Reyes v. United States of America

District Court, D. Guam·Decided September 30, 2013·No. 1:08-cv-00005·Unknown

Opinion

DISTRICT COURT OF GUAM TERRITORY OF GUAM

JESSE JAMES CRUZ REYES, CIVIL CASE NO. 08-00005 Plaintiff, ORDER vs.

UNITED STATES OF AMERICA, et al.,

Defendants.

The court accepts and adopts the Magistrate Judge’s Report and Recommendation dated February 21, 2013 (ECF No. 179). The court hereby GRANTS IN PART Defendants’ Motion to Dismiss and GRANTS Defendants’ Motion for Summary Judgment. This is a tort action in which Plaintiff Jesse James Cruz Reyes seeks damages for injuries caused by his fall from a scaffold while working for a contractor on a project at Naval Base Guam. A. Factual Background Naval Facilities Engineering Command Pacific (“NAVFAC”) entered into a contract with Dick Pacific Construction Co., Ltd. (“Dick Pacific”) to make improvements to the Fena Water Treatment Plant (“Fena Project”) at Naval Base Guam. Jesse James Cruz Reyes (“Plaintiff”) was employed as a laborer by Dick Pacific to work on the Fena Project. On May 17, 2006, Plaintiff was assigned to work on the wall gang form at Filter Back Wash Settling Tank #2 (“Tank #2”). While descending a scaffold, which was provided by Dick Pacific, Plaintiff fell approximately fifteen (15) feet to the concrete floor of Tank #2. There were no direct witnesses of Plaintiff’s fall despite there being two other Dick Pacific employees and two employees of a subcontractor in the immediate area at that time. The scaffold from which Plaintiff fell was initially assembled with two tiers. Between May 16, 2006 and the time of Plaintiff’s fall on May 17, 2006, the scaffold was refashioned to

three tiers. At the time of Plaintiff’s fall, the mid-rail at the access point of the top platform was missing, and the toggle pins that hold the mid-rail in place were either facing the wrong direction or in the open position. The scaffold had not been tagged as unsafe to use. In its investigation report of the accident, Dick Pacific concluded that the direct cause of Plaintiff’s fall was “failure to secure the mid-rail in place” and the indirect cause was “failure to follow scaffold erection procedures, which requires the presence of a competent person during erection, dismantling, or alterations.” A report by NAVFAC determined that the root cause of the accident was that the “[s]caffold and associated components were not inspected and certified for use by a Competent Person.” B. Relevant Procedural Background

On January 5, 2011, approximately thirty-two (32) months after filing his initial Complaint, Plaintiff filed a Third Amended Complaint (“TAC”), which named as defendants the United States of America, the Department of the Navy, and Defendants Doe 1–98. See ECF No. 81. The TAC alleges three causes of actions: Count I – Negligence, Count II – Defective Design, Manufacture, and/or Assembly and Failure to Warn, and Count III – Negligent and Intentional Infliction of Emotional Distress. The United States and Department of the Navy (collectively “Defendants” or “Government”) filed their Answer on January 19, 2011. See ECF No. 82. On July 25, 2011, Defendants filed a Motion to Dismiss the TAC. See ECF No. 96. Defendants argue that the court lacks subject matter jurisdiction because: (1) the independent contractor’s exception to the Federal Tort Claims Act (“FTCA”) precludes claims by employees of independent contractors against the Government; (2) availability of worker’s compensation benefits bars recovery against the Government; and (3) the discretionary function exception to the FTCA precludes liability. Additionally, Defendants argue that the emotional distress claim

should be dismissed for failure to state a claim. On August 23, 2011, Plaintiff filed his Opposition to the Motion to Dismiss. See ECF No. 108. Plaintiff argues that the independent contractor exception is not applicable in the instant action; that under Guam law, worker’s compensation benefits are not an exclusive remedy and does not bar suit against the Government; and that the discretionary function exception did not preclude Government liability under the facts of the instant case. Defendants filed the Reply on September 6, 2011. See ECF No. 119. The Motion to Dismiss was referred to the Magistrate Judge for a Report and Recommendation. See ECF No. 137. On January 4, 2012, Defendants filed a Motion for Summary Judgment. See ECF No. 152. Defendants allege that subsequent discovery, and clarification that Plaintiff’s theory of

liability is direct negligence of the Government rather than vicarious liability for the negligent acts of Dick Pacific, demonstrates that there are no genuine issues of any material fact. On February 2, 2012, Plaintiff filed an Opposition and Amended Opposition. See ECF Nos. 157 and 159. On February 15, 2012, Defendants filed the Reply. See ECF No. 165. The Motion for Summary Judgment was referred to the Magistrate Judge for a Report and Recommendation. See ECF No. 154. On April 10, 2012, the Magistrate Judge heard arguments on the motions and took the motions under advisement. See ECF No. 173. The Magistrate Judge issued the Report and Recommendation (“R&R”) on February 21, 2013. See ECF No. 179. In the R&R, the Magistrate Judge concluded: (1) the motion to dismiss should be granted in part as the discretionary function exception is available as a defense to Defendants with respect to the allegations referenced in paragraphs 26, 28, and 29 of the TAC; and (2) the motion for summary judgment should be granted because the pleadings show that there is no dispute as to any material fact and Defendants are entitled to judgment as a matter of law as to all counts of the TAC. Id. at 32–33.

Plaintiff filed an Objection to the R&R on March 7, 2013. See ECF No. 180. Therein, Plaintiff contends that the R&R “wrongly concluded that Defendants owed no duty to provide a safe work environment to Plaintiff or to warn him of the danger of the scaffold.” Id. at 1. Defendants filed their Response to the Objection on April 29, 2013. See ECF No. 183. The court has jurisdiction to hear this matter pursuant to 28 U.S.C. § 1331 for Plaintiff’s claims under the Federal Tort Claims Act, 28 U.S.C. § 1346(b). Venue is proper in this judicial district, the District of Guam, because all of the events or omissions giving rise to Plaintiff’s claims occurred here. See 28 U.S.C. § 1391.

Free access — add to your briefcase to read the full text and ask questions with AI

Reyes v. United States of America, (gud 2013).

Reyes v. United States of America (Reyes v. United States of America) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

First Nat. Bank of Ariz. v. Cities Service Co.
391 U.S. 253 (Supreme Court, 1968)
United States v. Raddatz
447 U.S. 667 (Supreme Court, 1980)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Tomaiolo v. Mallinoff
281 F.3d 1 (First Circuit, 2002)
Kathlyn M. Kennedy v. Applause, Inc.
90 F.3d 1477 (Ninth Circuit, 1996)
Zamudio v. City and County of San Francisco
82 Cal. Rptr. 2d 664 (California Court of Appeal, 1999)
Kinney v. CSB Construction, Inc.
103 Cal. Rptr. 2d 594 (California Court of Appeal, 2001)
Mann v. McAtee
37 Cal. 11 (California Supreme Court, 1869)
People v. Bunn
37 P.3d 380 (California Supreme Court, 2002)