Red River Waterway Com'n v. Fredericks
This text of 566 So. 2d 79 (Red River Waterway Com'n v. Fredericks) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
RED RIVER WATERWAY COMMISSION
v.
Marjorie M. FREDERICKS, et al.
Supreme Court of Louisiana.
*80 Daniel Regard, for Marjorie M. Fredericks, et al., defendant-applicant.
Henry Bruser, III, Randall L. Wilmore, for Red River Waterway Comm., plaintiff-respondent.
LEMMON, Justice.[*]
This is an expropriation action filed by the Red River Waterway Commission, a subdivision of the State, to acquire in full ownership a strip of land across a larger parcel owned by defendants. Certiorari was granted to review the appellate court's reversal of the trial court's finding that the Commission's decision to expropriate defendants' property was arbitrary, capricious and in bad faith.
The construction of Lock & Dam No. 3 was part of an extensive federal-state joint project between the United States Corps of Engineers and the Commission to construct locks and dams along the Red River. Secondary goals of the project were to stabilize the banks of the river, to develop hydroelectric power at the lock and dam sites, and to install recreational facilities in the area. Part of the responsibility of the Commission in the project was to provide servitudes and utility alterations in connection with the project and to pay fifty percent of the cost of, as well as to operate and maintain, any recreational area that may be developed.
The purpose of the expropriation of defendants' property was to acquire a route for building a permanent access road to Lock and Dam No. 3.
In the planning stages of the construction of Lock and Dam No. 3, officials of the Corps and of the Commission met many times, beginning as early as 1984. The Corps, which had previously constructed Lock and Dam Nos. 1 and 2 along the river, outlined its needs for access roads to the site, and investigation was begun of several routes. However, in using an existing substandard road to construct Lock and Dam No. 1, the Commission had encountered many problems when the transportation of building materials and heavy equipment destroyed the road and severely limited access by the local residents to their homes. The Corps and Commission therefore decided to build a modern updated road prior to the beginning of construction of Lock and Dam No. 3.
Access from U.S. Highway 1 on the south was considered along three routes, referred to for purposes of this opinion as the La. Highway 490 route, the Ridge route, and the Lena route. The three *81 routes are shown on the following annotated exhibit:
The first route considered was the Highway 490 route along a public road which provided existing access from Highway 1 to the site. The Commission rejected that route for the following reasons: use of Highway 490 would be unsafe for local residents whose homes were very close to the existing road; the present road was substandard and incapable of supporting the heavy construction traffic and anything more than the existing light residential traffic; the roadway and the servitude were too narrow, and the passing sight distances, the stopping sight distances, the steep grades of the hills, and the vertical curves made the route unsafe for any significant volume of heavy traffic; new servitudes would be required to widen the road *82 and reduce the grades; and a 230-foot bridge was unsafe and had to be replaced. Being anxious to avoid the expense of building bridges along any route selected, the Commission decided to pursue acquiring access along the Ridge route, which was a private road along a ridge line developed and maintained by the owners of the several parcels of land along the route.
After extensive engineering and design work for the Ridge route had been performed, several citizens from the Lena community suggested to the Commission in March, 1986 that the Lena route be considered. The Commission's investigation determined that there was no recorded servitude for the route, which was primarily an overgrown trail across bottom land that was being used only by hunters on all-terrain vehicles. There was also a 600-foot flood plain across Davis Creek which would require a bridge and a large embankment, and a large culvert would be required at another creek. The estimated cost of using the Lena route, although far less than the Highway 490 route, was $208,500 more than the shorter Ridge route. Because of the greater cost, because $140,000 had already been spent on engineering work for the Ridge route, and because a change of routes would cause extensive delays in the overall project (since construction of the road had to be completed prior to commencement of construction of the lock and dam), the Lena route was rejected. Accordingly, the Commission in mid-1986 proceeded with servitude acquisitions along the Ridge route.
In January, 1987, the Corps informed the Commission that final authority and funding had been received for the $165,000,000 Lock and Dam No. 3 project and that permanent servitudes would be required for access roads from both north and south. The Corps indicated that since permanent access roads were needed for project purposes and would be maintained by the federal government, full ownership of the route should be acquired and title subsequently conveyed to the United States.
When the Commission was unsuccessful in negotiations to purchase the property from defendants, the present action was filed pursuant to La.Rev.Stat. 34:2309(4), which authorized the Commission to expropriate property for Lock and Dam Nos. 3, 4 and 5, but not for recreational purposes, by using the expropriation procedure in La. Rev.Stat. 48:441-48:460, the highway quick-taking statute.[1]
After the trial judge signed the order of expropriation, two of the defendants filed a timely motion to vacate the order, contesting among other things the necessity of the taking. The trial court, following a hearing on the motion, ruled that the Commission had acted arbitrarily in determining that the existing Highway 490 servitude was inadequate and that a new route across defendants' property was necessary. The court noted that Highway 490 was a hard-surfaced road of sufficient width to accomodate large trucks and was at that time being used by maximum load trucks in the logging industry. The court concluded that the Commission did not have a reasonable basis for expropriating the proposed route, which was merely a short cut from Highway 1 to a point along Highway 490 closer to the project.
The court of appeal reversed. 546 So.2d 904. Pointing to evidence that it was less expensive to construct a new road across the Ridge route than to improve either of the existing roads so as to provide adequate access, the court held that the Commission's decision was not arbitrary, capricious or in bad faith.
We granted certiorari to consider the issues of (1) the necessity of expropriating a new route across defendants' property when there were existing roadways on either side of the proposed route and (2) the necessity of expropriating anything more than a construction servitude. 551 So.2d 1309.
The highway quick-taking statute, which was patterned after the Federal Declaration *83 of Taking Act, 40 U.S.C. § 258a
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
566 So. 2d 79, 1990 La. LEXIS 1462, 1990 WL 109600, Counsel Stack Legal Research, https://law.counselstack.com/opinion/red-river-waterway-comn-v-fredericks-la-1990.