Perry v. Georgia Power Co.

629 S.E.2d 588, 278 Ga. App. 759, 2006 Fulton County D. Rep. 1234, 2006 Ga. App. LEXIS 405
CourtCourt of Appeals of Georgia
DecidedApril 12, 2006
DocketA06A0599
StatusPublished
Cited by6 cases

This text of 629 S.E.2d 588 (Perry v. Georgia Power Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Perry v. Georgia Power Co., 629 S.E.2d 588, 278 Ga. App. 759, 2006 Fulton County D. Rep. 1234, 2006 Ga. App. LEXIS 405 (Ga. Ct. App. 2006).

Opinion

BLACKBURN, Presiding Judge.

In this personal injury action against Georgia Power Company (GPC) and E-Z Ditching Service (E-Z Ditching), H. Vanzel Perry appeals the trial court’s grant of summary judgment to GPC, contending: (1) that the trial court erred in ruling that GPC is not vicariously liable to Perry for the allegedly negligent acts of its independent contractor E-Z Ditching, and (2) that the trial court erred in ruling that GPC is not liable for Perry’s injuries because of its failure to flag the power line trench in violation of the Georgia Utility Facility Protection Act (GUFPA), as GPC’s conduct was not the cause thereof. We disagree and affirm the trial court’s rulings.

Summary judgment is proper when there is no genuine issue of material fact and the movant is entitled to judgment as a matter of law. OCGA § 9-11-56 (c). A de novo standard of review applies to an appeal from a grant of summary judgment, and we view the evidence, and all reasonable conclusions and inferences drawn from it, in the light most favorable to the nonmovant.

Matjoulis v. Integon Gen. Ins. Corp. 1 So viewed, the evidence shows that Perry visited a construction site at Larry’s Giant Subs in Hazlehurst to install an underground telephone cable for BellSouth *760 Utilities. Pursuant to its independent contract with GPC, E-Z Ditching had recently dug a trench and installed and buried a power line in the area where Perry was injured. While no flags had been installed to mark the subject power line trench pursuant to Bell-South’s statutory request, Perry was aware of this fact but elected to proceed with his task. He was, in fact, aware of the location of the power line prior to his injury. Perry walked across a level area of the site, and the ground partially collapsed beneath him, causing him to fall and injure himself. Perry never came into contact with the buried power line, nor did he suffer any electric shock.

As a result of his injuries, Perry underwent surgery on his back and was terminated from his job for his inability to perform tasks required by his work. Perry alleged E-Z Ditching was the employee of GPC in his suit against both parties, and that GPC was thus liable for Perry’s damages. Perry alleged that GPC was also liable for Perry’s injuries based on its failure to flag the power line trench in violation of GUFPA, OCGA § 25-9-1 et seq. The trial court ruled for GPC on both issues, and granted its motion for summary judgment, which Perry now appeals.

1. We first address Perry’s contention that GPC is liable here for the negligent actions of its employee, E-Z Ditching, in that GPC is vicariously liable for the actions of its employees. Because E-Z Ditching was an independent contractor of GPC, we disagree.

“An employer generally is not responsible for torts committed by his employee when the employee exercises an independent business and in it is not subject to the immediate direction and control of the employer. OCGA § 51-2-4.” (Punctuation omitted.) Cooper v. Olivent. 2 Such was the case as between E-Z Ditching and GPC: E-Z Ditching performed the work pursuant to a contract naming it as an independent contractor (where contract denominates one party as an independent contractor, that relationship is presumed to be true). See Loudermilk Enterprises v. Hurtig. 3 E-Z Ditching performs work for companies other than GPC, owns and maintains its own equipment, manages its own payroll and tax withholding, trains its own employees, and controls the execution of the work. Therefore, under these circumstances, GPC would not as a general matter be vicariously liable for the negligence of its independent contractor, E-Z Ditching, in burying the power line. See Bell South Telecommunications v. Widner. 4

*761 Perry acknowledges the independent contractor status of E-Z Ditching as provided by its contract with GPC, but argues that GPC retained a sufficient amount of control over the time, method, and manner of executing the work as to make GPC vicariously liable pursuant to OCGA§ 51-2-5 (5) (exception to general rule of nonliability where one retains an independent contractor). We therefore address the issue of whether GPC retained the right to control or direct the time and manner of E-Z Ditching’s work as argued by Perry.

Here, E-Z Ditching performed the work at issue pursuant to a blanket contract with GPC. The contract designated E-Z Ditching as an independent contractor to dig trenches for GPC as assigned by GPC and accepted by E-Z Ditching. Upon acceptance of a work assignment, E-Z Ditching would decide how to do the work and direct its own employees. The contract specified that E-Z Ditching had to comply with GPC’s specifications and that GPC retained the right to “inspect the work being done and require performance to comply with specifications, not for the purpose of controlling the method and manner of the performance of the work, but in order to assure the completion of same in accordance with the plans and specifications.” GPC did not provide on-site supervision of the work of E-Z Ditching, nor were any GPC employees on site when E-Z Ditching dug the trench that collapsed under Perry. E-Z Ditching owns and maintains its own trenching equipment, and E-Z Ditching determines the hours its employees will work.

Under these circumstances, the trial court did not err in concluding that GPC did not control the time and manner of E-Z Ditching’s performance or interfere with E-Z Ditching’s work to the extent that GPC became vicariously liable for E-Z Ditching’s acts. GPC’s right to inspect the work does not render it liable for E-Z Ditching’s alleged negligence, because “ [i] t is well recognized that merely taking steps to see that the contractor carries out his agreement, by supervision of the intermediate results obtained, or reserving the right of dismissal on grounds of incompetence, is not such interference and assumption of control as will render the employer liable.” (Punctuation omitted.) Slater v. Canal Wood Corp. 5 Therefore, under the facts before us, GPC did not retain “the right to direct or control the time and manner of executing the work or interfere [ ] and assume [ ] control so as to create the relation of master and servant or so that an injury results which is traceable to [GPC’s] interference.” 6 We cannot say that the trial court erred in its ruling on this issue.

*762 2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sharon Ward v. Directv LLC
801 S.E.2d 110 (Court of Appeals of Georgia, 2017)
Wilann Properties I, LLC v. Georgia Power Company
Court of Appeals of Georgia, 2013
Wilann Properties I, LLC v. Georgia Power Co.
740 S.E.2d 386 (Court of Appeals of Georgia, 2013)
Rayburn v. Georgia Power Co.
643 S.E.2d 385 (Court of Appeals of Georgia, 2007)
Cotton States Mutual Insurance v. Kinzalow
634 S.E.2d 172 (Court of Appeals of Georgia, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
629 S.E.2d 588, 278 Ga. App. 759, 2006 Fulton County D. Rep. 1234, 2006 Ga. App. LEXIS 405, Counsel Stack Legal Research, https://law.counselstack.com/opinion/perry-v-georgia-power-co-gactapp-2006.