Reeves Construction & Supply, Inc. v. Corrigan

24 So. 3d 1077, 2010 Miss. App. LEXIS 1, 2010 WL 11188
CourtCourt of Appeals of Mississippi
DecidedJanuary 5, 2010
Docket2008-CA-01072-COA
StatusPublished
Cited by12 cases

This text of 24 So. 3d 1077 (Reeves Construction & Supply, Inc. v. Corrigan) is published on Counsel Stack Legal Research, covering Court of Appeals of Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reeves Construction & Supply, Inc. v. Corrigan, 24 So. 3d 1077, 2010 Miss. App. LEXIS 1, 2010 WL 11188 (Mich. Ct. App. 2010).

Opinion

ROBERTS, J.,

for the Court.

¶ 1. This appeal evolved from a dispute involving a contract between Reeves Construction Company, Inc. (Reeves, Inc.) and Kate Corrigan for repair work that Reeves, Inc. was to perform on Corrigan’s home in Hattiesburg, Mississippi. After Reeves, Inc. had performed a portion of the work contemplated by the contract, a dispute arose, and as a result, Corrigan refused to pay Reeves, Inc. for any further work. Ken Reeves, the principal owner of Reeves, Inc., filed a notice of construction lien against Corrigan’s property. Reeves did not file the notice of construction lien in his capacity as an agent of Reeves, Inc. Instead, Reeves filed it under his own name as an individual. Corrigan sued Reeves, Inc. and “Ken Reeves d/b/a Reeves Construction.” Corrigan raised causes of action for breach of contract, false notice of a construction lien, and slander of title. Reeves responded with an answer and a counterclaim to enforce the previously-filed construction lien.

¶ 2. After other procedural matters, which will be discussed in greater depth as necessary, Corrigan filed a motion for summary judgment. Corrigan did not claim that she was entitled to summary judgment because Reeves could not demonstrate the existence of a genuine issue of material fact regarding his counterclaim. Instead, Corrigan claimed that she, as the plaintiff, was entitled to summary judgment incident to her claims for false notice of a construction lien and slander of title. After a hearing on the matter, the Forrest County Circuit Court found that it was undisputed that there was no contractual relationship between Reeves, individually, and Corrigan. Accordingly, the circuit court found that there was no genuine issue of material fact that Reeves “wrongfully” filed his notice of construction lien against Corrigan’s property. The circuit court went on to find that Corrigan was entitled to statutory damages against Reeves. However, the circuit court denied Corrigan’s request for summary judgment incident to Corrigan’s cause of action for slander of title. Reeves appeals and claims the circuit court erred when it granted Corrigan’s motion for summary judgment incident to her claim for false notice of a construction lien. However, after careful consideration, we find that the circuit court improvidently granted a final judgment pursuant to Mississippi Rule of Civil Procedure 54(b). Accordingly, we dismiss this appeal for lack of jurisdiction.

FACTS AND PROCEDURAL HISTORY

¶ 3. “Reeves Construction” submitted an estimate of $46,500 to perform numerous interior and exterior repairs of Corrigan’s home. Later, Reeves, Inc. and Corrigan *1080 entered into a contract for repair work to Corrigan’s home after her home sustained damage caused by Hurricane Katrina. Corrigan agreed to pay Reeves, Inc. $46,500. Among other things, Reeves, Inc. agreed to replace Corrigan’s roof. On February 15, 2006, Corrigan made a partial payment of $26,181.05 to “Reeves All Pro Roofing” for work that had been completed up to that time. On that same date, per Corrigan’s request, Reeves executed a release of lien for $26,181.05. The release of lien document was in the name of “Ken Reeves, All Pro Roofing” or “Reeves All Pro Roofing.”

¶ 4. The record is not entirely clear as to the events that transpired after February 15, 2006. However, it is clear that the relationship between Corrigan and Reeves soured. On March 2, 2006, Corrigan sent a letter to “Reeves All Pro Roofing.” In that letter, Corrigan referenced a letter that her daughter-in-law had sent to Reeves on February 23, 2006. That letter does not appear in the record. However, Corrigan’s March 2, 2006, letter indicated that it was a “list of work remaining and [a] punch list for [her] home.” Corrigan also stated that she had “requested [the] schedule by 26 February for completion of the work” and that “[t]o date, I have not received that schedule.” Additionally, Corrigan informed Reeves that he had “three days to complete this work or [he would] be released from [his] contract for non-performance.”

¶ 5. On March 4, 2006, Corrigan sent another letter to “Mr. Reeves” at “Reeves All Pro Roofing.” In that letter, Corrigan stated that: “As of the date of this letter[,] you are hereby dismissed from your responsibilities per our contract signed 25 January 2006 due to your default of the terms of the contract, failure to meet the schedule, and failure to perform the required work in the contract.” Corrigan also informed Reeves that he was “dismissed due to default in the terms of the contract by [his] failure to obtain a permit for the work on [Corrigan’s] home at the start of the job. [The] permit was not obtained until 3 March, well after the start of the work in January 2006 and the completion of the roof and structural [sic] on 15 February 2006.” Corrigan included a list of repairs that she considered incomplete. Corrigan went on to state that “[t]he balance of payment to Reeves as of the date of this letter is $10,148.16, which includes the siding and the above outstanding items.”

¶ 6. According to the record, the next notable event occurred on March 9, 2006, when Reeves filed a notice of construction lien against Corrigan’s property for $12,450. Reeves, acting pro se, did not file the notice of construction lien on behalf of Reeves, Inc. or “Reeves All Pro Roofing.” Instead, Reeves filed on behalf of “Ken Reeves d/b/a Reeves Construction.”

¶7. Approximately five months later, Corrigan filed a complaint in the Forrest County Chancery Court. As mentioned, Corrigan raised causes of action for breach of contract, false notice of a construction lien, and slander of title. Reeves responded with an answer and a counterclaim to enforce the previously-filed construction lien. A portion of Reeves’s response stated that Reeves had “suffered a loss of expectation interest of future wealth which would have been gained had [Corrigan] not breached the contract.” Reeves also moved to transfer all matters to the Forrest County Circuit Court. The chancellor granted Reeves’s motion and transferred all claims to the circuit court. However, before the claims were transferred to the circuit court, Reeves agreed to cancel the construction lien and filed a lis pendens notice on Corrigan’s property, thus disposing of Reeves’s counterclaim to enforce his *1081 construction lien. The chancellor subsequently entered an order cancelling Reeves’s notice of construction lien.

¶ 8. On March 25, 2008, Corrigan next filed a motion for summary judgment. On April 18, 2008, the circuit court conducted a hearing on Corrigan’s motion. Approximately one month later, the circuit court entered its opinion on Corrigan’s motion. Specifically, the circuit court found as follows:

The Court is of the opinion and does find that Defendant Ken Reeves individually was under a duty and obligation to distinguish the contractual relationship with Plaintiff as between Plaintiff and the Reeves Corporation and Ken Reeves d/b/a Reeves Construction. The issue of no contractual relationship between Plaintiff and Ken Reeves d/b/a Reeves Construction is undisputed and the Court finds that there is no dispute as to the lack of contractual relationship in this case between Plaintiff Kate Corri-gan and Defendant Ken Reeves d/b/a Reeves Construction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Davis Davenport v. Hertz Rental Equipment Corporation
187 So. 3d 194 (Court of Appeals of Mississippi, 2016)
Northeast Mental Health-Mental Retardation Commission v. Cleveland
126 So. 3d 1020 (Court of Appeals of Mississippi, 2013)
Stathos v. Lee County Rentals, LLC
119 So. 3d 377 (Court of Appeals of Mississippi, 2013)
Cook v. Wallot
172 So. 3d 788 (Court of Appeals of Mississippi, 2013)
Chevis v. Mississippi Farm Bureau Mutual Insurance
76 So. 3d 187 (Court of Appeals of Mississippi, 2011)
R.A.S. v. S.S.
66 So. 3d 1257 (Court of Appeals of Mississippi, 2011)
Ras, Jr. v. Ss
66 So. 3d 1257 (Court of Appeals of Mississippi, 2011)
Golliday v. Patel
58 So. 3d 1221 (Court of Appeals of Mississippi, 2011)
Miller v. Continental Mineral Processing
39 So. 3d 998 (Court of Appeals of Mississippi, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
24 So. 3d 1077, 2010 Miss. App. LEXIS 1, 2010 WL 11188, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reeves-construction-supply-inc-v-corrigan-missctapp-2010.