Raymond Handling Concepts Corp v. Invata LLC

CourtCourt of Appeals for the Third Circuit
DecidedJuly 18, 2024
Docket23-3002
StatusUnpublished

This text of Raymond Handling Concepts Corp v. Invata LLC (Raymond Handling Concepts Corp v. Invata LLC) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Raymond Handling Concepts Corp v. Invata LLC, (3d Cir. 2024).

Opinion

NOT PRECEDENTIAL

UNITED STATES COURT OF APPEALS FOR THE THIRD CIRCUIT ______________

No. 23-3002 ______________

RAYMOND HANDLING CONCEPTS CORP, A New York Corporation, Appellant

v.

INVATA LLC, FKA Invata Inc, DBA Invata Intralogistics ______________

On Appeal from the United States District Court for the Eastern District of Pennsylvania (D.C. No. 2:23-cv-00145) District Judge: Honorable John F. Murphy ______________

Submitted Under Third Circuit L.A.R. 34.1(a) July 9, 2024 ______________

Before: SHWARTZ, PHIPPS, and MONTGOMERY-REEVES, Circuit Judges.

(Filed: July 18, 2024 ) ______________

OPINION* ______________

SHWARTZ, Circuit Judge.

* This disposition is not an opinion of the full Court and, pursuant to I.O.P. 5.7, does not constitute binding precedent. Raymond Handling Concepts Corporation appeals the District Court’s order

dismissing its contract claims on limitations grounds and tort claims under the gist of the

action doctrine. For the reasons set forth herein, we will affirm.

I

A

In early 2018, Raymond contracted to install storage systems at Taylor Farms’

fresh produce distribution center. The contract required Raymond to install a software

called FastTrak and Raymond subcontracted with Invata, Inc. to provide FastTrak to

Taylor Farms. The subcontract, which was prepared by Invata, was to take effect in

September 2018, with the installation of FastTrak to be completed by April 2019.

Shortly after the contract was approved, Invata told Raymond that it could not

install FastTrak by April 2019, and asked for a two-month extension, which Taylor

Farms authorized. This deadline was later extended until August 26, 2019, which Invata

failed to meet.

As a result of Invata’s repeated failures to meet its deadline, in October 2019,

Taylor Farms formally terminated its general contract with Raymond, and Raymond

thereafter sought a “monetary concession” from Invata. App. 63. From January through

June 2020, all three companies tried to resolve their contract issues. Taylor Farms gave

Invata a final chance to redevelop its portion of the project by June 2020, but Invata

failed to timely submit a workplan.

B 2 The subcontract between Raymond and Invata provided that (1) Pennsylvania law

would govern; (2) “[a]ny action brought by [Raymond] must be brought within one (1)

year after the cause of action arose,” App. 84 (¶ 5); and (3) Raymond could not bring a

claim of “alleged breach of” the subcontract unless each of the following were satisfied:

(i) Raymond “notifies” Invata “within thirty (30) days from the date of such alleged breach[,]” (ii) “Invata does not remedy or correct the breach . . . within sixty (60) days from the receipt of [Raymond’s] notice[,]” (iii) Raymond “notifies Invata in writing of such claim . . . within one (1) year from date of acceptance,” and (iv) Raymond “commences an action to enforce its rights” no “later than forty-five (45) days” after notifying Invata of its claim.

App. 85 (¶¶ 20-22).

In 2023, Raymond sued Invata for breach of contract (Count I); breach of the

implied covenant of good faith and fair dealing (Count II); negligent misrepresentation

(Count III); negligence (Count IV); and breach of implied warranty (Count V). The

District Court dismissed the complaint with prejudice, holding that the subcontract’s one-

year limitations provision barred Raymond’s contract claims (Counts I, II, and V),1 and

that the gist of the action doctrine barred Raymond’s tort claims (Counts III and IV).

Raymond Handling Concepts Corp. v. Invata, LLC, No. 23-145, 2023 WL 6626127, at

*11 (E.D. Pa. Oct. 11, 2023). Raymond appeals.

1 Raymond does not challenge the District Court’s holding that its claims for breach of contract, breach of the implied covenant of good faith and fair dealing, and breach of implied warranty are contract claims that fall within a contract for sale. See Raymond Handling Concepts Corp., 2023 WL 6626127, at *9-10. 3 II2

Under Pennsylvania law, the “[g]eneral rule” is that “[a]ny action” based on

“contracts for sale” has a four-year statute of limitations.3 42 Pa. Cons. Stat. § 5525(a)(2)

(citing 13 Pa. Cons. Stat. § 2725). Contracting parties, however, “may reduce the period

of limitation” in their contract “to not less than one year.” 13 Pa. Cons. Stat. § § 2725(a).

The parties here reduced the limitations period in their subcontract. One provision

required suit to be brought within one year “after the cause of action arose.” App. 84 (¶

5). A second provision, which addressed “Invata’s alleged breach of” the subcontract,

required Raymond to bring an action to enforce rights under the subcontract “not later

than forty-five (45) days” after Raymond notified Invata of its claim. App. 85 (¶¶ 20-22).

Even if we assume that both provisions could apply to Raymond’s breach of contract

claims, Raymond’s claims are untimely.

First, Raymond’s complaint was filed too late under the one-year limitations

period set forth in paragraph five of the subcontract. Raymond was aware that: (1) Invata

2 The District Court had jurisdiction under 28 U.S.C. § 1332. We have jurisdiction under 28 U.S.C. § 1291. We review a district court’s order granting a motion to dismiss de novo, Krieger v. Bank of Am., N.A., 890 F.3d 429, 437 (3d Cir. 2018). We accept the factual allegations as true and construe them in a light most favorable to the plaintiff. Fleisher v. Standard Ins. Co., 679 F.3d 116, 120 (3d Cir. 2012). “[W]e may affirm on any ground supported by the record.” Laurel Gardens, LLC v. McKenna, 948 F.3d 105, 116 (3d Cir. 2020). 3 “Contracts for sale” include the sale of software. Advent Sys. Ltd. v. Unisys Corp., 925 F.2d 670, 672, 675 (3d Cir. 1991). 4 had not installed the operational software by the extended August 2019 deadline; (2)

Taylor Farms notified Invata that it was terminating the project on which Invata worked

in October 2019; and (3) despite Taylor Farms giving Invata a final chance to complete

the project by June 2020, Invata failed to timely submit a workplan. Thus, the cause of

action arose as early as August 2019 and certainly no later than June 2020. Accordingly,

even if Raymond viewed the additional time (until June 2020) that Taylor Farms gave

Invata to submit a new workplan as delaying the termination, Raymond’s 2023 complaint

was still filed after the one-year limitations period expired.4

Second, even assuming (a) Raymond satisfied the requirements for the more

specific breach of contract provision in paragraphs twenty to twenty-two, and (b) the

time-period in those provisions is enforceable under Pennsylvania law, 13 Pa. Const. Stat.

§ 2725,5 the complaint would still be untimely because this provision required Raymond

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fleisher v. Standard Insurance
679 F.3d 116 (Third Circuit, 2012)
Eigen v. Textron Lycoming Reciprocating Engine Division
874 A.2d 1179 (Superior Court of Pennsylvania, 2005)
Etoll, Inc. v. Elias/Savion Advertising, Inc.
811 A.2d 10 (Superior Court of Pennsylvania, 2002)
Mirizio v. Joseph
4 A.3d 1073 (Superior Court of Pennsylvania, 2010)
Clairton Slag, Inc. v. Department of General Services
2 A.3d 765 (Commonwealth Court of Pennsylvania, 2010)
Robert Addie v. Christian Kjaer
737 F.3d 854 (Third Circuit, 2013)
Werwinski v. Ford Motor Co.
286 F.3d 661 (Third Circuit, 2002)
William Krieger v. Bank of America NA
890 F.3d 429 (Third Circuit, 2018)
Laurel Gardens, LLC v. Timothy McKenna
948 F.3d 105 (Third Circuit, 2020)
Lisa Earl v. NVR Inc
990 F.3d 310 (Third Circuit, 2021)
Cole v. Lawrence
701 A.2d 987 (Superior Court of Pennsylvania, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
Raymond Handling Concepts Corp v. Invata LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/raymond-handling-concepts-corp-v-invata-llc-ca3-2024.