Reliable Building Maintenance Co. v. United States

39 Cont. Cas. Fed. 76,680, 31 Fed. Cl. 641, 1994 U.S. Claims LEXIS 144, 1994 WL 406160
CourtUnited States Court of Federal Claims
DecidedAugust 3, 1994
DocketNo. 91-956C
StatusPublished
Cited by7 cases

This text of 39 Cont. Cas. Fed. 76,680 (Reliable Building Maintenance Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reliable Building Maintenance Co. v. United States, 39 Cont. Cas. Fed. 76,680, 31 Fed. Cl. 641, 1994 U.S. Claims LEXIS 144, 1994 WL 406160 (uscfc 1994).

Opinion

OPINION

SMITH, Chief Judge.

Plaintiff, Reliable Building Maintenance Company, seeks damages for breach of contract by the Air Force. The contract was for custodial services at Travis Air Force base, located in Travis, California. The dispute centers on the interpretation of a contract term referred to as “high dusting.” The court finds that the defendant must prevail in this case for two independent reasons. First, after examining the disputed contractual provision in light of the contract as a whole, as well as the facts, circumstances, and course of dealings between the parties, the court finds the contractual interpretation advocated by the government best reflects the true intent of the parties. Second, even assuming arguendo that the contract’s “high dusting” provision is ambiguous, the court concludes the ambiguity was patent so that Reliable had a “duty to inquire,” which it failed to do.

Facts

In 1989, the Air Force awarded a contract for custodial services at Travis Air Force base to Reliable. The contract covered custodial services for most of the public buildings on the base. The contract contained the following provision:

1.1 Scope of Work

The contractor shall provide all personnel, equipment, tools, materials, supervision, and other items and services necessary to perform custodial services as specified in this Performance Work Statement (PWS) except as specified in Section C-3 as government furnished property and service at Travis AFB California. The contractor shall perform to the standards in this contract.

Subsequent provisions outline the specific custodial tasks which Reliable was obligated to perform. The present dispute centers on the contractual provisions which require Reliable to perform custodial services referred to as “high dusting” and “low dusting.” The relevant contract provisions are the following:

5.2.1.7 Perform Low Dusting The contractor shall perform Low dusting, so that after dusting, all dust, lint, litter and dry soil shall be removed from the surfaces of desks, chairs, file cabinets, and other types of office furniture and equipment and from ledges, window sills, hand rails, etc., to a line 7'0" above the top of the floor level. Typewriters, business machines, and equipment of similar nature shall not be dusted by the contractor. Personal and/or [643]*643decorative items on desks will not be touched by the contractor.
ij: sji s¡«
5.2.2.1 The contractor shall perform high dusting, so that after dusting, all dust, lint, litter, and dry soil shall be removed from all surfaces 7'0" above the top of the floor surface to include Venetian blinds, where installed, (emphasis added.)

Reliable argues that prior to 1988, and until some point in 1989, it understood the above task descriptions to require the removal of dust up to the seven-foot level but did not require dusting areas above seven feet. Reliable alleges it was first advised by defendant in 1989 that the contract required dusting above the seven-foot level, including the ceiling, pipes, and other fixtures. After initially disputing the government’s interpretation of the high dusting requirement, Reliable demanded additional payment for the alleged increased costs required to perform “high dusting.” In response to Reliable’s demand, the government unilaterally modified the contract to eliminate the high dusting provision. Accordingly, the government deducted $56,143.33, from its payments to Reliable.1 Reliable then brought this action, contending that it performed fully under the contract, and seeking recovery of the monies deducted by the government.

Discussion

As with the interpretation of any contract, the court must first examine the language of the provision in question, and analyze the provision within the context of the entire contract. Contract 115.2.2.1 sets out the contractual requirements for high dusting. At trial, both parties argued forcefully that the high dusting provision was clear and unambiguous. Plaintiff argued that the language only required dusting up to seven feet, except for Venetian blinds, which it conceded must be dusted regardless of height. Defendant argued that the language of the contract clearly required Reliable to dust above seven feet. However, neither of these interpretations is obvious solely from the language of the “high dusting” provision.2 Nevertheless, a proper interpretation of a contract should give meaning to each provision, if possible, by viewing the contract as a whole, rather than rendering some provisions meaningless. Steve Altman Photography v. United States, 18 Cl.Ct. 267 (1989).

The proper interpretation of H5.2.2.1 is obvious when the contract is examined as a whole. Paragraph 5.2.I.7. — “Perform Low Dusting” — specifically describes the low dusting tasks, including that “after dusting, all dust, lint, litter and dry soil shall be removed from the surfaces of desks, chairs, file cabinets, and other types of office furniture and equipment and from ledges, window sills, hand rails, etc.” Further, this provision specifically states that the low dusting tasks be performed “to a line 7'-0" above the top of the floor level.” Thus, under the rubric of low dusting, the contract requires these specifically defined tasks to be performed under the seven foot level. Similarly, contract H 5.2.2.I. lays out the requirements the contractor must meet in performing “high dusting.” Both provisions refer to the seven-foot benchmark, and the contract’s use of the “low” and “high” terminology is not without meaning. A common sense interpretation of the terms “low” and “high” leads to the logical conclusion that “high dusting” takes place at a greater distance above the floor [644]*644than does “low dusting,” with the demarcation line, in this case, being the 7'-0" benchmark mentioned in both provisions. Thus, the arguable ambiguity in H 5.2.2.I. is superficial, a result of poor draftsmanship, and does not impede the court’s ability to discern the true intent of the parties.

Viewed in proper context, the high dusting provision logically requires dusting at a greater height than seven feet above the floor’s surface. The court finds that such an interpretation is consistent with the contract when viewed as a whole, and reflects the true intentions of the parties. Reliable’s argument that they never would have agreed to perform “high dusting” at the stated contract price would be stronger if all the buildings in question were massive aircraft hangers, or similar buildings with high ceilings that would require the use of scaffolding or similar equipment. To the contrary, the evidence at trial indicated that “high dusting” constituted a small portion of the work. It appears that very few of the buildings to be cleaned had ceilings substantially above seven feet. Moreover, Reliable actually performed some dusting above seven feet throughout the 1984 and 1989 contracts. In short, while the high-dusting provision is admittedly poorly drafted, it is evident to the court that the parties intended for high dusting to cover dusting above seven feet.

However, even assuming arguendo that the H 5.2.2.1 of the contract is ambiguous so that the intent of the parties is not fairly discernable, the court concludes defendant still must prevail.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alliant Techsystems Inc. v. United States
74 Fed. Cl. 566 (Federal Claims, 2007)
Travelers Casualty & Surety of America v. United States
74 Fed. Cl. 75 (Federal Claims, 2006)
Tecom, Inc. v. United States
66 Fed. Cl. 736 (Federal Claims, 2005)
Summitt Investigative Service, Inc. v. Herman
34 F. Supp. 2d 16 (District of Columbia, 1998)
Blinderman Construction Co. v. United States
42 Cont. Cas. Fed. 77,210 (Federal Claims, 1997)
Huna Totem Corp. v. United States
40 Cont. Cas. Fed. 76,937 (Federal Claims, 1996)
Conoco Inc. v. United States
35 Fed. Cl. 309 (Federal Claims, 1996)