Hudson River Power Transmission Co. v. United Traction Co.

98 A.D. 568, 91 N.Y.S. 179

This text of 98 A.D. 568 (Hudson River Power Transmission Co. v. United Traction Co.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hudson River Power Transmission Co. v. United Traction Co., 98 A.D. 568, 91 N.Y.S. 179 (N.Y. Ct. App. 1904).

Opinion

Parker, P. J.:

I do not concur with the trial judge in his construction of this complaint.

It states that the power company and the traction company, on or about August 1, 1901, “ entered into a contract in writing, bearing date on that day, ready to be produced when and where this court may direct, whereby,” etc., and then proceeds to give the substance of the agreement therein, as it understands it; sets forth wherein it claims the traction company has broken the same; states the balance due for energy ” delivered thereunder, and seeks to recover such balance and damages suffered on account of such breach.

The defendant has annexed to its answer a copy of a contract which it alleges therein is the same one to which the complaint refers.

Upon the trial it argued that because of the statement in the complaint, above quoted, that such contract was ready to be produced when and where the court ordered, the contract so annexed to its answer must be deemed annexed to the complaint, and must be read as a part of the complaint; and that, when so read into the complaint, the facts appearing in such complaint did not warrant a recovery. The trial judge so held. It is not claimed that the complaint, on its face, and as it states the contract to be, fails to state a cause of action. Concededly it is a good complaint and not demurrable, unless facts which appear in the copy of the contract annexed to the defendant’s answer are to be added to the averments in the complaint.

Manifestly the production of such copy by the defendant is not a production of the eonf/ract by the plaintiff. It is not in court upon the plaintiff’s response to the order of the court. It is produced by the defendant, and it may or may not be a correct copy of the contract upon which the plaintiff brings this action.

The defendant, however, having averred in the answer that it is the same contract, it is claimed that it must now not only be so considered, but that all its provisions must be deemed averments of the complaint.

But an admission of the truth of the statements contained in a pleading is implied upon a demurrer only for the purpose of testing the sufficiency of that .pleading. It does not concede their [572]*572truth for any other purpose. It does not bar the one who demurs from disproving them upon the trial nor from disputing them when his own pleading is being analyzed to determine its sufficiency. For the purpose of construing the defenses to which the plaintiff has demurred, all the statements of fact in them contained are to be taken as true, but that by no means operates to transfer such statements, or facts, to the complaint and make them a part thereof. The sufficiency of the complaint should, therefore, be determined upon the facts which are alleged therein, and those only should be considered.

But assume that every provision contained in the contract was specifically set forth in the complaint, it would still in my judgment sufficiently set forth a good cause of action against the defendant.

By that contract the power company undertakes to furnish to the traction company for a period of ten years a certain specified amount of “electrical energy” for each year, and which yearly amount is specifically distributed among the several months of the year in varying proportions, and for which the traction company agrees to pay the sum of $70,000 annually, such payment to be distributed among the several months of the year in certain specified sums, and to be made on or prior to the tenth of each succeeding month. The performance of the contract was to commence on July 1, 1902.

It was further provided by the 4th article of the contract that “ if, by reason of accident, lack of water, or other matter beyond its control, the power company shall at any time be unable to furnish the electrical energy continuously in accordance with the terms of this agreement,” the deficiency so arising in the energy furnished for any month should be compensated for by deducting from the amount agreed to be paid for such month a sum equal to three thousand six hundred and fifty-three ten-thousandths of a cent per horse-power hour for the amount of such deficiency during the period of its occurrence, and such amount was fixed as liquidated damages for the failure on the plaintiff’s part.

It was further provided by the 6th article of the contract that the power company should also deliver to the traction company all the electrical energy, in excess of the amount above required, that the power company could produce at its water power plant, [573]*573provided that the traction company should not be obliged to receive in any one day “ excess electrical energy ” amounting to more than 500 horse power. Provision was also made for the amounts and times and manner of ascertaining and paying for the same by the traction company.

With the contract so annexed, the contention is as follows: In order to recover against the traction company for a breach of this contract the plaintiff must show, and hence must aver in the complaint, a full performance on its part. The 3d paragraph contains an allegation to that effect, but the 4th paragraph contains a statement that it delivered all the energy that it was required to deliver during the month of August, 1903, “ less certain small deficiencies.” By the 4th article of the contract deficiencies to a certain extent, viz., such as occurred through matter beyond the control of the power company, were permitted, and provision was made for a money compensation for the same. And if it appeared in the complaint that such deficiencies occurring in August were of the kind so permitted, then their existence would not necessarily modify the averment in the 3d paragraph and be a concession that full performance had not been made. In that event both averments might be consistent. And so in the original complaint, it being left to appear that such a money compensation might be made for all deficiencies, a concession of non-pei'formance could not be claimed from the averments in its 4th paragraph. But, now that the full terms of such 4tli article are found in the complaint, a clear admission appears in its 4th paragraph that default was made in furnishing the requisite amount of energy ” for August, inasmuch as it is nowhere alleged that such deficiencies were occasioned by means beyond the power company’s control. And hence the complaint is claimed to be insufficient because it appears therefrom that the plaintiff, not having fully performed on its part, is not entitled to recover the damages which it claims.

But the same 4tli paragraph of the complaint shows that this argument should not prevail. It proceeds to state that the traction company estimated and fixed the amount of such deficiencies at the rates provided therefor in the contract at the sum of $210.26 ; that the power company accepted and allowed it upon the $4,670.84, which the contract required the traction company to pay for said [574]*574month of August; and that the balance only, viz., $4,460.58, is the amount for which such company made default on September tenth, and for which this action seeks to recover.

It is apparent, therefore, that the certain small deficiencies ” conceded to exist in that paragraph were of the kind referred to in the 4th article of the contract. They were of the kind for which compensation could he made by the method and at the rate fixed in the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Walker v. American Central Insurance
38 N.E. 106 (New York Court of Appeals, 1894)
Reilly v. . Lee
50 N.E. 1121 (New York Court of Appeals, 1898)
Bellinger v. Craigue
31 Barb. 534 (New York Supreme Court, 1860)
Prouty v. Eaton
41 Barb. 409 (New York Supreme Court, 1863)
City of Schenectady v. Furman
15 N.Y.S. 724 (New York Supreme Court, 1891)
Reilly v. Lee
32 N.Y.S. 976 (New York Supreme Court, 1895)

Cite This Page — Counsel Stack

Bluebook (online)
98 A.D. 568, 91 N.Y.S. 179, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hudson-river-power-transmission-co-v-united-traction-co-nyappdiv-1904.