Revett v. Globe Navigation Co.

106 P. 176, 56 Wash. 550, 1910 Wash. LEXIS 844
CourtWashington Supreme Court
DecidedJanuary 8, 1910
DocketNo. 8006
StatusPublished
Cited by1 cases

This text of 106 P. 176 (Revett v. Globe Navigation Co.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Revett v. Globe Navigation Co., 106 P. 176, 56 Wash. 550, 1910 Wash. LEXIS 844 (Wash. 1910).

Opinion

Chadwick, J.

This action was brought to recover damages for an alleged breach of contract of carriage. Defendant was the owner of, and operated, a line of steamers between the ports of Seattle and Nome, Alaska, during the season of 1905. The “Tampico” was advertised to sail on or about June 1, and the “Eureka” was to follow on or about June 15. Plaintiff is a manufacturer of mining dredges, and had contracted with the Seward Peninsular Mining Company, operating near Nome, to set up a mining dredge complete and ready for operation on or before September 1,1905. A contract of carriage was entered into between the plaintiff and defendant on the 27th day of May, the material parts of which follow:

“Seattle, Wash., U. S. A., May 27, 1905. “Mr. B. Stanley Revett, Hotel Butler, City.

“Dear Sir: We agree to ship for you and you hereby agree to deliver to us for shipment from Seattle to Cape Nome on steamship Tampico and Eureka, Tampico sailing from Seattle on or about June 1st and the steamship Eureka sailing from Seattle on or about June 15th, all of the freight you have to go to Cape Nome during the season of 1905 and more particularly a shipment of about 225 tons of machinery included in which shipment are two boilers weighing 11 tons each, 2 pieces weighing 6,300 lbs each and 2 pieces é.700 lbs each, now on the Northern Pacific cars, and 190,000 ft of lumber contained in which are 2 pieces to be made into spuds weighing about 6 tons each, shipment to be made by the Stetson Post Mill Co., of Seattle.

“On the sailing of the Tampico, June 1st, you agree to ship and we agree to carry not less than 75,000 ft. of aforesaid lumber and one car of bolts and any part of the shipment of the machinery which we desire to carry forward on that [552]*552vessel. On the sailing of the steamship Eureka on or about the 15th of June you are to ship the balance of the lumber from the Stetson Post Mill Co. and the balance of the machinery not shipped on the Tampico.”

Of the total shipment of seventy-five thousand feet of lumber which was to be carried on the Tampico, only sixty-three thousand five hundred feet went forward, the captain refusing to take more. It was intended that the balance of the lumber, as well as the other freight, should go forward on the Eureka. On or about June 25 plaintiff’s agent at Seattle was informed by Mr. Thorndyke, the general agent of defendant, that the Eureka was disabled and that her sailing date had been canceled. This fact was communicated to plaintiff at Breckenridge, Colorado, who immediately telegraphed Mr. Thorndyke as follows:

“Eureka sailing abandoned. Request you ship balance lumber first Nome sailing. Machinery on Tampico. Do all you can remedy. I will do all in my power. Writing.”

The balance of the lumber was shipped on the Olympian, a vessel belonging to another company, which sailed on or about July 15, and the dredger machinery followed on the second trip of the Tampico, which sailed on or about July 21. It is alleged that the machinery arrived too late to be set up for delivery on or before September 1, and because of defendant’s failure to keep its contract, plaintiff has been damaged. From a judgment of nonsuit, plaintiff has appealed.

It appears that the trial judge was moved to grant the nonsuit because of the telegram quoted above. This he construed to be a rescission of the original contract of carriage. Standing alone there might be some difference of opinion as to the legal effect of the telegram, but when considered in the light of the letter written at the same time and of which the telegram carried notice, the telegram cannot be made to bear that construction. The material parts of the letter, after quoting and confirming the telegram, are as follows:

“I am seriously afraid that the delay in getting the balance of the lumber to Nome may seriously retard our work as I [553]*553doubt whether our men will have enough work to keep them employed until the lumber gets there. I have cabled Wilkins and asked them to arrange accordingly. The delay is a most serious one as I am under contract to the company to have the dredge built by Sept. 1st, which at the best under the conditions was an exceedingly limited time, and I would therefore urge you to do everything in your power to expedite the shipment and landing of the lumber first. You may rest assured that we will do everything in our power to remedy the delay.”

Taken together these communications do not admit the right of respondent to breach the contract. They recognize -a situation for which appellant was not responsible, and contain an assurance that he would do all that he could to mitigate any damages that might follow, and in turn calls upon respondent to do all that it could to remedy the delay.

It is further contended by respondent that, although the court may have erred in its construction of the telegram, nevertheless, if it appears on other grounds that the judgment was right, it should be sustained by this court. Respondent asserts, in behalf of his theory, that the testimony shows that, notwithstanding its breach, appellant was unable to complete and carry out his own contract, in that it was impossible for him to deliver the freight mentioned in the contract on the dock at the time agreed upon, and that therefore respondent is released from any obligation to him. We cannot sustain the judgment by the application of the principles invoked to maintain this contention. Respondent cannot defend because the complete shipment was not tendered at the dock on the day agreed upon — June 15 — when it did not have the ship ready, or intend to have it ready, to receive the cargo. It would be a curious rule of law that would sustain a nonsuit when appellant’s agent in charge had testified in speaking of the shipment to go forward on the Eureka: “Did you have your load ready for her when she got here [about June 26] ? Ans. Yes, sir; had it waiting. Q. Waiting for her? Ans. Yes.” Aside from this, appellant was not bound to have the [554]*554freight on the dock on the day named in the contract. On May 27 appellant wrote Mr. Thorndyke as follows:

“This will be your authority for arranging with Mr. Nadeau, agent of the Northern Pacific, to deliver to you car No. 34726, containing bolts and spikes, which it is absolutely necessary to go up on the Tampico with 75,000 feet of lumber. There are seven other cars of machinery at Tacoma at the present time, ready for delivery, and it is understood that the Northern Pacific people will transfer these cars from Tacoma to Seattle, free of charge, demurrage or wharfage, as per the arrangement made by Mr. Seegar, the general agent in New York, for delivery to S. S. Lyra, said arrangements being released through the courtesy of Mr. Frank Waterhouse, per the letter which I now enclose you. Kindly keep in touch with Mr. Nadeau in regard to a carload of machinery now in transit from the Taylor Steel & Iron Co., Highbridge, N. J., a carload of machinery from the Standard Boiler Works, Lebanon, N. J., and another carload from Reeves Engine Co., Trenton, N. J. We are promised shipments of these delayed cars by June 1st, and would ask yourself and Mr. Nadeau to arrange for them to be forwarded not later that the Tampico’s sailing July 4th.”

The two letters voice the agreement of the parties. Courts may well take notice of the fact that freight such as the heavy parts of a dredger may be more conveniently loaded from the car than by passing them through a warehouse, and respondent, so far as the testimony shows, may.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Revett v. Globe Navigation Co.
123 P. 459 (Washington Supreme Court, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
106 P. 176, 56 Wash. 550, 1910 Wash. LEXIS 844, Counsel Stack Legal Research, https://law.counselstack.com/opinion/revett-v-globe-navigation-co-wash-1910.