Raitman v. McCune

1934 OK 180, 30 P.2d 878, 167 Okla. 511, 1934 Okla. LEXIS 598
CourtSupreme Court of Oklahoma
DecidedMarch 20, 1934
Docket21986
StatusPublished
Cited by4 cases

This text of 1934 OK 180 (Raitman v. McCune) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Raitman v. McCune, 1934 OK 180, 30 P.2d 878, 167 Okla. 511, 1934 Okla. LEXIS 598 (Okla. 1934).

Opinion

RILEX, C. J.

This action was commenced by defendant in error (in the court of common pleas of Tulsa county) against plaintiff in error to recover for services alleged to have been rendered in the preparation of plans and specifications for the erection of a certain building and for superintending the construction thereof, and to establish and enforce a laborer’s lien.

Plaintiff in his petition alleges, in substance, that he entered into an oral contract with defendant whereby defendant employed plaintiff to survey certain lots in the city of Tulsa owned by defendant, and to draw plans and specifications and superintend the construction of a two-story residence thereon, for which plaintiff was to receive compensation in an amount equal to 5 per cent, of the cost of said building; that he performed the services in compliance with his contract; that in addition to the services so rendered, he took out and paid for a building permit for defendant at a cost of $12; that the cost of construction of said building was $19,944.80, making the amount due for such services the sum of $997.24, to which should be added the $12 paid for the building permit; that defendant had paid plaintiff on account thereof the sum of $250, and no more, leaving a balance due of $759.24.

1-Ie also pleaded the preparation and filing of a lien statement as provided by law, attaching a copy thereof to his petition.

Defendant, by answer, amended answer, and second amended answer, admitted the employment of plaintiff by oral contract to furnish plans and specifications and superintend the construction of a building in replica or similar to the one in which defendant was then living and which was owned by plaintiff; he alleged, however, that the contract was that the plaintiff should have as compensation for his services the sum of $600 for the plans and specifications and $200 for superintending the- construction. He admitted the payment of $250. He denied that plaintiff had complied with the- contract, and alleged that on account of a breach thereof defendant had caused the employment to be terminated, and that he owed plaintiff nothing.

He then alleged that after plaintiff had filed his lien claim, defendant did dicharge and release same and deposited the cash and bond as provided for in section 7465, C. O. S. 1921 [O. S. 1931, sec. 10980],

By way of counterclaim, defendant reiterates his claim that the contract called for payment of only $800. He then alleged negligence and inefficiency on the part of plaintiff in preparing the plans and specifications in several particulars whereby he claims plaintiff had failed to properly prepare the plans of the building, resulting in the erection of a building different in several particulars, set out, from that he had contracted for; in that the living room was smaller than contemplated in the contract, one of the inside walls being placed some 18 inches from where it should have been; that certain changes had been made in the stairway, whereby he claimed to have been damaged more than $2,500, but he waived *513 tlie excess over $2,500, for which sum he prayed judgment against plaintiff.

Plaintiff replied by general denial of new matter.

The cause was tried to a jury, resulting-in a verdict and judgment for plaintiff in the sum of $759.24. The court allowed plaintiff an attorney’s fee in the sum of $300. From the judgment and order, defendant appeals.

There are nine assignments of error, but such of those as are presented in the brief of plaintiffs in error are presented under two propositions, stated as follows:

“1. A new trial must be granted for the reason that a lien was given for the' entire contract price, whereas the proof shows that plaintiff was discharged prior to full performance. He cannot have a lien for damages for breach of contract, and the allowance of such is reversible error.
“2. Since the plaintiff is not entitled to a lien, the judgment allowing him an -attorney’s fee is not proper.”

Defendant cites a number of authorities which in effect hold that one employed to superintend the construction of a building not completed because of the owner’s financial inability has an action for damages in which he can recover profits he would have made had the contract been fully performed, but that he cannot recover damages in an action to foreclose a mechanic’s lien.

The authorities cited have no application here. In the first place, plaintiff contended that he had fully complied with his contract and commenced the action to’ foreclose his lien. Defendant did not in his pleadings deny the contract, but contended for a different amount of compensation, and alleged that plaintiff had breached the contract. Furthermore, no lien was adjudged in favor of plaintiff. At the trial it was stipulated that defendant had made the deposit and given the bond provided for in section 7465, O. O. S. 1921 [O. S. 1931, sec. 10980].

Defendant pleaded that he had procured the discharge of the lien by depositing the money and giving the bond, and the court found that such deposit had been made, and the judgment does not give a lien for the amount of the claim or any other amount. After the deposit was made, the lien was discharged by operation of law. Thereafter it became a question of how much, if anything, plaintiff was entitled to recover. This issue was tried to the jury on conflicting evidence as to the terms of the contract as well as the alleged breach of the contract by plaintiff. True, the evidence does show that a very small amount of work remained to be done on the building at the time defendant discharged or attempted to discharge plaintiff. But the building was substantially completed. It is not shown that the contractor in doing whatever was necessary to complete the building was not guided by the instructions given by plaintiff before he was discharged. So far as the record shows, no one was employed to superintend the work necessary to complete the building.

Omissions or imperfections so slight that they cannot be regarded as an integral or substantive part of the original contract do not deprive .the contractor of his right to compensation. Whether a contract has been complied with is a question of fact for the trial court or jury, as the case may be, In this case the jury by its verdict must have found that plaintiff had complied with his contract. In this connection it must be borne in mind that the principal issue as formed by pleadings was not whether plaintiff had failed to furnish plans and specifications and superintend the construction of the building, but was as to what compensation plaintiff was to receive. Plaintiff contended that such compensation was to be 5 per cent, of the cost of the building, while defendant contended that the compensation provided for in the contract was $600 for the plans and specifications and $200 for superintending the construction. Defendant made no claim in his pleadings for a deduction on account of failure to completely superintend the construction.

The jury by its verdict must have found the contract price to be that claimed by plaintiff, otherwise the verdict could not have been for the full amount claimed.

In Gould v. McCormick (Wash.) 134 P. 679, a case in many respects like the one here under consideration, the Supreme Court of Washington quoted with approval from Sedgwick on Damages (9th Ed.) vol.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McGuigan v. Harris
1968 OK 58 (Supreme Court of Oklahoma, 1968)
Consolidated Cut Stone Co. v. Seidenbach
1937 OK 701 (Supreme Court of Oklahoma, 1937)
Long v. Higgins
1934 OK 422 (Supreme Court of Oklahoma, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
1934 OK 180, 30 P.2d 878, 167 Okla. 511, 1934 Okla. LEXIS 598, Counsel Stack Legal Research, https://law.counselstack.com/opinion/raitman-v-mccune-okla-1934.