Rehkemper & Sons, Inc. v. Mid-Rivers Development and Construction LLC

CourtDistrict Court, E.D. Missouri
DecidedDecember 23, 2021
Docket4:21-cv-00380
StatusUnknown

This text of Rehkemper & Sons, Inc. v. Mid-Rivers Development and Construction LLC (Rehkemper & Sons, Inc. v. Mid-Rivers Development and Construction LLC) is published on Counsel Stack Legal Research, covering District Court, E.D. Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rehkemper & Sons, Inc. v. Mid-Rivers Development and Construction LLC, (E.D. Mo. 2021).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF MISSOURI EASTERN DIVISION REHKEMPER & SONS, INC., ) ) Plaintiff, ) ) v. ) Case No. 4:21-CV-00380-SEP ) MID-RIVERS DEVELOPMENT AND ) CONSTRUCTION LLC, ) ) Defendant. MEM ORAND U )M AND ORDER

Before the Court is Mid-Rivers Development and Construction LLC’s Motion to Dismiss the Complaint. Doc. 4. FoFrA tChTeS r AeNaDso BnAsC sKeGtR fOoUrtNhD b1 elow, the Motion is denied. Plaintiff Rehkemper & Sons, Inc., is a subcontractor that specializes in providing construction developers with roof and floor trusses, factory-fabricated stud walls, loose wood products, and connection hardware. Doc. 1 ¶¶ 1, 2. Defendant Mid-Rivers Development and Construction LLC is a construction developer that, at the time of the Complaint, was in the process of developing an apartment complex known as The Reserve at Mid-Rivers (The Reserve). Doc. 4 at 1. In March 2020, Rehkemper and Mid-Rivers began discussing a deal where Rehkemper would provide Mid-Rivers with certain wood carpentry components and materials for use at The Reserve complex. Doc. 1 ¶ 9. In response to a proposal from Id. Rehkemper, Mid-Rivers sent back a “Non-Binding Letter of Intent and Authorization to Id. Proceed.” ¶ 11. Mid-Rivers initially represented that work at The Reserve would begin in March but then postponed negotiations with Rehkemper for six months. ¶ 12. In September 2020, Mid-Rivers re-initiated discussions with Rehkemper and Id. proposed that the parties enter an agreement to complete all “pre-panelized wood framing work” based on Rehkemper’s original proposal. ¶ 13. The Mid-Rivers proposal, which

1 Neitzke v. Williams Id. was based on Rehkemper’s earlier proposal, referenced a delivery schedule but did not attach one. ¶ 14. Rehkemper, already concerned about the ongoing delay and with growing apprehension over the sudden rise in lumber prices, revised portions of the Mid- Id. Rivers proposal to provide that any agreement be contingent on a “mutually agreeable delivery schedule.” ¶¶ 15, 16. Mid-Rivers approved the revised proposal (the Contingent Id. Agreement) and specifically initialed three separate provisions indicating that the agreement was contingent on a “mutually agreeable schedule.” ¶ 17; Pl. Ex. 1 at 2, 5. According to Rehkemper, however, Mid-Rivers intentionally omitted an attachment that Id. normally included the delivery schedule, with specific commencement and completion dates, because they were still not ready to proceed with the project. ¶¶ 17, 18. There was only Id. one deadline set forth in the Contingent Agreement: “Rehkemper’s ‘work is to be completed no later than March 25, 2022 (the Completion Date).” ¶ 20; Pl. Ex. 1. Id. Once the Contingent Agreement was made in September 2020, the parties began Id. negotiating the delivery schedule. ¶ 21. Negotiations apparently continued for months, until Mid-Rivers “emerged and demanded immediate delivery” in February 2021. ¶ 22. Id. Between March 2020 and February 2021, lumber prices had risen between 200% and nearly Id. 300%. On February 12, 2021, Rehkemper submitted a proposed delivery schedule that Id. accounted for the change in lumber prices. ¶ 23. Mid-Rivers rejected the proposal and Id. demanded that Rehkemper “confirm the contract will be honored.” ¶ 24; Pl. Ex. 2. A week later, Mid-Rivers requested that Rehkemper provide proposed delivery dates. ¶ 25. Id. Rehkemper responded by proposing that the parties discuss a mutually agreeable delivery Id. schedule that would account for the increase in lumber prices and ongoing project delay. ¶ 26. Mid-Rivers again rebuffed Rehkemper’s suggestion. ¶ 27. On February 25, 2021, Rehkemper submitted a “final proposal” to Mid-Rivers that Id. offered two delivery alternatives, both of which would meet the original agreement’s final completion deadline of March 25, 2022. ¶ 28. The first option offered to meet Mid-Rivers’ expedited delivery schedule in exchange for an adjustment reflecting the increased lumber Id. prices, “plus a $700,000 good faith discount to be applied by Rehkemper to Mid-Rivers’ overall cost.” ¶ 29. The second option offered to maintain the original price in exchange Id. Id. for delivery beginning January 20, 2022, and completion by the March 25, 2022, deadline. Id. The parties made a last-ditch effort to negotiate in person but were unable to reach a Id. mutually agreeable delivery schedule. ¶ 32. On March 12, 2021, negotiations having failed, Rehkemper declared the Contingent Agreement null and void. ¶ 33. Rehkemper then brought this state law claim for declaratory judgment under Mo. Rev. Stat. § 527.020. Rehkemper believes that the product delivery schedule was an Id. essential term of the Contingent Agreement, and because it was reserved for future determination and never agreed to, there was no valid contract. ¶¶ 55-56. Alternatively, Id. Rehkemper argues that the mutually agreeable delivery schedule term established a condition precedent that was not met, rendering the agreement unenforceable. ¶¶ 57- 61. As relief, Rehkemper requests that the Court declare that the Contingent Agreement lacked an essential term or, alternatively, contained an unfulfilled condition precedent, and hold that the agreement is unenforceable. Mid-Rivers now moves to dismiss the Complaint under Federal Rule of Civil Procedure 12(b)(6), arguing that the Complaint fails to state a claim upon which relief can be granted. Doc. 4 at 1. For the reasonLsE GthAaL tS fToAllNoDwA,R tDh e Motion is denied. The purpose of a motion to dismiss under Federal Rule of Civil Procedure 12(b)(6) is to test the legal sufficiency of a complaint. When considering a Rule 12(b)(6) motion, a court Neitzke v. Williams Braden v. Wal- assumes the factual allegations of a complaint are true and draws all reasonable inferences Mart Stores, Inc in the non-movant’s favor. , 490 U.S. 319, 326-27 (1989); ., 588 F.3d 585, 595 (8th Cir. 2009) (citation omitted). Bell Federal Rule of Civil Procedure 8(a)(2) provides that a complaint must contain “a Atlantic Corp. v. Twombly short and plain statement of the claim showing that the pleader is entitled to relief.” In , the Supreme Court clarified that Rule 8(a)(2) requires complaints Ashcroft v. Iqbal to contain “more than labels and conclusions, and a formulaic recitation of the elements of a cause of action will not do.” 550 U.S. 544, 555 (2007); accord , 556 U.S. 662, 678-79 (2009). Specifically, to survive a motion to dismiss, a complaint must “contain Iqbal Twombly sufficient factual matter, accepted as true, to ‘state a claim to relief that is plausible on its face.’” , 556 U.S. at 678 (quoting , 550 U.S. at 570). The issue in considering SeeTwombly such a motion is not whether the plaintiff will ultimately prevail, but whether the plaintiff is DISCUSSION

Although not briefed by the parties, this case poses the question of whether and how a federal court may adjudicate a cause of action brought under a state declaratory judgment statute. The Court has diversity jurisdiction over Rehkemper’s state law claim under 28 U.S.C. § 1332. “[A] federal court adjudicating a state-created right solely because of the Guaranty Trust Co. of N.Y. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Aetna Life Insurance v. Haworth
300 U.S. 227 (Supreme Court, 1937)
Erie Railroad v. Tompkins
304 U.S. 64 (Supreme Court, 1938)
Maryland Casualty Co. v. Pacific Coal & Oil Co.
312 U.S. 270 (Supreme Court, 1941)
Neitzke v. Williams
490 U.S. 319 (Supreme Court, 1989)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Braden v. Wal-Mart Stores, Inc.
588 F.3d 585 (Eighth Circuit, 2009)
Missouri Soybean Ass'n v. Missouri Clean Water Commission
102 S.W.3d 10 (Supreme Court of Missouri, 2003)
Northgate Apartments v. City of North Kansas City
45 S.W.3d 475 (Missouri Court of Appeals, 2001)
Levinson v. State
104 S.W.3d 409 (Supreme Court of Missouri, 2003)
Mercantile Trust Company v. Chase Hotel, Inc.
510 S.W.2d 807 (Missouri Court of Appeals, 1974)
Jones v. Carnahan
965 S.W.2d 209 (Missouri Court of Appeals, 1998)
Fidelity Nat. Title v. Captiva Lake Investments
788 F. Supp. 2d 970 (E.D. Missouri, 2011)
National Railroad Passenger v. Consolidated Rail Corp.
670 F. Supp. 424 (District of Columbia, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
Rehkemper & Sons, Inc. v. Mid-Rivers Development and Construction LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rehkemper-sons-inc-v-mid-rivers-development-and-construction-llc-moed-2021.