Rausch v. Buisse

146 N.W.2d 801, 33 Wis. 2d 154, 1966 Wisc. LEXIS 879
CourtWisconsin Supreme Court
DecidedDecember 16, 1966
StatusPublished
Cited by50 cases

This text of 146 N.W.2d 801 (Rausch v. Buisse) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rausch v. Buisse, 146 N.W.2d 801, 33 Wis. 2d 154, 1966 Wisc. LEXIS 879 (Wis. 1966).

Opinion

Wilkie, J.

The issues presented by this appeal fall into two categories:

First, what duty was owed by the sewer contractor to the plaintiff?

Second, were the trial judge’s rulings concerning the admission or exclusion of evidence erroneous so that the appellant is entitled to a new trial ?

*161 In the trial court’s view the duty placed upon the defendant was restricted to requiring the contractor to warn as regards the protruding manhole. When the jury found that the plaintiff did not strike the manhole that disposed of the case. The learned trial court, we conclude, correctly rejected any further theory of imposing a duty on the defendant that could give rise to negligence.

What other duty was imposed on the contractor? Appellant contends an additional duty was imposed by contract. He attempts to establish a duty on the part of the defendant to warn against all obstructions on Forty-fifth street in the area of the accident. Plaintiff’s first theory for establishing this duty on defendant is based upon the contract between defendant and the city. This contract requires defendant to “put up and maintain, at his own cost, such barriers as will protect the public from all danger in any manner connected herewith, and that during the nighttime he will put up and maintain a sufficient number of red lights to give warning of danger.” A duty may be imposed on a person by a contract and nonperformance of this duty created by the contract may constitute actionable negligence. 1 The issue thus becomes whether the contract required the defendant to maintain barricades and warning lights on Forty-fifth street on the date of the accident.

The contract imposes the above duty “during the construction of said sewers and until the completion of each and every one of said sewers.” The contract involved the construction of several sewers and manholes throughout the city of Kenosha. The plaintiff argues that the defendant had a duty to put up barricades and lights during the nighttime and had a duty to continue doing so until the contractual work was accepted as a whole. *162 The trial court refused to accept this construction of the contract, ruling that the duty was imposed during the progress of the work at each particular site, and terminated at that site upon completion of the sewer and manhole there.

Sec. 27.8 of the specifications supports the trial court’s ruling. This section says:

“It shall be the duty of the Contractor to erect, and keep erected, a fence or proper barrier along the line of the work or trenches and across the ends of same in order effectually to guard the public from liability of falling into the trenches, or from upsetting vehicles by the earth thrown from the trenches, during the progress of the work,, both by day and by night. A red light must also be maintained at each end of the barriers from twilight in the evening until sunrise, and also at all street intersections where trenches are open.” (Emphasis added.)

Once a job is completed at a particular site, a contractor generally removes equipment when he moves on to construction at another site. Otherwise a great number of warning devices would be needed in order to place a warning device at each jobsite (whether completed or not) under a contract. Imposing a continuing obligation on the contractor for accidents at a jobsite where work has been completed until completion of all jobs under the entire contract is too burdensome, and unless the wording is much more explicit than here, would not be part of the intention of the parties to the contract.

Plaintiff’s second theory for imposing a contractual duty on the contractor to provide barricades and warning devices on Forty-fifth street, is that the work had not been completed at the jobsite so that the contractual duty on Forty-fifth street remains upon defendant. The trial court rejected this contention. All testimony indicated that the work had been completed several days prior to the accident. Defendant’s foreman testified that the work was completed and the grade was reestablished *163 level with the manhole by backfilling ten to twelve days before the accident. Plaintiff argues that the duty to grade imposed by the contract refers to grading the whole street, thereby making defendant responsible for the condition of the whole street. The trial court correctly confined the duty to grade to the trenches and to the area around the manhole. The contract and specifications regarding the fill and grading of the trenches support this interpretation. Thus the work at this jobsite was completed and no further duty upon the defendant remained, except in regard to the improper protrusion of the manhole.

Plaintiff also asserts that a duty is imposed upon the defendant under the safe-place statute (sec. 101.06, Stats.). This statute requires that certain precautions must be taken by an employer at a place of employment. Defendant, however, had completed his work on Forty-fifth street. Once work on a street project has terminated it is no longer a place of employment. 2 Thus a duty cannot be imposed upon defendant via the safe-place statute because of the absence of a place of employment.

Thus, the trial court was correct in limiting defendant’s duty to this appellant to the protruded manhole.

At the trial the jury was asked:

“Did the plaintiff, Roy Frank Rausch, Jr., strike the manhole installed by the defendant, Charles Buisse?”

With two dissents it answered “No” thus, in the opinion of the trial court, deciding the case.

This question was evidentiary in form like the one approved in the case of Fehrman v. Smirl. 3 Fehrman was a medical malpractice case, and during the trial the evidence only concerned injury to the external sphincter. The plaintiff was attempting to use this evidence to show the negligence of Dr. Smirl and our court stated it would *164 recommend (at a new trial) submitting the question whether Fehrman’s external sphincter was injured in the course of the first or second operation, or the postoperative care. A “No” answer by the jury to this question would be determinative of the case. 4

Similarly, in the case at bar the trial court believed that the plaintiff’s recovery of damages hinged upon a finding that plaintiff actually struck the manhole constructed by the defendant. The trial court’s basis is that the defendant’s duty toward the plaintiff was restricted to warning of the protruding manhole. The trial court explicitly rejected plaintiff’s attempts to broaden the duty of the defendant. The existence of a duty between two parties and the scope of such duty are pure questions of law to be decided by the judge. 5

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Estate of Kriefall v. Sizzler USA Franchise, Inc.
2011 WI App 101 (Court of Appeals of Wisconsin, 2011)
In RE MARRIAGE OF SIKER v. Siker
593 N.W.2d 830 (Court of Appeals of Wisconsin, 1999)
State v. Barnes
552 N.W.2d 857 (Court of Appeals of Wisconsin, 1996)
In Re Paternity of Dustine RP
518 N.W.2d 270 (Court of Appeals of Wisconsin, 1994)
Pophal v. Siverhus
484 N.W.2d 555 (Court of Appeals of Wisconsin, 1992)
Kaltenbrun v. City of Port Washington
457 N.W.2d 527 (Court of Appeals of Wisconsin, 1990)
State v. Vander Linden
414 N.W.2d 72 (Court of Appeals of Wisconsin, 1987)
State v. Van Straten
409 N.W.2d 448 (Court of Appeals of Wisconsin, 1987)
Lobermeier v. General Tel. Co. of Wisconsin
349 N.W.2d 466 (Wisconsin Supreme Court, 1984)
State v. Rosenfeld
286 N.W.2d 596 (Wisconsin Supreme Court, 1980)
Neely v. State
272 N.W.2d 381 (Court of Appeals of Wisconsin, 1978)
Wofford v. State
1978 OK CR 93 (Court of Criminal Appeals of Oklahoma, 1978)
Simpson v. State
266 N.W.2d 270 (Wisconsin Supreme Court, 1978)
Chart Ex Rel. Sommer v. General Motors Corp.
258 N.W.2d 680 (Wisconsin Supreme Court, 1977)
Karl v. Employers Insurance of Wausau
254 N.W.2d 255 (Wisconsin Supreme Court, 1977)
Sanford v. State
250 N.W.2d 348 (Wisconsin Supreme Court, 1977)
Hart v. State
249 N.W.2d 810 (Wisconsin Supreme Court, 1977)
King v. State
248 N.W.2d 458 (Wisconsin Supreme Court, 1977)
Ceplina v. South Milwaukee School Board
243 N.W.2d 183 (Wisconsin Supreme Court, 1976)
Hough v. State
235 N.W.2d 534 (Wisconsin Supreme Court, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
146 N.W.2d 801, 33 Wis. 2d 154, 1966 Wisc. LEXIS 879, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rausch-v-buisse-wis-1966.