RCC FABRICATORS, INC. v. UMOJA ERECTORS, LLC

CourtDistrict Court, E.D. Pennsylvania
DecidedAugust 6, 2021
Docket2:17-cv-05304
StatusUnknown

This text of RCC FABRICATORS, INC. v. UMOJA ERECTORS, LLC (RCC FABRICATORS, INC. v. UMOJA ERECTORS, LLC) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
RCC FABRICATORS, INC. v. UMOJA ERECTORS, LLC, (E.D. Pa. 2021).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF PENNSYLVANIA

RCC FABRICATORS, INC., : CIVIL ACTION Plaintiff, : : v. : : UMOJA ERECTORS, LLC, et al., : No. 17-5304 Defendants. :

MEMORANDUM OPINION

UNITED STATES MAGISTRATE JUDGE August 6, 2021 TIMOTHY R. RICE

The City of Philadelphia in 2015 began to renovate a massive property at 4601 Market Street as its new public safety headquarters. Six years and more than $14 million later, the City has sold the property and abandoned the project, leaving a trail of construction litigation in its wake. This case features a narrow dispute between the project’s contractor, D.A. Nolt, Inc. (“Nolt”) and two sub-contractors, Umoja Erectors, LLC (“Umoja”) and RCC Fabricators, Inc. (“RCC”) for $198,000 in steel – a fraction of the project’s massive price tag. During a trial on April 27-29, 2021, several facts were uncontested: (1) all steel supplied by RCC was installed no later than April 2017; (2) Nolt has received nearly $450,000 – about 85% of full payment – from the City for steel work performed by its sub-contractors; (3) Umoji has received about $250,000 – nearly 50% – for its role in the steel work; and (4) RCC has not received a penny for fabricating the steel. Complicating matters further, in a separate, unrelated lawsuit, Nolt is seeking an additional $2.7 million from the City, and the City is seeking $1.3 million for delays by Nolt even though the City abandoned the project for unrelated reasons shortly after Nolt completed its work. See D.A. Nolt v. Philadelphia Municipal Authority, No. 18-4997 (the “City Lawsuit”). This has prompted Nolt to assert potentially inconsistent positions in the two lawsuits. In the City Lawsuit, Nolt claims its work was timely completed, notwithstanding the delays and errors by RCC and Umoja. Ex. 165 ¶ 99. In this lawsuit, Nolt claims the delays and errors by RCC and Umoja justify its withholding payment to RCC for more than four years even though it has

received more than 85% of the money the City agreed to pay for steel work. Umoja admits that it withheld more than $66,000 from RCC even after Nolt directed Umoja to pay a portion of RCC’s bill in 2017. Nolt has not joined Umoja or RCC in the City Lawsuit, and has not separately pursued a claim for any backcharges against either of them. Instead, Umoja alleges a contractual right to withhold payment from RCC based on the possibility that claims could be brought against it by Nolt, and Nolt alleges a contractual right to withhold payment from Umoja and RCC based on the possibility that it faces exposure for damages to the City. I find by a preponderance of the evidence that RCC complied with its contractual

obligation to provide steel. Based on its contract terms and the Prompt Pay Act, RCC is entitled to damages of 85.5% of its $198,645.85 contract price, plus statutory interest. There is no dispute that RCC last delivered steel to the project in February 2017 and that the steel RCC provided was installed. Neither Umoja nor Nolt has established any lawful basis to withhold all payment for the steel used in the project.1

1 Judge Pratter will decide to what extent, if any, the parties may have breached their contractual obligations by delaying the project. I need not reach that issue here because, as explained below: (1) the Prompt Pay Act required Nolt to pay its sub-contractors for materials that were provided and used in the project; and (2) the operative contracts did not permit Umoja or Nolt to withhold payment entirely based on the possibility that they might be liable for damages in the future. Findings of Fact I. The Project and the Parties 1. In 2015, the Philadelphia Municipal Authority (“PMA”) entered into an agreement with Nolt (the “Nolt” agreement or contract) which required Nolt to provide general contracting services for Phase II of the construction of a planned Public Safety Service Campus at 4601

Market St. in Philadelphia (the “PSSC”). Ex. 1. 2. Nolt purchased a Payment Bond for the PSSC project from the North American Surety and Insurance Company (“NASIC”).2 Ex. 1. 3. On May 5, 2016, Nolt issued a purchase order to RCC for “complete shop drawings” of the steel for the PSSC project for $19,000. Ex. 69. 4. Nolt subcontracted with Umoja, requiring Umoja to undertake the “steel fabrication and erection work” for the PSSC project, including “layout and verification of field dimensions prior to fabrication,” for $244,537. Ex. 3 at 18 (the “Umoja subcontract”). 5. The Umoja subcontract specified that Umoja “shall coordinate the fabrication with and

procure all steel from” RCC. Id. 6. On September 20, 2016, Umoja and RCC entered into a subcontract requiring RCC to “furnish (but not erect) all fabricated steel and related materials” for the PSSC project for $209,805. Ex. 4 at 1 (the “RCC subcontract”). II. Measurement and Fabrication Issues and Completion of the Project 7. The steel-related design portion of the PSSC project consisted of several steps. First, the

2 Payment bonds are standard requirements for municipal construction projects. See Nicholson Const. Co. v. Standard Fire Ins. Co., 760 F.2d 74, 75 (3d Cir. 1985). They guarantee payment for businesses who provide materials and labor even if the prime contractor is unable to pay them. Id. City’s designer drew up “contract drawings” or “design drawings.” N.T. 4/27/21 at 12. Second, those design drawings were translated into “shop drawings.” Id. 8. Once the “shop drawings” were approved by the city’s engineer -- but before they could be used to fabricate steel -- they had to be “field verified,” i.e., the measurements and calculations used from the City’s design drawings had to be checked against the physical space.

Id. at 18. 9. Then, “field verified” drawings had to be finalized, i.e,. reviewed for the final time by Nolt and the engineer, who would confirm that they could be used to fabricate the steel for the project. Id. at 86. 10. Confirmed shop drawings were turned into erection drawings, or “e” drawings, which explained to Umoja’s erection contractors at the site how to install the various pieces of steel. Id. at 203-204. 11. RCC was obligated to produce shop drawings that conformed to the project specifications included in “Bulletin 7,” a design change document the City gave Nolt in March 2016 and which

Nolt reminded RCC about on May 18, 2016. Ex. 70. 12. Nolt was required to provide RCC a “[s]urvey of existing field conditions including, but not limited to, installed anchor bolts, steel framing, elevations, etc.” before RCC prepared the shop drawings. RCC subcontract “Qualifications & Exclusions.” 13. RCC subcontracted its obligation to prepare shop drawings to a third party, some of whose employees worked in India. N.T. 4/27/21 at 72, 80. 14. Many of RCC’s original calculations were inaccurate because they ignored changes to the project required by Bulletin 7. Ex. 138 at 4. 15. RCC submitted shop drawings that included the changes in Bulletin 7 on June 28, 2016. Ex. 148 at 5. 16. On July 15 and 18, 2016, the shop drawings were returned by the engineer to RCC for revision with comments. Id. at 2-3. 17. Umoja was responsible for “verification of field dimensions prior to fabrication.” Ex. A

to Umoja subcontract, § 1(c). 18. In August 2016, representatives of RCC and Umoja worked together to “field verify” some of the shop drawings. N.T. 4/27/21 at 21. 19. Umoja was solely responsible for the field verification and RCC voluntarily assisted to help expedite the process. RCC bears no responsibility for any field verification errors. Ex. A to Umoja subcontract, § 1(c). 20. Umoja reported it had completed field verification of all shop drawings on Friday, September 23, 2016. Ex. 14 at 1. 21. After promising to begin delivery on Tuesday, September 27, 2016, RCC began

delivering steel on Wednesday, September 28, 2016. Ex. 6 at 1; Ex.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Commonwealth Ex Rel. Pappert v. TAP Pharmaceutical Products, Inc.
885 A.2d 1127 (Commonwealth Court of Pennsylvania, 2005)
Neville v. Scott
127 A.2d 755 (Superior Court of Pennsylvania, 1956)
Murphy v. Duquesne University of Holy Ghost
777 A.2d 418 (Supreme Court of Pennsylvania, 2001)
Sphere Drake, P.L.C. v. 101 Variety, Inc.
35 F. Supp. 2d 421 (E.D. Pennsylvania, 1999)
Superior Precast, Inc. v. Safeco Ins. Co. of America
71 F. Supp. 2d 438 (E.D. Pennsylvania, 1999)
Clipper Pipe & Service, Inc. v. Ohio Casualty Insurance
115 A.3d 1278 (Supreme Court of Pennsylvania, 2015)
Charlson's Furniture Co. v. Heigley
53 A.2d 878 (Superior Court of Pennsylvania, 1947)
Porter v. Chevron Appalachia, LLC
204 A.3d 411 (Superior Court of Pennsylvania, 2019)
East Coast Paving & Sealcoating, Inc. v. North Allegheny School District
111 A.3d 220 (Commonwealth Court of Pennsylvania, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
RCC FABRICATORS, INC. v. UMOJA ERECTORS, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rcc-fabricators-inc-v-umoja-erectors-llc-paed-2021.