Hillhouse v. Duca

125 A. 367, 101 Conn. 92, 1924 Conn. LEXIS 95
Supreme Court of Connecticut·Decided June 30, 1924·Published·Cited by 15 cases

Opinion

Keeler, J.

The appellants attack the judgment of the court in twelve reasons of appeal which are identical in form and claim, and the appellant Kennedy files two additional reasons of appeal assigning error as to the finding by the court as to the date of the commencement of his lien, and in ruling that he was not entitled to interest on his claim. We will first consider these claims. The committee in his report, accepted by the court, expressly finds as a fact that the work by Kennedy upon the Highland Apartments began April 10th, 1920, which date, of course, fixes the time of commencement of the lien. Kennedy claimed that he began work October 6th, 1919, basing his claim upon the fact found by the committee that on the date last mentioned he cut out and removed pipes from the old house before the same was moved and while situated upon the Granite Street lot to be stored and eventually again used in the same house when moved to the Bristol Street lot, although in fact they were not so used. No further work was done upon the Granite Street lot or any building thereon until April 10th, 1920. The find *101 ing is one of fact by the committee, and no remonstrance was filed by Kennedy to the committee’s report. The plaintiffs therefore contend that the finding concludes the matter. Kennedy claims that the finding is one of mixed law and fact, that is, that the finding of the date of April 10th, 1920, as the commencement of the lien is dependent upon the subordinate facts found with reference to the work done in October, 1919. Assuming this defendant to be correct in this regard, the finding of the date in April, 1920, is clearly justified by all subordinate facts. The cutting, removal and storage of pipe to be used later in the same building when removed to another lot, is not work upon a new building begun on the former site of the old house six months afterward, nor so connected with any such work as to form any basis for a claim of lien on the new building, and the fact was correctly found by the committee. As regards the question of interest entering into the total amount claimed by Kennedy, it appears that the committee found certain facts with reference thereto, but stated no conclusion, and that the court, having found that Kennedy had no claim whatever by way of lien, was not concerned to find the amount of the owners’ indebtedness to him; and as the conclusion we have reached will not result in that task being assumed by another judge, the matter becomes academic and immaterial. The court committed no error in respect to these reasons of appeal.

Ten of the remaining twelve reasons of appeal fall into two groups, the first, second, third, sixth and ninth relating to the construction and validity of the waiver of lien executed by appellants as determined by its form and content in view of the circumstances surrounding its execution; the fourth, fifth, seventh, eighth and tenth are concerned with a claim that plaintiffs are not entitled to the benefit of the waiver of liens, by *102 reason of conduct on their part which estops them from so doing.

Taking up the claims of appellants as outlined in the first group of reasons of appeal just noted, we find the contention that the object of the waiver as disclosed in the negotiations preceding its execution indicated an understanding and intent that the liens of the parties executing the waiver were only so far to be affected as to subordinate them to the mortgages which Lomas & Nettleton and the Land, Mortgage and Title Company proposed to take from the owners, leaving the rights and claims of all lienors as between themselves unaffected thereby. In construing any instrument we' have recourse to the negotiations and other circumstances attendant upon its execution. In Weinberg v. Valente, 79 Conn. 247, 249, 64 Atl. 337, we said, in considering the construction and consequent effect of a waiver of lien, that “it is necessary to consider the words employed by the parties ... in the light of the object which they had in view while employing them.”

First considering the words employed by the parties in the instant case, we find in the instrument as executed an absolute and unqualified waiver and relinquishment of all liens and claims of lien which the signers had or might thereafter have upon the land described and all buildings thereon, making use of a form readily recognizable as in frequent use for such a purpose. This is conceded by appellants, who contend, .however, that the instrument, viewed in connection with surrounding circumstances, must be construed as limited to a waiver in favor of the proposed mortgagees. Under the claim made this object is to be effected not by giving some meaning to words employed, different from their apparent import, but by reading into the instrument itself an additional clause limiting its effect in accordance with appellants’ claim. It is *103 extremely doubtful whether the object sought could legally be brought about in this way. In doing so we should enter the domain of reformation for which no claim is made in the pleadings, and for which the record does not afford the necessary findings of fact.

Free access — add to your briefcase to read the full text and ask questions with AI

Hillhouse v. Duca, 125 A. 367, 101 Conn. 92, 1924 Conn. LEXIS 95 (Colo. 1924).

125 A. 367 (Hillhouse v. Duca) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Connecticut Concrete v. Arc Icesports, No. X01-Cv00-0160662 (Feb. 8, 2001)
2001 Conn. Super. Ct. 2173 (Connecticut Superior Court, 2001)
New England Savings Bank v. Meadow Lakes Realty Co.
706 A.2d 465 (Supreme Court of Connecticut, 1998)
Thompson & Peck, Inc. v. Division Drywall, Inc.
696 A.2d 326 (Supreme Court of Connecticut, 1997)
Calabrese Development Corp. v. Carpinella, No. 90341 (Jun. 16, 1992)
1992 Conn. Super. Ct. 5449 (Connecticut Superior Court, 1992)
Pds Engineering Const. v. Double Rs, No. Cv90-0378684 (Dec. 19, 1991)
1991 Conn. Super. Ct. 10306 (Connecticut Superior Court, 1991)
Red Rooster Constr. Co. v. River Assoc., No. 29 06 33 (Jul. 2, 1991)
1991 Conn. Super. Ct. 5981 (Connecticut Superior Court, 1991)
Red Rooster Constr. Co. v. River Assoc., No. 29 06 33 (Aug. 2, 1990)
1990 Conn. Super. Ct. 1543 (Connecticut Superior Court, 1990)
Camputaro v. Stuart Hardwood Corp.
429 A.2d 796 (Supreme Court of Connecticut, 1980)
Lundstrom Construction Co. v. Dygert
94 N.W.2d 527 (Supreme Court of Minnesota, 1959)
Bland v. Bregman
192 A. 703 (Supreme Court of Connecticut, 1937)
Bridgeport People's Savings Bank v. Palaia
161 A. 526 (Supreme Court of Connecticut, 1932)
Siller v. Philip
141 A. 872 (Supreme Court of Connecticut, 1928)
Persky v. Puglisi
127 A. 351 (Supreme Court of Connecticut, 1925)
Townsend v. Barlow
124 A. 832 (Supreme Court of Connecticut, 1924)