RCN Telecom Services of Philadelphia, Inc. v. Newtown Township

848 A.2d 1108, 2004 Pa. Commw. LEXIS 369
CourtCommonwealth Court of Pennsylvania
DecidedMay 7, 2004
StatusPublished
Cited by5 cases

This text of 848 A.2d 1108 (RCN Telecom Services of Philadelphia, Inc. v. Newtown Township) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
RCN Telecom Services of Philadelphia, Inc. v. Newtown Township, 848 A.2d 1108, 2004 Pa. Commw. LEXIS 369 (Pa. Ct. App. 2004).

Opinion

OPINION BY

Judge FRIEDMAN.

RCN Telecom Services of Philadelphia, Inc. (RCN) appeals from the July 2, 2003, order of the Court of Common Pleas of Bucks County (trial court), which affirmed the order of the Board of Supervisors (Board) of Newtown Township (Township) directing RCN to pay damages to the Township as a result of RCN’s breach of its agreement with the Township. We affirm.

On December 16, 1998, the Township authorized and enacted into ordinance 1 a Cable Television Franchise Agreement (Agreement or Ordinance) between RCN and the Township. (Board’s Findings of Fact, No. 1; R.R. at 106a, 138a.) Pursuant to the Agreement, the Township granted RCN a non-exclusive right to erect, construct, operate and maintain a cable television system (Cable System) in the public rights-of-way of the Township for an initial term of ten years. 2 (Board’s Findings of Fact, No. 2; Sections 2 and 3 of *1110 Agreement, R.R. at 111a.) Pursuant to section 6.1 of the Agreement, RCN was to complete construction of, and fully activate, the Cable System by December 16, 2002. (Board’s Findings of Fact, No. 4; Section 6.1 of Agreement, R.R. at 114a.) The Agreement also required RCN to design, construct and activate an Institutional Network 3 for the Township by December 16, 2002. (Board’s Findings of Fact, No. 4; Section 25 of Agreement, R.R. at 135a.)

By letter dated November 7, 2001, Thomas K. Steel, Jr., Vice-President and Regulatory Counsel for RCN, informed Scott Harper, then-Secretary of the Board, that “RCN had no plans to begin construction in Newtown Township in 2001, nor 2002, nor for the foreseeable future.” (Board’s Findings of Fact, No. 5; R.R. at 141a.) On November 27, 2001, the Township, by its solicitor, sent a Notice of Default to RCN President Jeffrey White, notifying RCN that it was in default of the Agreement. 4 (Board’s Findings of Fact, No. 6; R.R. at 143a-44a.)

On December 20, 2001, Andrew J. Kat-sock, III, Esquire, representing RCN, sent a letter to the Township stating, “Pursuant to Section 12.3 of the Agreement, please accept this correspondence as notice that RCN contests the assertion of non-compliance alleged by [the] Township-In accordance with said Section 12.3, the time specified to cure the alleged defect shall be stayed or tolled pending a hearing.” 5 (R.R. at 145a; see Board’s Findings of Fact, No. 7.) On January 16, 2002, the Township, by its solicitor, notified RCN, by its attorney Katsock, that a hearing would be held pursuant to section 12.3 of the Agreement on February 28, 2002, regarding RCN’s contest to the Township’s November 27, 2001, Notice of Default. (Board’s Findings of Fact, No. 8.)

At the February 28, 2002, hearing, the Board accepted the following Township exhibits into evidence; a copy of the Agreement in the form of Township Ordinance No. 98-0-21, which had attached to it RCN’s acceptance of the conditions and *1111 obligations imposed by the Ordinance; the November 7, 2001, letter from Steel indicating that RCN had no plans to begin construction in the Newt owns in 2001, 2002, nor the foreseeable future; the November 27, 2001, Notice of Default letter to RCN; and Katsock’s December 20, 2001, letter, on behalf of RCN, contesting the Township’s Notice of Default. (Board’s Findings of Fact, Nos. 12-18.) The Board also admitted into evidence the January 16, 2002, letter to Katsock notifying RCN of the date, time and place of the hearing. (Board’s Findings of Fact, No. 12.)

For its part, RCN attempted to offer into evidence its request for modification of the Agreement; 6 however, the Board did not admit this evidence, ruling that it was not relevant to the issue of whether the Agreement had been breached. (R.R. at 74a-82a.) RCN presented no witnesses at the hearing and no evidence to refute the Township’s allegation of default. (Board’s Findings of Fact, No. 20.)

The Board concluded that the Agreement is a legally binding contract between the Township and RCN and that RCN committed an anticipatory breach of the Agreement by issuing its November 7, 2001, letter. (Board’s Conclusions of Law, Nos. 6, 7.) The Board also concluded that RCN breached the Agreement by (1) failing to complete construction and fully activate the Cable System in accordance with section 6.1 of the Agreement, and (2) failing to complete an Institutional Network pursuant to section 25.A of the Agreement. (Board’s Conclusions of Law, No. 8.) The Board determined both of these to be material breaches of the Agreement. (Board’s Conclusions of Law, No. 8.)

The Board then considered the issue of liquidated damages, which are provided for under section 12.4 of the Agreement, which provides:

(A) Amounts of Liquidated Damages. Because [RCN’s] failure to comply with provisions of the Franchise will result in injury to the [Township] in amounts that will be difficult to quantify with reasonable certainty, the [Township] and [RCN] agree to the following liquidated damages for the following violations. These damages represent the parties’ best estimate of the damages resulting from the specified injury and are not a penalty or forfeiture and are one or more exclusions to the term “franchise fee” provided in the [Communications Act of 1934],...
(3) For failure to complete construction and/or fully activate the Cable System in accordance with Section 6, five hundred dollars ($500.00) per day that the Cable System is not provided, installed and/or activated.
(6) For all other material violations of this Agreement, $500/day for each day the violation continues.

(R.R. at 121a.) Pursuant to section 12.4, the Board determined that, for RCN’s failure to construct and activate the Cable System, RCN owes liquidated damages in the amount of $1,096,000.00, and for RCN’s failure to complete an Institutional Network, RCN owes liquidated damages in the amount of $1,096,000.00. 7 Thus, the *1112 Board entered an award against RCN and in favor of the Township in the total amount of $2,192,000.00. (Board’s Conclusions of Law, Nos. 13-15, Order.)

RCN appealed to the trial court, arguing that: (1) the Board lacked jurisdiction over the matter because the Agreement contained a mandatory arbitration provision, and this dispute should have been submitted to arbitration; (2) federal law required the Board to stay the imposition of damages, which RCN characterizes as “penalties,” so long as RCN’s application for modification was pending; (3) the liquidated damages provision is unenforceable because it constitutes a penalty; and (4) RCN’s constitutional rights were violated. (R.R. at 169a-78a, 196a-206a.) As to these issues, the trial court concluded that the Agreement’s arbitration provision did not apply, and, thus, the Agreement did not require that the matter be arbitrated.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Georgetown Yacht Basin, Inc. v. M/V Fourth Pawn
455 F. Supp. 2d 370 (E.D. Pennsylvania, 2006)
A. G. Cullen Construction, Inc. v. State System of Higher Education
898 A.2d 1145 (Commonwealth Court of Pennsylvania, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
848 A.2d 1108, 2004 Pa. Commw. LEXIS 369, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rcn-telecom-services-of-philadelphia-inc-v-newtown-township-pacommwct-2004.