Reilly v. Lee

32 N.Y.S. 976, 92 N.Y. Sup. Ct. 315, 66 N.Y. St. Rep. 460, 85 Hun 315
CourtNew York Supreme Court
DecidedMarch 15, 1895
StatusPublished
Cited by2 cases

This text of 32 N.Y.S. 976 (Reilly v. Lee) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reilly v. Lee, 32 N.Y.S. 976, 92 N.Y. Sup. Ct. 315, 66 N.Y. St. Rep. 460, 85 Hun 315 (N.Y. Super. Ct. 1895).

Opinion

PARKER, J.

The complaint alleged two separate causes of action, growing out of two different contracts. As to one there is [977]*977no dispute, and for convenience we shall treat the matters in controversy as if but one cause of action was pleaded in the complaint. In brief, it was for a balance claimed to be due under a written contract entered into between the parties to this action in June, 1889, by which the plaintiffs agreed to build, construct, and finish “in the most substantial and workmanlike manner, and to the satisfaction and acceptance of the engineer or engineers in "charge of the Pennsylvania, Poughkeepsie and Boston Railroad Company, all the masonry work required to be done by the first party (this defendant) for the bridge to be constructed by it across the Lehigh river at or near Slatington, Pennsylvania.” And the defendant engaged that whenever, in the opinion of the said engineer or engineers in charge, the said work should be completely finished in every respect, and performed agreeably to the various stipulations and specifications in the said agreement contained, and the said engineer or engineers in charge should have furnished to the defendant a certificate to that effect, together with an estimate of the quantity of work done by the plaintiffs, he would, within 20 days thereafter, pay the plaintiffs the amount found to be due. Performance by the plaintiffs, and the making and delivery of the required certificate and estimate by the engineer in charge, under which they claimed to be due $1,671.95, were also alleged. The answer put in issue the allegations of performance and the making of the certificate and estimate by the engineer, and by way of counterclaim asserted that the plaintiffs failed to construct the masonry in a substantial and workmanlike manner, as required by said agreement; and that a portion of the work was so defectively done that it was rebuilt at defendant’s expense, and the sum expended therefor defendant claimed the right to recover against the plaintiffs under the fifth provision of the contract, which is as follows:

“Fifth. It is mutually agreed between the parties hereto that, if the second party shall execute any part of such work defectively, then such defective work shall be rebuilt at the expense of the party of the second part, upon receiving the order from the engineer or engineers in charge to that effect.”

The referee found that the engineer in charge did not furnish to the defendant a certificate that the work had been performed in a substantial and workmanlike manner, nor make and deliver to the plaintiffs an estimate of the quantity of work done by the plaintiffs, all of which was, by the terms of the contract, a condition precedent to a right of recovery by the plaintiffs; and he further found that there was no proof of'a waiver of such certificate by defendant. In accordance therewith he held that the plaintiffs were not entitled to recover any sum whatever, and directed judgment accordingly. His report also directed that judgment should be entered dismissing the counterclaim set forth in the answer, but not upon the merits. With the reasons for the decision respecting the counterclaim as stated in the referee’s opinion, the appellant is dissatisfied. We shall refrain from a discussion of them, however, on this review, because we think the decision must be upheld upon other grounds, and it matters not whether proper reasons are given for rendering a correct judgment.

[978]*978Assuming the defendant’s contention to be correct, that under the fifth provision of the contract, which we have quoted, he was entitled to recover of plaintiffs the expense of rebuilding the pier, which it is proved was done by the railroad company with whom the defendant had contracted to do the work, which he subsequently subcontracted to these plaintiffs, and which was done at a cost exceeding $3,000, hfe certainly could not recover until after performance; and performance could not be undertaken until after the order from the engineer or engineers in charge to that effect had been received. They might have provided otherwise, but they chose this method of guarding against defective work, and, in effect, provided that the remedy for unskillful performance on the part of the plaintiffs should be the rebuilding of such work as should be done defectively. Even that was not left to the discretion of the defendant, for it was further conditioned that the rebuilding should only be done upon an order of the engineer in charge. There was controversy on the trial whether the order was properly made by the engineer and received by the party to be affected; and whether the rebuilding was done at the expense of the party of the second part But that is of no moment in the present discussion, for, conceding the defendant’s contention in such respects to be correct, nevertheless a cause of action in his favor could not arise therefrom ■until performance had been completed; and it was not completed-until after the commencement of this action. At that time defendant could not have commenced an action against the plaintiffs to ■recover for the expense incurred in rebuilding the pier, for the rebuilding had not been finished, and his cause of action was not, therefore, complete. And it was none the less necessary that he •should have a complete cause of action in order to set it up by way of counterclaim against these plaintiffs. Patterson v. Patterson, 59 N. Y. 574; Taylor v. Mayor, etc., of New York, 82 N. Y. 10. While the counterclaim was dismissed, the dismissal was not upon the merits, so the defendant is not thereby deprived of his right to enforce his cause of action if it has in the meantime become or shall become complete. The decision of the referee in dismissing the counterclaim is also justified by the decision in Walker v. Millard, 29 N. Y. 375. In that case the plaintiff sought to recover a balance claimed to be due under a building contract. The defendant answered that plaintiff could not recover, because of his failure to fully perform the contract, and by way of counterclaim .demanded damages for defective performance. It was held that the plaintiff had committed a breach of his contract, and could not recover, and also that defendant could not recover on his countertdaim. The reason assigned is briefly stated in the opinion of Johnson, J., as follows:

“He alleges that the plaintiff has broken the contract, or failed to perform it, and cannot, therefore, compel him to pay, and yet insists that he can compel the plaintiff to pay for defects in the work, for which» the latter gets no ■compensation. This, I apprehend, he can scarcely be allowed to do. He ■cannot both repudiate the contract, and enforce it, in the same action. Had (the defendant brought his action to recover damages for the nonperformance of the contract on the part of the plaintiff, it would have been necessary for
[979]*979him to allege performance or an offer to perform, on his part, or he would not have stated a cause of action. Certainly he is in no better situation in regard to his own counterclaim, as defendant. Having interposed the plaintiff’s breach, in avoidance of his own obligation to pay, and procured a ruling to that effect in his favor, he is in no situation to enforce the contract against the other party, in any particular, especially in the same action.” .

This case was cited and followed in Woodward v. Fuller, 80 N. Y. 312. The same question came before the court in Lennon v. Smith, 124 N. Y. 578, 27 N. E. 243.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Caspary v. Hatch
157 A.D. 679 (Appellate Division of the Supreme Court of New York, 1913)
Hudson River Power Transmission Co. v. United Traction Co.
98 A.D. 568 (Appellate Division of the Supreme Court of New York, 1904)

Cite This Page — Counsel Stack

Bluebook (online)
32 N.Y.S. 976, 92 N.Y. Sup. Ct. 315, 66 N.Y. St. Rep. 460, 85 Hun 315, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reilly-v-lee-nysupct-1895.