Reserve Mooring Inc. v. American Commercial Barge Line, LLC

251 F.3d 1069, 2001 A.M.C. 1853, 2001 U.S. App. LEXIS 9380, 2001 WL 521331
CourtCourt of Appeals for the Fifth Circuit
DecidedMay 16, 2001
Docket00-30611, 00-30944
StatusPublished
Cited by16 cases

This text of 251 F.3d 1069 (Reserve Mooring Inc. v. American Commercial Barge Line, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reserve Mooring Inc. v. American Commercial Barge Line, LLC, 251 F.3d 1069, 2001 A.M.C. 1853, 2001 U.S. App. LEXIS 9380, 2001 WL 521331 (5th Cir. 2001).

Opinion

HALL, Circuit Judge:

I. Facts and Procedural History

Plaintiff Reserve Mooring, Inc. (Reserve) maintains a midstream mooring facility at Mile 138.3 on the Mississippi River. The mooring facility consists of five buoys and anchor piles, which Reserve installed pursuant to a permit from the United States Army Corps of Engineers. 1 On May 5, 1998, while moored at the site, a barge owned and operated by defendant *1070 American Commercial Barge Line (ACBL) sank while goods were being unloaded to it from another barge owned by defendant Associated Terminals (Associated). Although the accident did not cause any physical damage to the mooring facility, the site remained blocked until salvage operations were completed on August 20, 1998.

Reserve sued ACBL and Associated in federal district court, invoking the district court’s admiralty jurisdiction. Reserve seeks to recover its lost income resulting from the loss of use of the mooring site allegedly caused by Defendants’ negligence. Defendants twice moved for summary judgment, arguing that Reserve is precluded from recovering its purely economic losses under Louisiana ex rel. Guste v. M/V TESTBANK, 752 F.2d 1019 (5th Cir.1985) (en banc), because (1) there was no physical damage to the mooring facility, and (2) Reserve did not have a proprietary interest in the facility. The district court denied both motions in orders dated November 30, 1999, and April 26, 2000. On June 27, 2000, the district court certified both orders for immediate appeal. 2 Defendants filed a timely petition for permission of appeal, which this court granted on August 1, 2000. 3 We thus have jurisdiction over Defendants’ interlocutory appeal pursuant to 28 U.S.C. § 1292(b).

II. Standard of Review

The district court’s decisions on a motion for summary judgment are reviewed de novo. Maher v. Strachan Shipping Co., 68 F.3d 951, 954 (5th Cir.1995). Summary judgment is proper if there is no genuine issue as to any material fact and the moving party is entitled to judgment as a matter of law. Fed.R.Civ.P. 56(c); Maher, 68 F.3d at 954.

III. Discussion

Defendants contend that they are entitled to summary judgment because Reserve did not suffer any physical damage to a proprietary interest as required by Robins Dry Dock and Repair Co. v. Flint, 275 U.S. 303, 48 S.Ct. 134, 72 L.Ed. 290 (1927), and TESTBANK as a prerequisite to recovery of economic damages in cases of unintentional maritime tort. Reserve does not dispute that it suffered no physical damage to its buoys and anchor piles, and that its suit is for lost income only. 4

In Robins Dry Dock, the time charterers of a vessel sued for the loss of use of the vessel after the defendant dry dock negligently damaged the vessel’s propeller. The Supreme Court held that “as a general rule, at least, a tort to the person or property of one man does not make the tort-feasor liable to another merely be *1071 cause the injured person was under a contract with that other unknown to the doer of the wrong.” 275 U.S. at 309, 48 S.Ct. 134. Because the time charterers had no property interest in the vessel, but only a contractual relation with the vessel’s owners, the Court denied recovery. Id. at 308-09, 48 S.Ct. 134.

Sitting en banc, this court elaborated on Robins Dry Dock in TESTBANK The M/V TESTBANK collided with another vessel in the Mississippi River Gulf Outlet and caused a chemical spill, which resulted in the closure of the outlet for several weeks. Suits were filed by shipping interests, marina and boat rental operators, fishermen, shops, and restaurants to recover their economic losses resulting from the loss of use of the outlet. The court examined the “pragmatic limitation on the doctrine of foreseeability” established in Robins Dry Dock, and held that physical injury to a proprietary interest is a prerequisite to recovery of economic losses in cases of unintentional maritime tort. 752 F.2d at 1022-23,1028-29.

In ruling on Defendants’ motions for summary judgment, the district court reasoned that the TESTBANK rule is merely an application of the general requirement that damage be foreseeable to be recoverable in tort. Therefore, the court reasoned, plaintiffs may recover where, as here, there was no physical damage but the harm was “clearly foreseeable.” 5 However, in TESTBANK this court considered and rejected just such a case-by-case foreseeability approach to recovery of economic damages in cases of unintentional maritime tort. Id. at 1028-29. The court determined that such an approach failed to provide a “determinable measure of the limit of foreseeability.” Id. at 1028. The court instead chose the predictability afforded by the “bright line” rule that allows plaintiffs to recover economic losses only where the plaintiff has suffered physical injury to a proprietary interest. Id. at 1029. This court has not retreated from TESTBANKs physical injury requirement. See, e.g., Corpus Christi Oil & Gas Co. v. Zapata Gulf Marine Corp., 71 F.3d 198 (5th Cir.1995) (holding that the plaintiffs firing of gas in order to save its gas wells after the defendant damaged a gas riser owned by a third party constituted physical damage to a proprietary interest that allowed the plaintiff to recover for the lost gas); Consolidated Aluminum Corp. v. C.F. Bean Corp., 772 F.2d 1217 (5th Cir.1985) (holding that the owner of a manufacturing plant could recover economic losses incurred after the defendant negligently punctured a gas pipeline leading to the plaintiffs plant, and the resulting loss of gas flow caused physical damage to the plaintiffs plant machinery); Domar Ocean Transp., Ltd. v. M/V ANDREW MARTIN, 754 F.2d 616 (5th Cir.1985) (allowing recovery of economic losses arising out of the loss of use of the plaintiffs barge/tug unit after the unit was damaged in a collision).

Reserve argues that because the sinking of the barge physically prevented any other vessel from using its mooring site while the barge was being salvaged, it is entitled to recover its lost income.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Plains Pipeline, L.P. v. Great Lakes Dredge & Dock Co.
46 F. Supp. 3d 632 (E.D. Louisiana, 2014)
Bertucci Contracting Co. v. Steele
712 F.3d 245 (Fifth Circuit, 2013)
Castellanos-Contreras v. Decatur Hotels, LLC
622 F.3d 393 (Fifth Circuit, 2010)
City of Joliet v. Southern Towing Co.
387 F. Supp. 2d 911 (N.D. Illinois, 2005)
DeHoyos v. Allstate
Fifth Circuit, 2003
Conoco Inc. v. Halter-Calcasieu LLC
865 So. 2d 813 (Louisiana Court of Appeal, 2003)
Dehoyos v. Allstate Corp.
345 F.3d 290 (Fifth Circuit, 2003)
In Re American Milling Co.
270 F. Supp. 2d 1112 (E.D. Missouri, 2003)
Intl Shipbreaking v. Smith
Fifth Circuit, 2002

Cite This Page — Counsel Stack

Bluebook (online)
251 F.3d 1069, 2001 A.M.C. 1853, 2001 U.S. App. LEXIS 9380, 2001 WL 521331, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reserve-mooring-inc-v-american-commercial-barge-line-llc-ca5-2001.