Resetarits Construction Corporation v. E&N Construction, Inc.

CourtDistrict Court, W.D. New York
DecidedApril 29, 2021
Docket1:19-cv-01258
StatusUnknown

This text of Resetarits Construction Corporation v. E&N Construction, Inc. (Resetarits Construction Corporation v. E&N Construction, Inc.) is published on Counsel Stack Legal Research, covering District Court, W.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Resetarits Construction Corporation v. E&N Construction, Inc., (W.D.N.Y. 2021).

Opinion

UNITED STATES DISTRICT COURT WESTERN DISTRICT OF NEW YORK

RESETARITS CONSTRUCTION CORPORATION, Plaintiff, v. DECISION AND ORDER 19-CV-1258S E & N CONSTRUCTION, INC. and ELIO FERREIRA, Defendants.

I. Introduction Before this Court is a contract dispute arising from a construction Master Subcontract for a project in New Jersey. Defendants (a New Jersey subcontractor and its principal) removed this case to this Court (Docket No. 1, Notice of Removal). Plaintiff Resetarits Construction Corporation (or “RCC”) is a New York corporation and contractor on the New Jersey project, while Defendant E&N Construction (“E&N”) is a New Jersey corporation (id. ¶¶ 7, 8, Ex. A, State Compl.) that performed work in the project. In his declaration in support of the Motion to Dismiss, Defendant Elio Ferreira states that he is a citizen of New Jersey (Docket No. 3, Decl. of Elio Ferreira ¶ 6; see also Docket No. 1, Notice of Removal ¶ 8 (Ferreira not a citizen of New York). This Decision and Order considers (a) Defendants’ Motion to Dismiss (Docket No. 3) and (b) Plaintiff’s Cross-Motion to Remand and for other, alternative relief (Docket No. 5). For the reasons stated herein, Plaintiff’s Cross-Motion to Remand (Docket No. 5) is denied. Defendants’ Motion to Dismiss (Docket No. 3) for lack of personal jurisdiction over Defendant Elio Ferreira is granted and their Motion to Dismiss (id.) Defendant E&N Construction, Inc., is granted. Plaintiff’s alternative motion for limited jurisdictional discovery (Docket No. 5) is denied and its motion (id.) for leave to amend the state Complaint as proffered is denied.

II. Background A. Removal Defendants removed this case from New York State Supreme Court, Erie County (Docket No. 1, Notice of Removal), asserting federal jurisdiction based on diversity jurisdiction (id. ¶¶ 7, 8, 4). In its Complaint, RCC alleges that RCC and E&N entered into a master subcontract (“Master Subcontract”) for construction of the Carrino Plaza Apartments in New Jersey (id., Ex. A, Compl. ¶ 6; see Docket No. 5, Decl. of David Resetarits [First], Ex. 1, Master Subcontract E&N Construction and Resetarits Construction Corporation). E&N denies this (Docket No. 7, Decl. of Shawn Roney ¶¶ 9, 12).

RCC alleges E&N breached the Master Subcontract by failing to secure labor and material bonds, performance bonds, and appropriate insurance; refusing to bill in a form acceptable to RCC, not paying required wages and benefits; and other breaches1 (id. ¶ 7). To the extent E&N did not pay, RCC claims that E&N’s principal owner Defendant Ferreira was personally responsible for the unpaid wages and benefits (id. ¶ 8). In addition to claiming damages from the breach, RCC also seeks to recover its attorneys’ fees, costs, and interest under Article 5.6 of the Master Subcontract (id. ¶¶ 9, 10).

1See Docket No. 5, Resetarits [First] Decl., Ex. 1, Master Subcontract E&N Construction and Resetarits Construction Corporation, arts. 14, 7, 4.2. B. Master Subcontract Article 20.4 of the Master Subcontract allows RCC to enforce its terms and provides that “Any such action and all actions by either party hereto, shall be venued and heard exclusively in Supreme Court, Erie County, New York” (Docket No. 5, Resetarits

[First] Decl., Ex. 1, art. 20.4). Article 2.2 calls for Work Orders that RCC issues to the subcontractor and “upon acceptance, a subcontract for that portion of the work shall exist between Resetarits and the Subcontractor for such Project, and containing all of the terms and conditions of this Master Subcontract and the provisions of the Work Order” (id.). The Master Subcontract contains an entire agreement provision which made the Master Subcontract, its attachments (including Work Orders, see id., art. 2.2), contract documents referred therein the “sole agreement between the parties hereto” (id., art. 16). The Master Subcontract submitted in this case is unsigned by both parties (id., at page 15). RCC’s Work Order (Docket No. 5, Ex. 3), however, was signed by both parties; senior project manager Thomas Wheeler2 signed for RCC and Shawn Roney signed for

E&N (id.). While the Work Order (Docket No. 5, Resetarits [First] Decl., Ex. 3; see also Docket No. 8, Resetarits Second Decl., Ex. 1) specified the scope of work, it does not contain a reference to the Master Subcontract or a forum selection clause. The Work Order does provide that E&N was to pay prevailing wages (id., at first to second pages) but did not require E&N to have requisite bonding and insurance or required procedures for payment. At issue here is the breach of this Master Subcontract (Docket No. 5, Decl. of David Resetarits [First], Ex. 1). This agreement (as RCC argues) is the asserted basis for

2E&N contend it negotiated with a “Thomas Vitiello.” The signature on the Work Order, Docket No. 5, Ex. 3, appears as “Vitiello” although the printed last name below the signature is “Wheeler.” personal jurisdiction over Defendants from their execution of the agreement containing a forum selection clause. The forum selection clause is also the reason RCC now seeks to remand this action to the New York State Supreme Court, Erie County. David Resetarits, the president and owner of RCC (Docket No. 5, Resetarits [First]

Decl. ¶ 1), represents that RCC never enters into a Work Order without the subcontractor first agreeing to a Master Subcontract (Docket No. 5, Resetarits [First] Decl. ¶¶ 8, 10 (practice of RCC to require subcontractors to agree to Master Subcontract before issuance of any Work Order); Docket No. 8, David Resetarits Decl. Second ¶ 15). The Master Subcontract here had the parties “agree that the terms of this Master Subcontract shall be deemed expressly incorporated by reference into each Work Order” (Docket No. 5, Resetarits [First] Decl. ¶ 14, Ex. 1, at 1). RCC sent the Master Subcontract to E&N for execution (Docket No. 5, Resetarits [First] Decl. ¶ 7, Ex. 1) but RCC later could not find that agreement (id. ¶ 11), concluding that E&N still had it (id. ¶ 12). RCC argues that after E&N agreed upon the Master

Subcontract RCC then sent the Work Order to E&N (id. ¶ 13, Ex. 3). Shawn Roney for E&N contends that the parties agreed to forego the Master Subcontract and to have E&N perform under a negotiated Work Order (Docket No. 7, Decl. of Shawn Roney ¶¶ 8-9, 13; Docket No. 8, Resetarits Second Decl. ¶ 6). E&N consistently rejected provisions that require it to litigate outside of New Jersey (Docket No. 7, Roney Decl. ¶¶ 7, 10-11). Roney claims he negotiated with Tom Vitiello whom Roney contends represented Plaintiff with another unnamed person (id. ¶ 9). E&N did not return a signed Master Subcontract because it rejected various terms in it, as E&N claims it communicated to Vitiello (id. ¶¶ 9, 10-12). Roney argues that Vitiello was “well aware that E&N rejected the terms of the proposed Master Subcontract” and that Vitiello and E&N agreed to work from the Work Order only (id. ¶ 13). E&N proceeded with the New Jersey project “without agreeing to any of the terms in the proposed Master Subcontract form” (id. ¶ 14).

Vitiello states, however, he never worked for RCC (he was employed instead by Sphere Construction) and claims he never negotiated with Roney or E&N regarding RCC’s Master Subcontract with E&N (Docket No. 11, Thomas Vitiello Decl. ¶¶ 5-6, 7-8, 9-11). Sphere’s role in this construction or negotiations (if any) is not stated in this record. David Resetarits agreed that Vitiello was not employed by or an agent of RCC (Docket No. 8, Resetarits Second Decl. ¶ 9). Resetarits did not give authority to Vitiello to negotiate the Master Subcontract with E&N (id. ¶ 11; see id. ¶ 12). Resetarits states that he was the sole individual who could bind RCC to terms of a Master Subcontract (id. ¶ 10). E&N never stated to Resetarits that E&N rejected the Master Subcontract (id. ¶ 13).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

International Shoe Co. v. Washington
326 U.S. 310 (Supreme Court, 1945)
Conley v. Gibson
355 U.S. 41 (Supreme Court, 1957)
Foman v. Davis
371 U.S. 178 (Supreme Court, 1962)
Zenith Radio Corp. v. Hazeltine Research, Inc.
401 U.S. 321 (Supreme Court, 1971)
Burger King Corp. v. Rudzewicz
471 U.S. 462 (Supreme Court, 1985)
Syngenta Crop Protection, Inc. v. Henson
537 U.S. 28 (Supreme Court, 2002)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Romano v. Kazacos
609 F.3d 512 (Second Circuit, 2010)
Chloé v. Queen Bee of Beverly Hills, LLC
616 F.3d 158 (Second Circuit, 2010)
Scott C. Savin v. Harry H. Ranier
898 F.2d 304 (Second Circuit, 1990)
Pino Distefano v. Carozzi North America, Inc.
286 F.3d 81 (Second Circuit, 2001)
Porina Ex Rel. Porins v. Marward Shipping Co.
521 F.3d 122 (Second Circuit, 2008)
Weichert Co. Realtors v. Ryan
608 A.2d 280 (Supreme Court of New Jersey, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
Resetarits Construction Corporation v. E&N Construction, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/resetarits-construction-corporation-v-en-construction-inc-nywd-2021.