R. E. Bean Construction Company, Inc. v. Middlebury Associates & Middlebury Developers, Inc.

451 A.2d 1096, 142 Vt. 1, 1982 Vt. LEXIS 583
CourtSupreme Court of Vermont
DecidedSeptember 7, 1982
Docket227-81
StatusPublished
Cited by14 cases

This text of 451 A.2d 1096 (R. E. Bean Construction Company, Inc. v. Middlebury Associates & Middlebury Developers, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R. E. Bean Construction Company, Inc. v. Middlebury Associates & Middlebury Developers, Inc., 451 A.2d 1096, 142 Vt. 1, 1982 Vt. LEXIS 583 (Vt. 1982).

Opinion

Barney, C.J.

After seven years of litigation over a contract to build a shopping center in Middlebury, Vermont, the defendants bring their fifth appeal before this Court. See Pike Industries, Inc. v. Middlebury Associates, 136 Vt. 588, 398 A.2d 280 (1979), aff’d after remand, 140 Vt. 67, 436 A.2d 725 (1980), aff’d on rehearing, 140 Vt. 72, 436 A.2d 728 (1981); R. E. Bean Construction Co. v. Middlebury Associates, 139 Vt. 200, 428 A.2d 306 (1980). Once more we affirm the decision of the trial court.

The plaintiff, Bean, a general contractor, and the defendants, Middlebury Associates and Middlebury Developers, Inc., owner-developers, entered into arbitration proceedings in 1976 to resolve a contract dispute which arose in 1974 when Middlebury failed to pay Bean for its work on Middlebury’s shopping center and Bean subsequently abandoned the job. The arbitrators held evidentiary hearings, and one of the key issues on which Bean sought to produce evidence was the percentage of completion of the project at various stages of construction and at the time it left the job.

Middlebury’s lender had hired a New York engineering firm to oversee and formally report to it on progress at the construction site before funds were periodically released to Middlebury for payment to Bean. Bean, claiming that its work had been substantially completed, sought to submit these engineering reports to the arbitrator, but neither the lender nor the *4 engineering firm would release them directly to Bean without Middlebury’s consent. Although throughout the hearing Middlebury claimed that they would request the reports from the lender and submit them when they were available, the reports were never furnished to the arbitrators, and Middlebury eventually forwarded to them instead a letter from their lender stating that it never released such reports. Bean v. Middlebury, supra,, 139 Vt. at 213-14, 428 A.2d at 314.

After the evidentiary hearings were closed, and before the arbitration award was made, the plaintiff submitted to the arbitrator an affidavit from one of its officers stating that he had dealt with the defendants’ consulting engineer and that the engineer had told him, before Bean ceased work on the project, that in his opinion the project was 95.5% complete. The officer further claimed that the engineer had told him that a principal of Middlebury had copies of the status reports in his possession. Id. at 214, 428 A.2d at 314. Bean submitted four architectural drawings along with the affidavit. Id.

Middlebury objected to the late evidence on the ground that its submission without an opportunity for rebuttal and cross-examination was prejudicial and requested a reopening of the hearings. The arbitrators did not respond to this request and announced an award of $333,261.53 to Bean. Middlebury took the matter to superior court on a motion to vacate the award, but the motion was denied on the trial court’s finding that there was no indication that the arbitrators had relied on the late evidence in making their award. We reversed, noting that since the arbitrators had not expressly rejected the late evidence it had to be fairly assumed that it was considered, and remanded for a determination of whether (i) the evidence actually affected the award and (ii) Middlebury had had evidence which reasonably tended to rebut or modify the late evidence. Id. at 214-15, 428 A.2d at 314-15.

A hearing on the remand was scheduled in Addison Superior Court. Prior to the hearing Middlebury was notified that they would be expected to make an offer of proof at that time, and that if the offer was found meritorious additional time would be scheduled to take evidence. Middlebury made no objection to this procedure and filed written offers of proof consisting of a copy of a Vermont subpoena duces tecum ordering the New York engineering firm to produce its construction *5 status reports, and two documents entitled “offer of proof relative to rebuttal evidence” and “offer of proof that late evidence actually affected the award,” each of which purported to list Middlebury’s evidence on the issue.

The hearing was held on February 20, 1981, and took thirteen minutes. Middlebury supplemented their previously submitted offers of proof and requested an opportunity to cross-examine Bean’s affiant and its architect. Bean argued the impropriety of Middlebury’s offer of proof, consisting almost entirely, as it did, of proposed testimony by Middlebury’s attorney, and further maintained that the offers of proof were too general under Vermont standards. It also questioned the sudden apparent availability, five years after the arbitrators’ hearings, of the inspection status reports, as well as their materiality.

Middlebury’s offer of proof, as amended, was that the report of the inspection taken just after Bean left the job would show a completion rate of 92.3%. Bean contended that this would not rebut the affidavit of Bean’s officer that the engineer had told Mm that it was his opinion that the job was 95.5% complete, and that rebuttal evidence was specifically required by our remand order in Bean v. Middlebury, supra. In its brief Bean argues additionally that the two figures are substantially the same, especially in light of the fact that Middlebury had only paid out for a 50% completed job.

The trial court ruled that Middlebury had made no showing that they had evidence reasonably tending to modify or rebut the late evidence, or that the late evidence had actually affected the arbitrators’ award. The award was affirmed in accordance with our order in Bean v. Middlebury, supra, and the present appeal followed.

Middlebury now makes three claims. First they maintain that our remand order was for a full evidentiary hearing with opportunity to cross-examine Bean’s affiant and architect, and that such a hearing has not been held. Secondly they claim error in the trial court’s conclusion that their offers of proof were too general and failed to modify or rebut the late evidence submitted by Bean. Their third claim, apparently one for “fairness,” asks us to vacate the award or at least remand the cause on a statement of proceedings composed by Middle-bury’s attorney and offered gratuitously for the Court’s use, *6 since no transcript of the proceedings before the arbitrators was made from which it can be conclusively demonstrated whether or not the late evidence affected the award. We consider the defendants’ claims in the order they were raised.

The first claim is quickly disposed of with a review of our previous decision in this case prior to remand. There we said:

We cannot determine the extent of prejudice without knowing what evidence Middlebury would have brought forward if given an opportunity.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jesse deVos v. Kimberly Volk
Supreme Court of Vermont, 2014
Champlain Parkway Act 250
Vermont Superior Court, 2012
Pion Sand & Gravel Pit
Vermont Superior Court, 2010
Havill v. Woodstock Soapstone Co.
2007 VT 17 (Supreme Court of Vermont, 2007)
Gladstone v. Stuart Cinemas, Inc.
Vermont Superior Court, 2005
USGen New England, Inc. v. Town of Rockingham
2003 VT 102 (Supreme Court of Vermont, 2003)
In Re Lilly
795 A.2d 1163 (Supreme Court of Vermont, 2002)
State v. Ringler
571 A.2d 668 (Supreme Court of Vermont, 1989)
Matzen Construction, Inc. v. Leander Anderson Corp.
565 A.2d 1320 (Supreme Court of Vermont, 1989)
Sullivan v. R. E. Bean Construction Co.
515 A.2d 1063 (Supreme Court of Vermont, 1986)
A. Emilo Building Supply, Inc. v. R. E. Bean Construction Co.
503 A.2d 528 (Supreme Court of Vermont, 1985)
R. E. Bean Construction Co. v. Middlebury Associates
499 A.2d 764 (Supreme Court of Vermont, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
451 A.2d 1096, 142 Vt. 1, 1982 Vt. LEXIS 583, Counsel Stack Legal Research, https://law.counselstack.com/opinion/r-e-bean-construction-company-inc-v-middlebury-associates-middlebury-vt-1982.