Red Rooster Constr. Co. v. River Assoc., No. 29 06 33 (Jul. 2, 1991)

1991 Conn. Super. Ct. 5981
CourtConnecticut Superior Court
DecidedJuly 2, 1991
DocketNo. 29 06 33
StatusUnpublished

This text of 1991 Conn. Super. Ct. 5981 (Red Rooster Constr. Co. v. River Assoc., No. 29 06 33 (Jul. 2, 1991)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Red Rooster Constr. Co. v. River Assoc., No. 29 06 33 (Jul. 2, 1991), 1991 Conn. Super. Ct. 5981 (Colo. Ct. App. 1991).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.] MEMORANDUM OF DECISION The plaintiff brought this action to foreclose a mechanic's lien on property of the defendant, River Associates, Inc. At the onset of trial, the defendants, River Associates, Inc. and Kenneth Kraus, stipulated as to the amount owing for services performed by the plaintiff and did not participate further in the trial. The defendant, Connecticut Savings Bank ("CSB") and the defendant, Connecticut Attorneys Title Insurance Corp. (CATIC), as surety under a bond substituted for the mechanic's lien, defended the action contending, in essence, that, because the mechanic's lien is invalid, CSB has priority by virtue of its mortgage.

Based on a preponderance of the evidence, the court finds the following facts proven.

In 1987, River Associates, Inc. owned a parcel of land on the Quinnipiac River, in New Haven. At that time, Red Rooster Construction Company was a building contractor which had conducted business for approximately seventeen years in the Greater New Haven Area.

In April, 1987, River Associates, Inc. and Red Rooster began negotiations for the construction of residential condominium units and a commercial building on said premises. Red Rooster was to act as the general contractor and River Associates, as the developer.

In September, 1987, Red Rooster entered into an agreement with River Associates and the defendant, Kenneth Kraus, by the terms of which Red Rooster agreed to construct 26 residential condominium units and approximately 4,000 square feet of commercial space on land owned by River Associates at 660 Quinnipiac Avenue in New Haven (the "Project") for the contract price of $3,376,985.14.

The Declaration of Condominium was recorded on the Land CT Page 5982 Records of the City of New Haven on July 5, 1989.

Red Rooster commenced construction on September 30, 1987 and worked continuously until August 23, 1989 when River Associates directed Red Rooster to stop work because the decline in the economy made the Project economically unfeasible.

Red Rooster furnished said materials and services with the consent of River Associates and Kenneth Kraus and pursuant, to an agreement with River Associates.

No written contract was ever executed although two separate draft contracts were prepared and reviewed by the parties. On March 31, 1988, a final schedule of values was in place. Buildable drawings were finalized in February, 1988.

In September, 1987, Red Rooster was aware that Connecticut Savings Bank would be the construction lender. On February 3, 1988, Connecticut Savings Bank loaned money to River Associates, secured by a construction mortgage on the premises dated February 3, 1988 and recorded February 4, 1988.

Between September 30, 1987 and August 23, 1989, Red Rooster had submitted ten requisitions to River Associates. River Associates paid the first eight requisitions which totalled $1,440,451.78, but not requisitions 9 and 10 which totalled $258,402.36.

Accompanying requisitions 2 through 6 were written mechanic's lien waivers prepared by Red Rooster. The lien waivers, preprinted forms modified by typed language limiting the waivers to specific time periods, indicated the plaintiff's intent to waive rights only as to work performed as of the date of execution of the waiver. CSB did not rely on a general waiver when advancing funds.

On September 25, 1989, after River Associates advised Red Rooster that it did not have the funds to pay these two requisitions, Red Rooster filed a mechanic's lien against the Project to secure payment of its claim.

The mechanic's lien, which was filed to secure payment for the materials and services furnished in the construction of the buildings, is recorded in Volume 148 at Page 95 of the New Haven Land Records. A copy of the certificate of mechanic's lien was served on River Associates, an owner, but not on CSB. There was no evidence of the filing of a lis pendens at any time.

During the course of construction, Red Rooster's work was done at the direction of River Associates. In August, 1989, at CT Page 5983 the direction of River Associates, Red Rooster ceased to work at the premises. Red Rooster stipulated on the record that, if successful, it would not seek to recover from Connecticut Savings Bank on the bond, but would limit recovery to a demand on CATIC.

By its note dated February 3, 1988, River Associates promised to pay to the order of CSB the principal sum of $1.8 million, payable with interest thereon as provided in the note.

By deed of February 3, 1989, River Associates, to secure the note, mortgaged to CSB the above property of which it was then the record owner. The deed is conditioned on the payment of the note according to its tenor and the performance of certain covenants and conditions contained in the mortgage deed. The mortgage deed was dated February 3, 1988, and recorded February 4, 1988 in Volume 3837 at Page 19 of the New Haven Land Records.

On February 3, 1988, CSB advanced $40,000 to River Associates under the construction loan. On October 17, 1988 CSB advanced $431,452.90 to River Associates under the construction loan. On December 23, 1988, CSB advanced $190,624.00 to River Associates under the construction loan.

On February 23, 1989, CSB advanced $211,662.00 to River Associates under the construction loan. On April 10, 1989, CSB advanced $238,425.00 to River Associates under the construction loan. On June 13, 1989, CSB advanced $169,174.00 to River Associates.

On July 3, 1989, CSB released its mortgage as to Unit C-1 only. On July 6, 1989, River Associates conveyed Unit C-1 to a third party.

On July 24, 1989, CSB advanced $183,468.00 to River Associates under the construction loan.

On or about August 20, 1989 River Associates advised Red Rooster that, because of the existing economic conditions, River Associates was suspending work on the buildings.

On October 16, 1989, Red Rooster commenced an action to foreclose its lien and named CSB as a party defendant. CSB claims an interest in the Project by virtue of a mortgage recorded on February 4, 1988, more than four months after Red Rooster commenced construction.

As of September 23, 1989 the outstanding balance on Requisitions 9 and 10 was $258,402.36.

Subsequently River Associates made an additional payment of CT Page 5984 $50,000.00 which reduced the unpaid contract balance to $208,402.36. On August 3, 1990, this court, Berdon, J., found there was probable cause to sustain the validity of the lien in the amount of $208,402.36.

Red Rooster is owed $208,402.36 for materials and services rendered in the construction of the Project.

The sole purpose intended by Red Rooster and River Associates for the delivery by Red Rooster of a lien waiver on July 5, 1989 was to release its right to claim a lien on Unit C-1. The lien was dissolved upon the substitution of a bond with CSB as principal and the Connecticut Attorneys' Title Insurance Company ("CATIC") as surety.

The bond provides, in relevant part:

NOW THEREFORE, if the Principal [CSB] shall pay to the Obligee [Red Rooster] or its assigns such amount as a court of competent jurisdiction may adjudge (i) to have been secured by Obligee's [Red Rooster's] Mechanic's Lien, and (ii) to have been prior in right under the Mechanic's Lien to the interest of the Principal's [CSB's] Mortgage on the Property, together with interest and costs and such attorney's fees as may be awarded by the Court, if any, all such amounts not exceeding, however, the amount of this bond, $325,000., then this bond shall be null and void, otherwise to remain in full force and effect.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

H & S TORRINGTON ASSOCIATES v. Lutz Engineering Co.
441 A.2d 171 (Supreme Court of Connecticut, 1981)
Henry F. Raab Connecticut, Inc. v. J. W. Fisher Co.
438 A.2d 834 (Supreme Court of Connecticut, 1981)
Rahmati v. Mehri
452 A.2d 638 (Supreme Court of Connecticut, 1982)
State v. Briggs
287 A.2d 369 (Supreme Court of Connecticut, 1971)
Papa v. Greenwich Green, Inc.
416 A.2d 1196 (Supreme Court of Connecticut, 1979)
Rossetti v. City of New Britain
303 A.2d 714 (Supreme Court of Connecticut, 1972)
State Ex Rel. McClure v. Northrop
106 A. 504 (Supreme Court of Connecticut, 1919)
Weinberg v. Valente
64 A. 337 (Supreme Court of Connecticut, 1906)
Townsend v. Barlow
124 A. 832 (Supreme Court of Connecticut, 1924)
Wilcox v. Woodruff
17 L.R.A. 314 (Supreme Court of Connecticut, 1891)
Hillhouse v. Duca
125 A. 367 (Supreme Court of Connecticut, 1924)
Bell & Zajicek, Inc. v. Heyward-Robinson Co.
182 A.2d 339 (Connecticut Superior Court, 1962)
Meyer, Kasindorf & Mancino, Architects v. Lafayette Bank & Trust Co.
377 A.2d 861 (Connecticut Superior Court, 1977)
Resnik v. Russell
5 Conn. Super. Ct. 146 (Connecticut Superior Court, 1937)
Camputaro v. Stuart Hardwood Corp.
429 A.2d 796 (Supreme Court of Connecticut, 1980)
Warner v. Leslie-Elliott Constructors, Inc.
479 A.2d 231 (Supreme Court of Connecticut, 1984)
Kelemen v. Rimrock Corp.
542 A.2d 720 (Supreme Court of Connecticut, 1988)
Bialowans v. Minor
550 A.2d 637 (Supreme Court of Connecticut, 1988)
J. C. Penney Properties, Inc. v. Peter M. Santella Co.
555 A.2d 990 (Supreme Court of Connecticut, 1989)
A. Dubreuil & Sons, Inc. v. Town of Lisbon
577 A.2d 709 (Supreme Court of Connecticut, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
1991 Conn. Super. Ct. 5981, Counsel Stack Legal Research, https://law.counselstack.com/opinion/red-rooster-constr-co-v-river-assoc-no-29-06-33-jul-2-1991-connsuperct-1991.