Raeis Constructors, LLC v. Circle K Stores, Inc.

CourtDistrict Court, E.D. North Carolina
DecidedAugust 2, 2021
Docket5:18-cv-00240-FL
StatusUnknown

This text of Raeis Constructors, LLC v. Circle K Stores, Inc. (Raeis Constructors, LLC v. Circle K Stores, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Raeis Constructors, LLC v. Circle K Stores, Inc., (E.D.N.C. 2021).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF NORTH CAROLINA WESTERN DIVISION

NO. 5:18-CV-240-FL

RAEIS CONSTRUCTORS, LLC, ) ) Plaintiff/Counter-Defendant, ) ) v. ) ORDER ) CIRCLE K STORES, INC., ) ) Defendant/Counter-Plaintiff. )

This matter is before the court on the motion for summary judgment filed by defendant/counter-plaintiff Circle K Stores, Inc. (“Circle K”) (DE 76). The motion is not opposed. In this posture the issues raised are ripe for ruling. For the following reasons the motion is granted. STATEMENT OF THE CASE Plaintiff/counter-defendant Raeis Constructors LLC (“Raeis”) commenced this action on May 25, 2018, and filed the operative third amended complaint on January 28, 2019, asserting claims of breach of contract and a claim of quantum meruit/unjust enrichment, on the basis of Raeis’s provision of labor and materials for the construction of a Circle K store in Hope Mills, North Carolina (the “store”). Circle K moved to dismiss claims by Raeis, and it filed an answer asserting a counterclaim for breach of contract against Raeis, as well as a third party complaint against former third-party defendant Meco Builders, Inc. (“Meco”). On December 13, 2019, the court granted Circle K’s motion to dismiss, and it granted third-party defendant’s motion to dismiss Circle K’s action against Meco, in favor of arbitration. Raeis Constructors, LLC v. Circle K Stores, Inc., No. 5:18- CV-240-FL, 2019 WL 6826356, at *10 (E.D.N.C. Dec. 13, 2019). This left Circle K’s counterclaim against Raeis as the sole remaining claim in this matter.1 Following a period of discovery, Circle K filed the instant motion for summary judgment on May 28, 2021, relying upon a statement of material facts and the following exhibits and categories of exhibits: 1) contract between the parties, 2) correspondence between the parties, 3)

declaration of Wes Williams, construction manager for Circle K, 4) building permit issued for the construction of the store, 5) records and correspondence of the North Carolina Licensing Board (“NCLB”), 6) contract between Circle K and Meco, 6) an expert report by FTI Consulting, Inc. regarding damages. STATEMENT OF FACTS The undisputed material facts may be summarized as follows.2 Circle K and Raeis entered into a contract for construction of the store (hereinafter the “Agreement”). The Agreement states that Raeis’ work “shall be commenced on 7/12/17, and substantially completed on or before 11/20/2017 (the ‘Substantial Completion Date’), and shall be finally completed to the satisfaction

of Company by 11/20/2017.” Article 1(a) of the Agreement’s Terms and Conditions states that Raeis’ work “shall be performed in compliance with all applicable codes, laws, ordinances, rules, regulations, decisions, orders, and requirements of governmental agencies having jurisdiction” and that Raeis “shall obtain and pay for all permits, licenses, full inspection fees, taxes, and other fees

1 The court inadvertently closed the case in its December 13, 2019, order, and it neglected to recognize the remaining pendency of Circle K’s counterclaim against Raeis. Accordingly, on February 4, 2020, the court corrected and amended its December 13, 2019, order to specify that Circle K’s counterclaim against Raeis remains open and pending for adjudication.

2 Undisputed facts are drawn from Circle K’s statement of material facts. Where Circle K relies upon a statement of material facts that is not controverted, the court may accept those facts as true for purposes of summary judgment, under Local Rule 56.1(a)(2). In addition, the undisputed material facts regarding Circle K’s damages are drawn from Circle K’s exhibit 17 in support of summary judgment. required in performance of the Work, except as to those, if any, specifically identified in the Contract Documents as the responsibility of the Company.” Article 1(e) of the Agreement states that Raeis “represents that it is fully licensed by, authorized to perform the Work in, and registered to do business in the state where the Project is located.” Raeis did not commence work on the Project by July 12, 2017 as required under the terms

of the Agreement. Raeis did not perform all work in compliance with all applicable codes, laws, ordinances, rules, regulations, decisions, orders, and requirements of governmental agencies having jurisdiction as required under Article 1(a) of the Agreement’s Terms and Conditions. Raeis did not obtain and pay for all permits, licenses, full inspection fees, taxes, and other fees required in performance of its work on the Project as required under Article 1(a) of the Agreement’s Terms and Conditions. At the time Raeis entered into the Agreement, it was not fully licensed by or authorized to perform the work for the Project by the state of North Carolina as required under Article 1(e) of the Agreement’s Terms and Conditions. Raeis entered into the Agreement prior to obtaining a license from the NCLB. Thus, Raeis

was not allowed to enter into a contract where the cost of the undertaking was equal to or exceeded $30,000.00. Even after obtaining its license, Raeis performed work on the Project when its license only permitted it to perform work on projects where the cost of the undertaking was less than $500,000.00. Article 10 of the Agreement’s Terms and Conditions states, in relevant part: If Contractor . . . breaches any term of this Agreement . . . then Contractor shall be in default of this Agreement. Upon Contractor’s default, Company, without limiting or waiving any other rights which Company may have at law or equity, may . . . terminate this Agreement for cause . . . and seek compensation from Contractor for all sums Company expended in excess of the Contract Sum to complete the Work or portion thereof . . . withhold payments . . . and/or . . . seek from Contractor monetary damages in excess of any unpaid Contract Sum . . . including . . . attorneys’ fees, additional costs of other contractors to perform the Work, and damages for delay to the Project. Company shall be entitled to collect its reasonable attorneys’ fees and costs, including expert and consulting fees, incurred in enforcing any term of this Agreement or as a result of Contractor’s breach of any term of this Agreement. Including, without limitation participation in any settlement discussions, alternative dispute resolution processes, or litigation. Article 10(a)(1) of the Agreement’s Terms and Conditions states, in relevant part: If Contractor is in default of this Agreement at any time for any of the reasons identified in this Paragraph 10, Company may . . . after giving Contractor seven (7) days written notice (unless circumstances require shorter notice), terminate Contractor and exclude Contractor from the site and take possession or all materials, equipment, tools. and construction equipment and machinery . . . and finish the Work by whatever reasonable method Company may deem expedient. On or about October 27, 2017, Circle K sent a termination letter to Raeis in accordance with Article 10 of the Agreement. At the time of termination, Raeis had been paid $182,700.00 towards the contract price of $1,659,940.00.24. The Project was not completed by November 20, 2017 as required under the Agreement. Circle K incurred $625,708.00 in financial damages as a result of the breach by Raeis, calculated as follows: ca Piel als Cost to Complete the Project After Raeis & Meco Termination $1,671,923

Remaining Value of Raeis & Meco Contracted Work 91,238,738 Adjustments to Sela Completion Costs Unrelated to Remaining Raeis ($11,550) & Meco Work g-t- 1-10 me) mele jagi (ely| be □□□ Amounts Reimbursed to Sela to Pay Vendors Raeis Meco Failed to Pa $108,223 Lost Profits From Project Delays in Opening 995,851 Bee: boyy □□□□ (Ex. 17 (DE 77-17) at 6).

COURT’S DISCUSSION A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Diebold, Inc.
369 U.S. 654 (Supreme Court, 1962)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Cantrell v. Woodhill Enterprises, Inc.
160 S.E.2d 476 (Supreme Court of North Carolina, 1968)
Wells Fargo Ins. Servs. United States, Inc. v. Link
827 S.E.2d 458 (Supreme Court of North Carolina, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
Raeis Constructors, LLC v. Circle K Stores, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/raeis-constructors-llc-v-circle-k-stores-inc-nced-2021.