

5. Did the court err in concluding that the dispute between [] Darien and Evolve was not within the scope of the arbitration agreement?

6. Did the court err in concluding that [] Darien did not make or waived any counter-argument to appellee’s claim of untimeliness when [] Darien raised the issue—that procedural questions such as the propriety or timeliness of invocation of the arbitration

-4- J-A28028-22

provision must be resolved by the arbitrators—in its petition to compel arbitration at [¶] 22?

7. Did the court err where it made a determination on the merits that [] Darien’s claim against Evolve arose in January 2020, and that [] Darien waived its right to enforce the arbitration agreement where [] Darien’s claim against Evolve cannot arise until the measure of damages for the claimed breach is known to [] Darien under the terms of Section 13 (pp. 11-12) of the Construction Agreement between the parties.

Brief of Appellant, at 5-6 (unnecessary capitalization omitted).

Prior to addressing the claims Darien raises on appeal, we must first

determine whether it has preserved for appellate purposes the sole issue

Free access — add to your briefcase to read the full text and ask questions with AI

Related

At&T Technologies, Inc. v. Communications Workers
475 U.S. 643 (Supreme Court, 1986)
Ryan v. Johnson
564 A.2d 1237 (Supreme Court of Pennsylvania, 1989)
Commonwealth v. Yi De Zheng
908 A.2d 285 (Superior Court of Pennsylvania, 2006)
Goral v. Fox Ridge, Inc.
683 A.2d 931 (Superior Court of Pennsylvania, 1996)
Hess v. Fox Rothschild, LLP
925 A.2d 798 (Superior Court of Pennsylvania, 2007)
Midomo Co. v. Presbyterian Housing Development Co.
739 A.2d 180 (Superior Court of Pennsylvania, 1999)
Commonwealth v. Poncala
915 A.2d 97 (Superior Court of Pennsylvania, 2006)
Ross Development Co. v. Advanced Building Development, Inc.
803 A.2d 194 (Superior Court of Pennsylvania, 2002)
Commonwealth v. DeJesus
868 A.2d 379 (Supreme Court of Pennsylvania, 2005)
Del Ciotto v. Pennsylvania Hospital of the University of Penn Health System
177 A.3d 335 (Superior Court of Pennsylvania, 2017)
Smay v. E.R. Stuebner, Inc.
864 A.2d 1266 (Superior Court of Pennsylvania, 2004)
Fulano, J. v. Fanjul Corp.
2020 Pa. Super. 166 (Superior Court of Pennsylvania, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
Rhee, N. v. Brugman, A., Counsel Stack Legal Research, https://law.counselstack.com/opinion/rhee-n-v-brugman-a-pasuperct-2023.