Residential Carpentry Corp. of Florida, Inc. v. Kister Wood Products

41 Fla. Supp. 2d 186
CourtCircuit Court for the Judicial Circuits of Florida
DecidedApril 9, 1990
DocketCase No. 86-0303-Ca-01-WLB
StatusPublished

This text of 41 Fla. Supp. 2d 186 (Residential Carpentry Corp. of Florida, Inc. v. Kister Wood Products) is published on Counsel Stack Legal Research, covering Circuit Court for the Judicial Circuits of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Residential Carpentry Corp. of Florida, Inc. v. Kister Wood Products, 41 Fla. Supp. 2d 186 (Fla. Super. Ct. 1990).

Opinion

OPINION OF THE COURT

WILLIAM L. BLACKWELL, Circuit Judge.

FINAL JUDGMENT

This case was tried for six days to the Court as fact-finder. Residential Carpentry Corporation of Florida, Inc. (Residential) contracted with Defendant, Kister Wood Products, Inc. (Kister) to install in the [187]*187Ritz-Carlton Hotel in Naples, Florida most of the finished woodwork and millwork which Kister had contracted to provide Metric Constructors, Inc. (Metric), the general contractor on this construction project. Residential sued Kister contending Kister unreasonably delayed performance and inadequately performed its obligations under Kister’s contracts with Metric and Residential, thereby damaging Residential in its attempts to timely do what was required of it under these contracts. The Court finds for the Plaintiff, Residential, on its claims against Kister; and also finds for Residential on the counterclaim of Kister.

Residential also sued Ohio Farmers Insurance Company (Kister’s surety), Metric, and the owner of the Ritz-Carlton. The claims involving Metric and the hotel owner were settled before trial.

I FINDINGS OF FACT

From the greater weight of the credible evidence the Court finds the following operative facts. The Ritz-Carlton Hotel construction project in Naples was a “fast-track” project (meaning the various sub-contractors involved, the general contractor, and the owner agreed to a rapid construction schedule, the ultimate goal being the opening of the hotel on December 5, 1985). Construction was begun in the Spring of 1984. The owner and general contractor never deviated from this target opening in spite of various problems, including an unexpected brush with a minor hurricane in the late summer of 1985.

Kister’s contract with Metric (Plaintiff’s Exhibit 1) called for the supplying and installation of wood paneling, stairways, doors, various trim, and other custom-made wood and glass products (referred to by these trades as “millwork”). The price was $1,568,647.00. This was revised upward in two later change orders to $2,019,352.00. Kister subcontracted the installation work to Residential for $302,000.00 plus the cost of a performance and payment bond. The Kister-Residential contract (Plaintiff’s Exhibit 2) is a simple two page document in which the parties agreed Residential would be bound to Kister as Kister was bound to Metric and to the owner, as provided in the Metric-Kister contract. Notably, both contracts contained “time is of the essence” provisions (paragraph 6, Plaintiff’s Exhibit 1 and center paragraph, page 2, Plaintiff’s Exhibit 2).

While these contracts contained no specific schedules of delivery and installation of the millwork, the parties had many discussions about scheduling and exchanged correspondence on this subject. These parties, as well as other sub-contractors involved in the project, seemingly understood and accepted the importance of timely delivery and installation of the various components of the project; the performance of one [188]*188was often a prerequisite or co-requisite to the performance of another. Regarding scheduling, two material letters appear in Plaintiffs Composite Exhibit 3 - the February 15, 1985 letter from Kister’s Jerry Bradley to Metric’s Neal Fleshour and the July 11, 1985 letter from Kister’s Herbert Newton to Metric’s Paul Daniels. These letters contained dates referencing delivery and installation.

The essence of Residential’s claims is that Kister delayed deliveries; sent incomplete, poorly marked or unmarked materials; sent nonconforming and non-matched materials; and that as a result of these errors, Residential’s performance of its obligations was delayed, impeded, and, ultimately, accelerated into the last few months prior to the hotel’s opening (Plaintiffs expert on millwork installation called this “compression”) — all of which added to the Plaintiffs costs of performance.

Kister contends its delivery problems were occasioned by the failure of Metric to implement and transmit design changes and information quickly and accurately enough for Kister to act upon; and says that Residential’s workmen were unskilled in doing a job of this quality and magnitude; and says they mishandled the millwork; and that the hotel owner, Metric, and Residential were all variously responsible for delivery and quality control problems. Kister’s and Residential’s claims against Metric and owner were settled before trial. Kister also emphasizes paragraph 7 of the Metric-Kister contract which is a provision for a request for additional time when delays occur; and which also provides that an extension of time is subcontractor’s sole remedy for delay. Kister argues this provision precludes Residential’s right to recover damages.

The parties agree that numerous problems with the wood were caused by high humidity (the hotel is at the edge of the Gulf of Mexico) and the failure of Metric to get the building closed and air-conditioned before the millwork went into the building. The brush with the hurricane in late summer also occurred before the closure of the building. This undoubtedly accounts for much of what Kister’s witnesses described as poor workmanship by Residential. Most of the experts and other witnesses agreed that high humidity or significant humidity changes caused expansion/contraction in the wood which caused poor-appearing joints and open joints which required filling and painting. The Court is unable to attribute these problems to a specific cause in the light of all of the evidence.

The Court is convinced that Kister failed in a material way to timely and properly do what was required of it under the two contracts; and [189]*189that this failure resulted in significant monetary losses to Residential which should be compensated.

The Court is also convinced that Residential underbid the job significantly. Mr. Shitama, Plaintiffs expert, testified the Plaintiffs bid was 20-25% too low in terms of manpower estimates for the job. Kister’s experts testified that Residential’s bid was $361,000 or $384,-000 too low. The Court feels that Residential should not be compensated for its losses attributable to underbidding the job.

Both Kister and Residential have settled their claims with Metric and the Owner, who, no doubt, occasioned some of the losses complained of by these parties. The amounts of these losses are not ascertainable and the Court can only conclude they were fairly liquidated by those settlements. The Court feels these litigants are still trying to exact from each other some losses which were self-inflicted and some which should be laid at the feet of others — and which have probably already been compensated to some extent by virtue of these settlements.

II CONCLUSIONS OF LAW

Kister’s reliance on the “no damages for delay” provision in the Metric — Kister contract (paragraph 7), adopted in the Kister — Residential contract, is misplaced under the foregoing findings of fact. Kister’s inattention to the delivery schedules referenced in the letters in Plaintiffs Exhibit 3 impacted the performance of Residential in a significant, negative way. Kister cannot shift its responsibilities to others so easily in order to escape liability. See Bumby & Stimpson v Peninsula Utilities Corp., 169 So.2d 499, 502 (3d DCA 1964); S. Leo Harmonway, Inc. v Binks Mfg Co., 597 F. Supp. 1014, 1028 (S.D.N.Y. 1984).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DEPT., TRANSP. v. Hawkins Bridge Co.
457 So. 2d 525 (District Court of Appeal of Florida, 1984)
Southern Gulf Utilities, Inc. v. Boca Ciega Sanitary District
238 So. 2d 458 (District Court of Appeal of Florida, 1970)
S. Leo Harmonay, Inc. v. Binks Manufacturing Co.
597 F. Supp. 1014 (S.D. New York, 1984)
CA Davis, Inc. v. City of Miami
400 So. 2d 536 (District Court of Appeal of Florida, 1981)
Bumby & Stimpson, Inc. v. Peninsula Utilities Corp.
169 So. 2d 499 (District Court of Appeal of Florida, 1964)
McIntire v. Green-Tree Communities, Inc.
318 So. 2d 197 (District Court of Appeal of Florida, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
41 Fla. Supp. 2d 186, Counsel Stack Legal Research, https://law.counselstack.com/opinion/residential-carpentry-corp-of-florida-inc-v-kister-wood-products-flacirct-1990.