City of Salem v. Koncelik

843 N.E.2d 799, 164 Ohio App. 3d 597, 2005 Ohio 5537
Ohio Court of Appeals·Decided October 20, 2005·No. No. 05AP-50.·Published·Cited by 8 cases

Opinion

Brown, Presiding Judge.

{¶ 1} The city of Salem, appellant, appeals from an order of the Environmental Review Appeals Commission (“ERAC”), in which the ERAC affirmed the action of Joseph P. Koncelik, Director of Environmental Protection (“Director”), appellee, in issuing to Salem a National Pollutant Discharge Elimination System (“NPDES”) renewal permit with certain restrictions.

{¶ 2} Salem owns and operates á municipal wastewater-treatment plant (“WWTP”) that, pursuant to a permit issued by the Ohio Environmental Protection Agency (“OEPA”), discharges effluent into the Middle Fork of Little Beaver Creek (“Middle Fork”) at approximately River Mile (“RM”) 38.2. In 1999, the OEPA conducted a routine stream survey, during which it performed biological and chemical sampling of the Middle Fork. As a result of the sampling, the OEPA discovered that the concentrations of phosphorus immediately downstream from the WWTP increased dramatically. The OEPA found that at RM 38.3, which is immediately upstream from the WWTP, phosphorus was measured at 0.19, 0.08, and 0.1 milligrams per liter (“mg/1”). The OEPA also found that at RM 37.8, the first sampling location downstream from the WWTP, phosphorus was measured at concentrations from 8.6 to 17.0 mg/1. Phosphorus concentrations decreased as the river flowed downstream from the WWTP toward the mouth of Middle Fork. Further, the OEPA found that downstream from the WWTP, there existed considerable amounts of sewage solids, while similar solids were not seen in Middle Fork upstream of the WWTP.

{¶ 3} In addition, the OEPA evaluated the Middle Fork to determine whether the stream was attaining its designated uses, using two biological indices: the Index of Biotic Integrity (“IBI”) and the Modified Index of Well Being (“MIWB”). The 1999 stream survey indicated that the IBI and MIWB scores reflect that the Middle Fork was not meeting the biological criteria at numerous locations downstream from the WWTP. Further, lesions and fin erosions, which are associated with excessive nutrients, were also observed on fish in the Middle Fork.

{¶ 4} In February 2002, the OEPA issued a draft renewal permit to Salem. The draft renewal permit proposed 1.0 mg/1 weekly and 1.5 mg/1 monthly concentration limits along with loading limits for total phosphorus. With regard *600 to suspended solids, the draft renewal permit proposed a total suspended solids (“TSS”) limit on the Salem WWTP discharge that was more stringent than the one previously in place. The draft permit also proposed adding an effluent limit on conductivity and a monitoring requirement for total dissolved solids (“TDS”).

{¶ 5} On May 15, 2002, the parties met to discuss the draft permit, at which time Salem indicated that to install a tertiary filtration system to meet the proposed TSS limits would cost approximately $3.5 million and the cost to meet the proposed phosphorus limits would be approximately $1.3 million, with annual operating and maintenance costs of $185,000. The OEPA believed that a compromise had been reached in which it would agree not to impose the more stringent TSS limits^ if Salem agreed to the proposed phosphorus limits. The OEPA entered the agreement believing that the proposed phosphorus-treatment system would also resolve issues involving the TSS.

{¶ 6} On May 31, 2002, the OEPA, under the direction of the Director, issued a final renewal permit to Salem, which imposed the proposed limits on the amount of phosphorus that the WWTP could discharge into the Middle Fork. The final permit also contained TDS conductivity limits. However, the final permit did not impose the more stringent TSS limits proposed in the draft permit.

{¶ 7} On June 28, 2002, Salem appealed the renewal permit issued by the ERAC, but only with regard to the new limits imposed for phosphorus. On February 2 through February 4, 2004, a de novo hearing was held by the ERAC. On December 16, 2004, the ERAC issued its findings of fact, conclusions of law, and final order. In its order, the ERAC concluded that it did not consider the application and interpretation of Ohio Adm.Code 3745(A)(6)(b) because it was finding that the OEPA’s action comported with the legal authority granted to it by R.C. 6111.03(J)(3). The ERAC found that because the biological water quality standards were not being met in the Middle Fork, the OEPA was legally required by R.C. 6111.03(J)(3) to impose limits that are necessary and appropriate to achieve and maintain the applicable standards of water quality. Further, the ERAC found that the specific numeric limits imposed in Salem’s permit were necessary and appropriate because other WWTPs were meeting similar limits, and the technology required to comply with those limits was achievable by well-known treatment processes. Salem has appealed the ERAC’s order to this court, asserting the following assignments of error:

I. The Commission’s ruling that ORC § 6111.03(J)(3) provides sufficient legal authority for the imposition of the phosphorus limits in Salem’s permit, without reference to the factors specified in Ohio’s biological criteria regulation at OAC § 3745-l-07(A)(6)(b), is not in accordance with law.
II. The Commission’s failure to find that the Director’s action was precluded by the limitations set forth in OAC § 3745-l-07(A)(6)(b) was not supported *601 by reliable, probative and substantial evidence and is not in accordance with law.
III. The Commission’s finding that the specific numeric limits for phosphorus of 1.0 mg/1 (weekly) and 1.5 mgd (monthly) included in Salem’s NPDES permit were “necessary and appropriate” to achieve applicable water quality standards is not supported by reliable, probative and substantial evidence and is not in accordance with law.

{¶ 8} Salem argues in its first assignment of error that the ERAC’s ruling that R.C. 6111.03(J)(3) provides sufficient legal authority for imposing the phosphorus limits in Salem’s permit, without reference to the factors specified in Ohio’s biological criteria regulation at Ohio Adm.Code 3745-1-07(A)(6)(b), is not in accordance with law. This court is charged with determining whether the ERAC’s order as to the lawfulness and reasonableness of the Director’s action is supported by reliable, probative, and substantial evidence and is in accordance with law. Red Hill Farm Trust v. Schregardus (1995), 102 Ohio App.3d 90, 95, 656 N.E.2d 1010; R.C. 3745.06. Reliable evidence is evidence that can be trusted. Our Place, Inc. v. Ohio Liquor Control Comm. (1992), 63 Ohio St.3d 570, 571, 589 N.E.2d 1303. In order for evidence to be reliable, there must be a reasonable probability that it is true. Id. Probative evidence is evidence that tends to prove the issue in question, while substantial evidence is evidence that carries weight or evidence that has importance and value. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

City of Salem v. Koncelik, 843 N.E.2d 799, 164 Ohio App. 3d 597, 2005 Ohio 5537 (Ohio Ct. App. 2005).

843 N.E.2d 799 (City of Salem v. Koncelik) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

State ex rel. Yost v. Church of Troy
2020 Ohio 4695 (Ohio Court of Appeals, 2020)
Stingray Pressure Pumping L.L.C. v. Tax Commr. of Ohio
2019 Ohio 5198 (Ohio Court of Appeals, 2019)
In re Acubens, L.L.C.
2018 Ohio 2607 (Ohio Court of Appeals, 2018)
Oxford Mining Co., L.L.C. v. Nally
2015 Ohio 182 (Ohio Court of Appeals, 2015)
City of Salem v. Korleski
934 N.E.2d 360 (Ohio Court of Appeals, 2010)
HCMC, Inc. v. Ohio Department of Job & Family Services
903 N.E.2d 660 (Ohio Court of Appeals, 2008)
Textileather Corp. v. Korleski, 06-Ap-955 (8-14-2007)
2007 Ohio 4129 (Ohio Court of Appeals, 2007)