Rettman v. City of Litchfield

354 N.W.2d 426, 1984 Minn. LEXIS 1450
CourtSupreme Court of Minnesota
DecidedAugust 31, 1984
DocketC1-83-1091
StatusPublished
Cited by23 cases

This text of 354 N.W.2d 426 (Rettman v. City of Litchfield) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rettman v. City of Litchfield, 354 N.W.2d 426, 1984 Minn. LEXIS 1450 (Mich. 1984).

Opinion

*427 WAHL, Justice.

This appeal raises the issue of whether quasi-contractual relief is available to a provider of services for a project initiated under Minn.Stat. ch. 429 (1982), governing local improvements and assessments, where the parties failed to comply with the procedures mandated by chapter 429. The jury found that the City of Litchfield (hereinafter city) had led plaintiff Edward Rett-man to believe he was hired to install a water main extension on his development property, that the city had benefited from Rettman’s work, and that he was entitled to recover the cost of the installation plus interest. The city appeals from an order denying its motion for judgment notwithstanding the verdict or a new trial. We reverse.

Edward Rettman, a contractor and developer, gained city approval to plat a parcel of land he owned within the city limits into 19 residential lots to be known as Quiet View Acres. Because he was an experienced ditching contractor, he installed sewer and water lines within the development himself according to city specifications. The dispute in this case arose over the installation of the extension to the city water main from its former end point, approximately 2 blocks from Rettman’s development, to connect with the water lines within the development.

In August 1978, Rettman petitioned the Litchfield City Council to approve the water main extension as an improvement under Minn.Stat. ch. 429. Such approval would make the installation a city project, the cost of which could then be assessed to those who benefited from the improvement. Thie initial, statutorily required public hearing on the petition was held in September 1978, and the city council approved the project over the protests of three of the four other potentially benefited property owners. After this hearing, the city dropped chapter 429 proceedings based on the understanding of council members and city employees that Rettman was going to do the work himself at no expense to the city to save time and money, with the hope of recouping the installation cost in the sale of the lots. Competitive bidding procedures mandated by chapter 429 were not followed, and there was no written contract.

Rettman testified that he never intended to install the water main extension at his own expense and that he thought throughout that the city was following the special assessment statute. He also testified that William Steinberg, an employee of the Litchfield Public Utilities Commission (hereinafter PUC), told him that he was low bidder on the job, based on an unsealed bid submitted without a bid bond, and that he could begin work. Rettman began work. Steinberg allowed him to use materials (pipe, etc.) that the city had on hand. Evidence at trial showed that in the past the city had supplied materials to contractors in order to expedite projects and had then billed the contractor for the cost of the materials.

The water main extension was completed by the early months of 1980. It served only the 19 lots in the development, Quiet View Acres, and does not have the capacity to be further extended. Steinberg died in May 1981, and it was not until the following fall that a PUC employee found the list of materials furnished to Rettman. The PUC forwarded the list to the city, which sent a bill to Rettman for $11,120.66 on January 2, 1982. Rettman’s only response was to send a bill to the city for $16,522.50 for installation of the water main extension.

As he sold lots in Quiet View Acres, Rettman told buyers and the real estate agent who handled some of the sales that the water and sewer were in and paid for and that there would be no future assessments for those services. He testified at trial that he knew there would be an assessment for the water main extension but that he intended to pay the entire amount assessed against the Quiet View Acres property.

*428 Rettman brought suit against the city on theories of contract, quasi-contract, and negligence for the $16,522.50 cost of installation. He also alleged willful indifference to his rights and asked punitive damages. The city counterclaimed for the $11,120.66 worth of materials it had furnished to Rett-man for the project, the $1,600 it had spent on repairs because of defective installation of the water main, and the $3,646.55 it had spent resurfacing the street torn up by Rettman in making the installation. The city has not appealed from the denial of its counterclaim but does raise the following issues:

1) whether quasi-contractual relief is available to Rettman for providing services for a project initiated under Minn.Stat. ch. 429 where the parties failed to comply with the mandates of that chapter;

2) whether the evidence supports recovery in quasi-contract even if such a remedy is available.

A third issue as to whether the jury award of prejudgment interest was appropriate, and Rettman’s issue, raised by notice of review, with regard to an award of attorney fees under Minn.Stat. § 549.21 (1982), we need not address because of our decision in the case.

1. We note at the outset that, on the record before us, the only theory on which Rettman may possibly recover is that of quasi-contract. Any express contract Rett-man may have had with the city was void for lack of compliance with the bidding procedures required by statute. Layne Minnesota Co. v. Town of Stuntz, 257 N.W.2d 295 (Minn.1977). Our cases set out the rule, however, that a contractor may recover under the theory of quasi-contract where the city had the power to contract but failed to comply with statutorily required procedures. Kotschevar v. North Fork Township, 229 Minn. 234, 39 N.W.2d 107 (1949). Kotschevar and the cases cited therein, as well as the few cases in this area decided subsequently, 1 involved situations where the alleged contracts were void for failure to comply with Minn.Stat. § 471.345 (1982), the Uniform Municipal Contracting Law, or its predecessor statutes. Section 471.345 prescribes procedures for municipalities to follow in letting general contracts for services and public projects. Its major purpose is to ensure fairness to contractors and to provide for competitive bidding to keep costs down. Under section 471.345 the city is the purchaser of the service or improvement involved. As a result, the general tax base is used to provide an improvement that benefits the city as a whole, such as a new water supply well, Layne Minnesota Co. v. Town of Stuntz; road repairs, Buffalo Bituminous, Inc. v. Maple Hill Estates, Inc., 311 Minn. 468, 250 N.W.2d 182 (1977); a new road, Kotschevar v. North Fork Township; or a bridge, Lundin v. Butternut Valley Township, 172 Minn. 259, 214 N.W. 888 (1927).

The statute involved in this case, however, is chapter 429, the Local Improvement, Special Assessments Statute.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kidwell v. Sybaritic, Inc.
784 N.W.2d 220 (Supreme Court of Minnesota, 2010)
Lester Building Systems v. Louisiana-Pacific Corp.
761 N.W.2d 877 (Supreme Court of Minnesota, 2009)
Taney v. Independent School District No. 624
673 N.W.2d 497 (Court of Appeals of Minnesota, 2004)
Navarre v. South Washington County Schools
652 N.W.2d 9 (Supreme Court of Minnesota, 2002)
Sentinel Management Co. v. Aetna Casualty & Surety Co.
615 N.W.2d 819 (Supreme Court of Minnesota, 2000)
Obst v. Microtron, Inc.
614 N.W.2d 196 (Supreme Court of Minnesota, 2000)
Frykman v. University of Minnesota-Duluth
611 N.W.2d 379 (Court of Appeals of Minnesota, 2000)
Obst v. Microtron, Inc.
588 N.W.2d 550 (Court of Appeals of Minnesota, 1999)
Baker v. Amtrak National Railroad Passenger
588 N.W.2d 749 (Court of Appeals of Minnesota, 1999)
Pouliot v. Fitzsimmons
582 N.W.2d 221 (Supreme Court of Minnesota, 1998)
Wong v. American Family Mutual Insurance Co.
562 N.W.2d 813 (Court of Appeals of Minnesota, 1997)
Benson v. Northwest Airlines, Inc.
561 N.W.2d 530 (Court of Appeals of Minnesota, 1997)
Cox v. Crown CoCo, Inc.
544 N.W.2d 490 (Court of Appeals of Minnesota, 1996)
Doe v. Redeemer Lutheran Church
531 N.W.2d 897 (Court of Appeals of Minnesota, 1995)
M.L. v. Magnuson
531 N.W.2d 849 (Court of Appeals of Minnesota, 1995)
Oelschlager v. Magnuson
528 N.W.2d 895 (Court of Appeals of Minnesota, 1995)
Gilman v. State Farm Fire & Casualty Co.
526 N.W.2d 378 (Court of Appeals of Minnesota, 1995)
Beck v. American Sharecom, Inc.
514 N.W.2d 584 (Court of Appeals of Minnesota, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
354 N.W.2d 426, 1984 Minn. LEXIS 1450, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rettman-v-city-of-litchfield-minn-1984.