Revett v. Globe Navigation Co.

123 P. 459, 68 Wash. 300, 1912 Wash. LEXIS 1285
CourtWashington Supreme Court
DecidedApril 30, 1912
DocketNo. 9535
StatusPublished
Cited by3 cases

This text of 123 P. 459 (Revett v. Globe Navigation Co.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Revett v. Globe Navigation Co., 123 P. 459, 68 Wash. 300, 1912 Wash. LEXIS 1285 (Wash. 1912).

Opinion

Crow, J.

This action, which was commenced by Ben Stanley Revett against Globe Navigation Company, Ltd., a corporation, to recover damages for the breach of a charter party agreement, has heretofore been in this court, 56 Wash. 550, 106 Pac. 176. After remittitur, a new trial was had, and findings, to which the plaintiff excepted, were made as follows:

“(1) That heretofore and on to wit: the 27th day of May, 1905, plaintiff and defendant entered into a contract of affreightment in words and figures set forth in paragraph 2 of plaintiff’s complaint herein, which said contract, among other things, contained, the following clause:
“ ‘Dangers of the sea. Fire, explosion, bursting of boilers and pipes, breakage of shaft, latent defects in boilers, pipes, machinery or hull, stranding, collision at sea, restraints of Princes or rulers, strikes and all other unavoidable accidents excepted.’
“(2) That the freight agreed to be delivered and delivered to the steamship Tampico on or before June 1st, was duly accepted by the defendant and1 shipped, in accordance with said contract.
“(3) That on the 27th day of May, 1905, the time when the said contract between plaintiff and defendant was entered into, the steamship Eureka was not at the Port of Seattle, but was then engaged in a voyage from the Port of Seattle to ports in California and return to the Port of Seattle.
“(4) That said steamship Eureka returned to the Port of Seattle at 3 a. m. on June 20th, 1905, and that upon her return the defendant discovered certain latent defects in her boilers which were not known and could not have been discovered by the exercise of ordinary diligence at the time of the making of said contract of affreightment, which said de[302]*302fects rendered said steamship Eureka unseaworthy to undertake a voyage to Nome, Alaska, and return without extensive repairs being made to her said boilers; that her said condition, immediately upon the arrival in Seattle, was reported to the agent of plaintiff in the city of Seattle and also communicated to plaintiff, and the balance of the lumber was shipped north on an available vessel leaving the port of Seattle after said June 20th, 1905, and that the remainder of the cargo, to wit: certain machinery, went north on the second sailing of the steamship Tampico; that said cargo was shipped as aforesaid.
“(5) That until the return of the Eureka to Seattle on June 20th, 1905, defendant had no opportunity to discover the said defects in her boilers or to make repairs to the same, and did send a portion of said cargo on the steamship Olympia, and the balance on the steamship Tampico. To have shipped said cargo forward on the Eureka at the time specified in said contract would have jeopardized vessel and freight.”

Upon these findings, the trial judge held that the relation of carrier was not actually assumed by defendant; that it was entitled to the exemptions from liability contained in the clause set forth in finding one;' and that, owing to the condition of the boilers of the Eureka at the time she was to have sailed, the defendant was excused from taking plaintiff’s freight. Thereupon the action was dismissed, and the plaintiff has appealed.

Other portions of the charter party then considered material were quoted in our former opinion, but we did not then quote the clause providing for exceptions from perils of the sea etc., as it was not then under consideration. The cause is now before us for trial de novo, and two controlling questions are presented: (1) Did the exception clause exempt respondent from performing its contract? and (2) if it did not, what damages is appellant entitled to recover?

Findings requested by appellant and refused by the trial judge need not be here set forth, as we will state our own findings. The charter party, which was executed on May 27, 1905, called for two sailings by respondent’s steamships, [303]*303one by the Tampico on or about June 1, 1905, and one by the Eureka on or about June 15, 1905. The first was made, but the second was abandoned. Respondent contracted to have the steamship Eureka at the port of Seattle on or about June 15, 1905, in seaworthy condition ready to receive and carry appellant’s freight. In the absence of any express stipulation to the contrary, the charter party carried an implied warranty on the part of respondent that the ship would then be in fit condition for the voyage. 3 Kent, Commentaries, 205.

The evidence shows that, on or about May 26, 1905, the steamship Eureka sailed for San Pedro, California, with a cargo of lumber and railroad ties; that she returned to Seattle with a cargo of cement, arriving about June 20, 1905; that during the voyage difficulties had arisen with her boilers, causing them to leak; that she was not then in fit condition to safely proceed on the contemplated voyage to Nome; that her boilers could have been thoroughly repaired within ten days, which would have enabled her to sail about July 1, 1905; that, instead of so repairing them, respondent, on June 21, contracted with the Pacific Coast Company, to carry a cargo of coal to San Francisco; that temporary repairs, requiring about two days, were made so that the ship might proceed to San Francisco; that while such temporary repairs were being made, the vessel was being loaded with coal, and that she went upon the San Francisco and Seattle run where she continued' for several months before permanent repairs were made.

Respondent contended, and the trial court held, that the exception clause applied to defects that occurred after the execution of the contract, and while the Eureka was at sea on the San Pedro voyage. Appellant contends that the exceptions applied only to such perils of the sea, defects in boilers, etc. as might occur after actual commencement of the contracted voyage from Seattle to Nome. Under the law and evidence, we conclude that appellant’s contention • must be [304]*304sustained. Commenting on such exceptions in a charter party contract, Carver in the fourth edition of his treatise on Carriage by Sea, at § 148, says:

“But it seems that the exceptions do not apply to matters which may happen before the ship has entered upon the voyage dealt with by the charter party. So that if she were disabled by perils of the sea while still completing a voyage on which she was engaged at the time of chartering, the shipowner would not be excused by the exceptions.”

The same doctrine has in effect been announced in this ■ country. The Caledonia, 157 U. S. 124; The Carib Prince, 170 U. S. 655; The Indrapura, 178 Fed. 591. Under the charter party, it was respondent’s duty to have the steamship at Seattle on or about June 15, 1905, in fit condition to receive appellant’s freight and carry the samé to Nome. If respondent did not intend to assume liability for any possible breach of its contract that might result from accidents or injuries to the steamship during a previous voyage, it should have contracted against such liability. This it did not do. In The Caledonia, supra, the supreme court of the United States said:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Silverdale Hotel Associates v. Lomas & Nettleton Co.
677 P.2d 773 (Court of Appeals of Washington, 1984)
People v. Superior Court
178 P.2d 1 (California Supreme Court, 1947)
Boston Trust Co. v. Evelon Co.
164 P. 606 (Washington Supreme Court, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
123 P. 459, 68 Wash. 300, 1912 Wash. LEXIS 1285, Counsel Stack Legal Research, https://law.counselstack.com/opinion/revett-v-globe-navigation-co-wash-1912.