Rayburn v. Georgia Power Co.

643 S.E.2d 385, 284 Ga. App. 131, 2007 Fulton County D. Rep. 856, 2007 Ga. App. LEXIS 271
CourtCourt of Appeals of Georgia
DecidedMarch 12, 2007
DocketA06A2026
StatusPublished
Cited by8 cases

This text of 643 S.E.2d 385 (Rayburn v. Georgia Power Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rayburn v. Georgia Power Co., 643 S.E.2d 385, 284 Ga. App. 131, 2007 Fulton County D. Rep. 856, 2007 Ga. App. LEXIS 271 (Ga. Ct. App. 2007).

Opinion

Barnes, Chief Judge.

Benjamin Rayburn worked for Caffrey Construction Company as a tree cutter, and was clearing land for a new power line right of way when he was paralyzed by a falling limb. He sued Georgia Power Company, which had hired Caffrey Construction, for negligence. After extensive discovery, Georgia Power moved for summary judgment. The trial court granted the motion, and Rayburn appeals. For the reasons that follow, we affirm.

On appeal we review the trial court’s grant of summary judgment de novo to determine whether the evidence, viewed in the light most favorable to the nonmoving party, demonstrates a genuine issue of material fact. Summary judgment is proper only when no issue of material fact exists and the moving party is entitled to judgment as a matter of law. Preferred Real Estate Equities v. Housing Systems, 248 Ga. App. 745 (548 SE2d 646) (2001). Further, when ruling on a motion for summary judgment, a court must give the opposing party the benefit of all reasonable doubt, and the evidence and all inferences and conclusions therefrom must be construed most favorably toward the party opposing the motion. Moore v. Goldome Credit *132 Corp., 187 Ga. App. 594, 596 (370 SE2d 843) (1988). On motions for summary judgment, however, courts cannot resolve the facts or reconcile the issues. Fletcher v. Amax, Inc., 160 Ga. App. 692, 695 (288 SE2d 49) (1981). When reviewing the grant or denial of a motion for summary judgment, this court conducts a de novo review of the law and the evidence. Desai v. Silver Dollar City, 229 Ga. App. 160, 163 (1) (493 SE2d 540) (1997).

So viewed, the record shows that Georgia Power determined that it needed to expand a substation in Glynn County to increase its capacity. The land over which Georgia Power’s right of way would run was “typical coastal plain of Georgia” with wet areas, marshy areas, creeks, and some high ground with planted pine. A committee established a proposed two-mile center line for the expansion, and Georgia Power’s land department crews set “control points” along the line by obtaining Global Positioning Satellite (GPS) data so that future survey work would be aligned with existing survey work. Georgia Power then hired an outside surveyor to determine the property lines and other topographical features of the center line and surrounding right of way, and Georgia Power’s land department used the outside surveyor’s data to fill in details on the map.

Once that map was prepared and the center line and boundaries were flagged, Georgia Power’s environmental supervisor and his assistant walked through the site to flag the boundaries of the stream buffers and wetlands. The timber within those areas would be felled by hand with chain saws, and the rest of the area would be cleared with machines. The supervisor testified that, although the company could have applied to the Corps of Engineers (COE) for a permit to clear wetlands mechanically, Georgia Power’s standard policy for the last 15 or 20 years required that all wetlands and stream buffers must be cleared by hand. The COE regulates the discharge of fill matter in wetlands and regulates mechanical land clearing because it destroys wetlands by disturbing the root mat underground. The COE does not regulate activities that only involve removing vegetation above ground, where the activity neither substantially disturbs the root system nor involves mechanically pushing or dragging vegetation and redepositing soil material. Hand-clearing minimizes the impact to the wetland because it does not disrupt the root mat. The company only sought a permit from the COE when it had to fill in a wetland area, as it did for .83 acres on this project to build a structure.

The Environmental Protection Division of the Georgia Department of Natural Resources (EPD) administers the National Pollution Discharge Elimination System, which tracks and regulates the amount of discharge from construction sites to control the amount of sediment in the water and reduce the impact to plants and wildlife. See OCGA § 12-5-23 (a) (1) (R), (c) (15). Each power line transmission project *133 requires a permit, which is obtained by filing a “Notice of Intent” that the company would be working in that area, and Georgia Power hires an outside company to monitor the rainfall and water quality during the project. The State Erosion and Sedimentation Act requires at least a 25-foot buffer to be cleared by hand on each side of a warm water stream, and at least a 50-foot buffer for trout streams, within which vegetation must be cleared by hand. OCGA § 12-7-6 (b) (15), (16).

Georgia Power’s environmental supervisor testified that whether to widen the buffer was a judgment call on his part, and he did so here because he determined that the stream running through this project was sensitive. He put flags along an estimated 50-foot-wide buffer, twice the required buffer width because the bigger the buffer, the better the protection in a sensitive area. In addition to marking the stream buffer, he also marked the edges of all wetland areas within the right of way, which he determined by considering data such as the type of vegetation, soil, drift lines, and water level. A survey map of the area with construction details includes a note that says, “CAUTION: 25' buffer each side of wetlands only special selected clearing. Coordinate work with Georgia Power Company Environmental Department. Field verify.” The environmental supervisor did not know who would determine the location of the 25-foot buffer from the edge of the wetlands that he flagged.

The environmental supervisor’s assistant, an environmental analyst, walked the property behind the supervisor and marked in her notebook that they put 100-foot buffers on the stream. In addition to physically flagging these areas, the assistant gathered GPS data showing the wetland and stream buffer delineations and the land department used that data to generate an overlay showing the wetlands and stream buffers on the existing map. At some point, Georgia Power staff moved the wetland buffer to the edge of the right of way. It is unclear from the record who flagged the stream buffer boundary within which Rayburn was working when he was injured.

Georgia Power requested bids on the clearing project, and Caffrey Construction won the bid, having taken into account that several areas in the project had to be hand-cleared. Caffrey’s first crew got behind, so in June 2003 its second crew, including Rayburn, went to Brunswick to assist. Two days after he began working on the job, Rayburn went into an area marked as a “streamside management” or buffer zone and worked for two and a half hours felling about thirty trees with a chain saw. The ground was flat and he stood ankle-deep in water. He then began cutting a tree with a fork in it. He cut one fork and turned to cut the second fork when a limb from another tree struck him from behind. Apparently the canopy of the first tree hit the *134 canopy of another tree and knocked off the limb. Rayburn sustained a spinal cord injury and is paralyzed from his chest down.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

PATTI PENNINGTON v. BRIDGE SENIOR LIVING, LLC
Court of Appeals of Georgia, 2023
Robert Wilson v. Hunter Lee Guy
Court of Appeals of Georgia, 2020
Ralph James Puckett, III v. The Plastics Group, Inc.
561 F. App'x 865 (Eleventh Circuit, 2014)
Diplomat Construction, Inc. v. State Bank of Texas
726 S.E.2d 140 (Court of Appeals of Georgia, 2012)
DaimlerChrysler Motors Co., LLC v. Clemente
668 S.E.2d 737 (Court of Appeals of Georgia, 2008)
Bruntz v. Cotton Tail Hunt Club
661 S.E.2d 849 (Court of Appeals of Georgia, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
643 S.E.2d 385, 284 Ga. App. 131, 2007 Fulton County D. Rep. 856, 2007 Ga. App. LEXIS 271, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rayburn-v-georgia-power-co-gactapp-2007.