Red Hill Farm Trust v. Schregardus

656 N.E.2d 1010, 102 Ohio App. 3d 90, 1995 Ohio App. LEXIS 1051
CourtOhio Court of Appeals
DecidedMarch 23, 1995
DocketNo. 94APH07-1046.
StatusPublished
Cited by9 cases

This text of 656 N.E.2d 1010 (Red Hill Farm Trust v. Schregardus) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Red Hill Farm Trust v. Schregardus, 656 N.E.2d 1010, 102 Ohio App. 3d 90, 1995 Ohio App. LEXIS 1051 (Ohio Ct. App. 1995).

Opinion

*93 Peggy Bryant, Judge.

Appellant, Red Hill Farm Trust (“RHF”), appeals from a decision of the Ohio Environmental Board of Review (“EBR”) upholding an order issued by appellee, Donald R. Schregardus, Director of the Ohio Environmental Protection Agency (“director”), which requires RHF to cease construction of all animal waste “disposal systems” until such time as it has received permits to install all such systems.

RHF owns a large tract of land located along State Route 22 in Guernsey County, Ohio, upon which it intends to operate a factory dairy farm. The farm as planned will include animal confinement barns, a milking operation, and a system for treating and storing animal waste generated at the farm; the treated animal waste, in turn, will be applied to the farm acreage in producing cattle feed. Construction on the project began during the summer or fall of 1990. However, the Ohio Environmental Protection Agency (“OEPA”) did not become aware of the project until sometime later when a nearby resident notified the OEPA that a large-scale farming operation was under construction at the RHF site.

On November 1, 1990, officials from OEPA’s Southeast District Office inspected the farm site and met with RHF’s manager for the project. OEPA’s inspection revealed that excavation for an animal waste disposal system and animal barns was well under way, and that RHF projected a herd size for the facility of four thousand dairy cattle -within ten years. Based on that information, OEPA informed RHF that it was required to obtain a permit to install the animal waste disposal system, and that to obtain the permit, RHF must submit an application together with comprehensive and detailed plans and specifications for the project.

Over the next eighteen months, OEPA repeatedly requested that RHF apply for a permit to install its animal waste disposal system. RHF, however, failed to comply with OEPA’s requests, arguing that it had reduced the number of cattle that it intended to place at the dairy farm, thus bringing its disposal system within a small-farm exception to the permit requirement. Despite RHF’s claimed reduction in the size of its projected herd, no similar reduction was made in the size of the facilities being constructed at the site. Consequently, pursuant to R.C. Chapter 6111, the director, on April 22, 1992, issued orders requiring RHF (1) to immediately cease construction of all disposal systems, and (2) to apply for permits to install such systems not later than ninety days from the effective date of the director’s order.

RHF appealed the director’s orders to the EBR on May 11, 1992, and a de novo evidentiary hearing on the merits of RHF’s appeal was held the following September. At the hearing, the director alleged that RHF was in the process of *94 constructing two animal waste “disposal systems” 1 for which it has not acquired permits to install as required by R.C. 6111.44, 6111.45 and Ohio Adm.Code 3745-31-02: a manure digester/storage system consisting of four large, mechanically stirred, heated, underground tanks, as well as an animal waste holding lagoon. RHF responded that because it now intended to place only four hundred cattle at its dairy farm, any disposal systems constructed to serve the farm were excepted from the permit requirement pursuant to R.C. 6111.03(R) and 6111.44. It further denied that it was building an animal waste storage lagoon at the farm.

On April 27, 1993, the EBR issued a final order affirming the director’s order. The EBR’s order was issued, however, with only two of its three board members participating: one member authored the order, and the second dissented. The third member of the EBR did not participate in the decision because she was not a member of the board at the time of the de novo hearing. On RHF’s appeal, this court reversed the board’s order, finding that it was invalid due to the absence of a two-member concurrence as required by R.C. 3745.02. However, concluding that the third member’s absence from the de novo hearing did not prevent her from participating in the decision as long as she first reviewed and examined the record of the hearing, this court remanded the matter to the EBR for an order in which at least two board members concurred. Red Hill Farm Trust v. Schregardus (Mar. 15, 1994), Franklin App. No. 93AP-749, unreported, 1994 WL 85316.

On remand, the third board member “thoroughly reviewed and examined the record and transcript of proceedings,” and on June 21, 1994, the EBR issued a second final order affirming the orders of the director, this time with two board members concurring in the decision. RHF appeals, assigning the following errors:

“I. The Environmental Board of Review erred as a matter of law in holding that Section 6111.03(H), Revised Code, authorizes the director to issue an enforcement order requiring cessation of construction of a facility for failure to obtain a permit to install.

“II. The Environmental Board of Review erred as a matter of law in holding that a livestock barn and associated waste management facilities for four hundred cows (five hundred sixty animal units) are not within the exemption from the requirement to obtain a permit to install afforded by law to facilities involving less than one thousand animal units.

*95 “III. The Environmental Board of Review erred as a matter of law in holding that a recipient of an enforcement order issued by the director bears the burden of proof before the EBR that the violations of law alleged in the order did not occur.

“IV. The Environmental Board of Review erred in concluding that the evidentiary record contained a valid factual foundation supporting the allegation by the director in the enforcement order that Red Hill Farm was constructing an animal waste holding lagoon.”

Preliminarily, in reviewing a decision of the director, the EBR is limited to considering whether the director’s action was unreasonable or unlawful, given the evidence presented at the de novo hearing; it may not substitute its judgment for that of the director as to factual determinations. CECOS Internatl., Inc. v. Shank (1992), 79 Ohio App.3d 1, 6, 606 N.E.2d 973, 977; see R.C. 3745.05. In contrast, an appellate court is charged with determining whether the EBR’s decision concerning the reasonableness and lawfulness of the director’s decision is supported by reliable, probative and substantial evidence and is in accordance with law. Id.; see R.C. 3745.06.

Under those parameters, we first address RHF’s second and third assignments of error, as together they raise the issue of whether the disposal systems being installed by RHF are statutorily excepted from the requirement of OEPA approval prior to installation.

Taken together, R.C. 6111.44, 6111.45 and Ohio Adm.Code 3745-31-02 prohibit the installation of any new disposal systems until the OEPA director has approved the plans for the systems and issued a permit to install. 2 R.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
656 N.E.2d 1010, 102 Ohio App. 3d 90, 1995 Ohio App. LEXIS 1051, Counsel Stack Legal Research, https://law.counselstack.com/opinion/red-hill-farm-trust-v-schregardus-ohioctapp-1995.