Reisch v. State

668 A.2d 970, 107 Md. App. 464, 1995 Md. App. LEXIS 209
Court of Special Appeals of Maryland·Decided December 28, 1995·No. No. 278·Published·Cited by 8 cases

Opinion

HOLLANDER, Judge.

In 1992, Edward Claire Reisch, appellant, was charged with two home improvement offenses, in violation of Code, Art. 56, §§ 255 and 261 (1957, 1988 Repl.Vol.). After a bench trial in 1995 in the Circuit Court for Baltimore County,1 appellant was convicted of operating without a home improvement license2 and sentenced to six months in the Baltimore County Detention Center, pursuant to Art. 56, § 267. He was also ordered to pay restitution of $18,880.00, a fine of $350.00, and court [467] costs of $225.00. Appellant’s sentence was to be served in home confinement, with all costs to be paid by appellant.

Appellant filed a pro se appeal and, in his “Questions Presented,” he states:

“1. The evidence adduced at trial was legally insufficient to sustain a conviction of not having a home improvement license.
2. Appellant was exempted from requirements for needing a home improvement license.
3. No criminal intent.
4. If anything the issue is a Civil matter not Criminal.”

Factual Summary

On April 21, 1992, appellant, owner of a business called Unleading America, entered into a contract with George Stuart Lacher to remove lead paint from Lacher’s house. The house, which was built in 1880, was approximately 5000-6000 square feet in size. Lacher learned of appellant’s company through information furnished to him by the Maryland Department of the Environment (“DOE”).

The contract provided, inter alia, for removal of “all existing paint” from the exterior of the house through use of “a high-pressure waterwash” and chemical stripping. In addition, Reisch agreed to remove the paint from specified interior portions of the house. The contract further obligated appellant to contain loose lead paint particles and to remove lead dust by various methods. In addition, Reisch agreed to repaint the entire exterior of the house and remove “existing screens and replace with either aluminum or fiberglass screening.” The total contract price was $27,000.00, payable in three installments. The contract also contained an option for “sash chain installation,” at additional expense.

In May 1992, Reisch began the work. Testimony at trial from Lacher and appellant differs in terms of the quality of work that was done, when the work was done, and whether it was done in accordance with contract specifications.

[468] According to Lacher, appellant began work on the exterior of the house by blasting it with water to remove the existing paint. But appellant lined only certain areas of the ground with plastic to contain lead contaminated paint removed by the blasting. Lacher also contended that the plastic lining did not effectively contain paint chips, many of which were strewn around the property. Further, he claimed that no measures were taken to contain paint removed from the exterior of the Lacher garage.

In his testimony, Lacher said that the paint was never completely removed from the exterior of the house, as required by the contract. He also maintained that appellant removed the screens from the porches, but the screens were never returned. He added that appellant spray painted the storm windows, the stone foundation, and the roof. Regarding the interior of the house, Lacher stated that appellant’s work was limited to the windows in two bedrooms. Lacher further denied that he asked Reisch to do any additional work beyond the terms of the contract.

Lacher also contended that, after he had paid appellant the second installment on or about May 15, 1992, the work basically ceased. In an effort to effect contract completion, Lacher related that he called appellant at least once a day because no work was being done. When appellant failed to complete the work by early July, Lacher hired another painter to finish the job. In July 1992, Lacher barred appellant from returning to Lacher’s property.

On July 13, 1992, Lacher filed a complaint against appellant with the Maryland Home Improvement Commission. He alleged, inter alia, that appellant failed to abate safely the lead paint from the exterior of his house, and that Reisch had more than two thirds of his money but only completed one third of the work. Robert Earl Hoggard, an investigator for the Home Improvement Commission, testified that appellant was not a licensed home improvement contractor at the relevant time.

[469] Appellant testified in his own defense. He said that the scope of work on the Lacher home included interior and exterior paint removal, including approximately 950 square feet of interior work. Although not particularized in the contract, he nonetheless claimed that the interior work included painting the walls, painting the woodwork, taking the doors down, rehanging cupboard doors, and painting the cupboard doors and all of the shelves.3 Appellant further stated that he began with the interior work because Lacher wanted the inside lead abatement work completed before Lacher’s then-expectant wife delivered.

Reisch also testified that he properly contained lead chips removed from the exterior of the house. Appellant conceded, however, that his “crew” failed to adhere to prescribed containment procedures in removing paint from the garage. But, when the problem was discovered, he brought a crew to the property and it was entirely cleaned. Furthermore, appellant testified that what Lacher referred to as spray painting was actually an “overspray,” a procedure utilized “when you do any treatment with lead,” the purpose of which was to seal the exterior surface prior to painting to ensure a “good bond.” He also claimed that the “job got more involved” because there were so many problems with the condition of the house that only became apparent once the work began.4 He asserted, too, that the porch screens were repaired and returned. Although he claimed that inclement weather hampered the progress of the work, he said that he was always ready and able to finish the job.

[470] Appellant acknowledged that he performed some additional work not specifically addressed in the contract. He stated that he repaired a concrete pad at the rear of the house, replaced two glass window panes, planed a door, and repaired windows that were not operating properly. Appellant explained that he repaired the concrete pad near the garage in an effort to seal the soil after its contamination from lead paint chips. Appellant further said that he performed additional work outside the contract because Lacher requested it.

Free access — add to your briefcase to read the full text and ask questions with AI

Reisch v. State, 668 A.2d 970, 107 Md. App. 464, 1995 Md. App. LEXIS 209 (Md. Ct. App. 1995).

668 A.2d 970 (Reisch v. State) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Okoro v. Maryland Department of the Environment
115 A.3d 709 (Court of Special Appeals of Maryland, 2015)
Chow v. State
881 A.2d 1148 (Court of Special Appeals of Maryland, 2005)
United States v. Talebnejad
342 F. Supp. 2d 346 (D. Maryland, 2004)
Zi Qiang Chen v. State
784 A.2d 641 (Court of Special Appeals of Maryland, 2001)
Suburban Hospital, Inc. v. Maryland Health Resources Planning Commission
726 A.2d 807 (Court of Special Appeals of Maryland, 1999)
Price v. State
681 A.2d 1206 (Court of Special Appeals of Maryland, 1996)
(1996)
81 Op. Att'y Gen. 112 (Maryland Attorney General Reports, 1996)
Hartford Accident & Indemnity Co. v. Scarlett Harbor Associates Ltd. Partnership
674 A.2d 106 (Court of Special Appeals of Maryland, 1996)