Pike Industries, Inc. v. Middlebury Associates

398 A.2d 280, 136 Vt. 588, 1979 Vt. LEXIS 921
CourtSupreme Court of Vermont
DecidedJanuary 11, 1979
Docket57-78
StatusPublished
Cited by12 cases

This text of 398 A.2d 280 (Pike Industries, Inc. v. Middlebury Associates) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pike Industries, Inc. v. Middlebury Associates, 398 A.2d 280, 136 Vt. 588, 1979 Vt. LEXIS 921 (Vt. 1979).

Opinion

Barney, C.J.

All parties to this litigation concede that the plaintiff, Pike Industries, Inc., has not been paid for paving work done as a subcontractor on a shopping center construction project. The lack of payment, according to the findings, is not based on any challenge as to the quality of the plaintiff’s work. The key question relates to determining which party is responsible for making payment to the plaintiff, the general contractor, R. E. Bean Construction Company, or the owner/developer, a pair of companies, Middlebury Associates, and Middlebury Developers, Inc. These parties are all defendants in the action. Middlebury Associates contracted with the Bean company, and was the equitable owner of the property. Middlebury Associates also contracted with a related company, Middlebury Developers, Inc., with respect to financing, and that corporation held legal title to the premises. For the purposes of this appeal we will treat them as they treated themselves, as a single entity, referred to as Middlebury.

The Bean company entered into a contract with Middlebury to construct a shopping center for a price guaranteed not to exceed $1,045,000.00, subject to any increases based on change orders. Middlebury’s cost for the project was to be. determined by Bean’s “cost of the work” as defined in the contract, plus a fee of $41,800.00 to Bean. There was a date of December, 1973, for one part and May 31, 1974, for the balance by which time Bean was to “attempt” to complete the project.

The plaintiff, Pike, did not enter the picture until sometime in July, 1974, when it engaged with Bean by oral subcontract to do the paving work required by the contract with Middle-bury. This work it carried on continuously until October 18, 1974. At that time, fifty-one per cent of the paving work had been accomplished, but Pike had received no payment from any source for its work. As a result, a tentative decision to cease operations was made.

On that same day, according to the evidence, Pike’s representative was called by an agent of one of the principal tenants advising of the need to finish the paving so that the tenant could assume occupancy. On being told of the decision to stop work because of lack of payment, the tenant’s agent indicated *590 that there would be a call from the owner/developer, Middle-bury.

Such a call came about. Pike’s representative was urged by Middlebury’s agent to not only continue the paving, but expedite it. Authorization to work overtime was orally given and a representation made which, although the matter was disputed, the trial court found to be a guarantee by Middlebury to Pike of payment. A confirmatory telegram was sent from Middle-bury to Pike which read as follows:

Kegarding Middlebury Shopping Center persuant [sic] to our telephone conversation you are directed to bill Middle-bury Developers, Ine. directly for the work performed and you are further authorized to perform all necessary overtime to complete your work by Sunday, Oct. 20, 1974.

The paving work was in fact completed November 6, 1974. The lower court found that no loss or prejudice resulted from the postponed completion. At the completion of the paving a billing invoice was sent to Bean, with copies to Middlebury and others showing an amount due of $115,651.13. On November 11, 1974, according to the testimony, Middlebury advised Bean that Middlebury was terminating the contract and taking over construction. This action purported to be in accordance with a right of termination given the owner under the master contract with Bean. The findings do not reflect that the terminating action was initiated by Middlebury, but it is not a matter of dispute. The only controversy about it is whether or not the termination by Middlebury was based on justifiable cause within the provisions of the contract.

The pertinent provisions of the master contract, in evidence as an exhibit, gave to the owner, Middlebury, the right to terminate on seven days’ notice if certain circumstances, such as receivership, bankruptcy or failure to pay subcontractors, among others, pertain. In such a case, the owner may go ahead and complete the construction and recover from the contractor, Bean, any costs over the contract price. At the same time, the owner engages to become liable for obligations, commitments and unsettled claims already incurred in good faith by the contractor.

Middlebury did, in fact, proceed to complete the project. The result was that a dispute arose between it and Bean concern *591 ing termination and the attempt by Middlebury to assess the cost overruns against Bean. This led to the arbitration proceedings whose relevance to the litigation now before us was contested by Middlebury.

In the meantime, Pike, still having had no pay for the work it had done, filed a mechanic’s lien under 9 Y.S.A. § 1921 on December 11, 1974. On March 6, 1975, this action was brought to comply with 9 V.S.A. § 1924. The original complaint alleged direct contracts with Bean and with Middlebury Developers, Inc., that corporation having legal title to the premises at the time the lien was filed. The complaint was amended to include an allegation of direct contract between Pike and Middlebury Associates and a count that asserted that Middlebury Developers, Inc. had guaranteed payment to Pike for all indebtedness to it incurred by Bean or by Middlebury Associates. The Middlebury answer included two cross-claims: one against Bean for $600,000 damages based on breaches of the contract between Bean and Middlebury; the second, a claim against Bean for any amounts found owing from Middlebury to Pike. The answers also raised affirmative defenses based on the Statute of Frauds and lack of consideration as to any alleged agreement between Middlebury and Pike.

It was a separate suit by Bean against Middlebury arising out of this same construction project that gave rise to the arbitration proceedings already noted. The award in favor of Bean, which is still under appeal in state court, specifically omitted any consideration of the Pike claim and its allocation between the parties. All of the litigation was delayed while the arbitration award was tested in federal court. That action was dismissed.

Although the litigation arises from a complex state of facts, the issues on appeal involve only a few aspects of the whole relationship. In defense against the judgment in favor of Pike, Middlebury acknowledges that it made a contract directly with Pike. But Middlebury views that contract as only involving the authorization of and payment for overtime necessary under the arrangement evidenced by the telegram of October 18, 1974, already quoted. It is standing on its Statute of Frauds defense because of its claim that there was no intention of making an indemnity contract involved in the October, 1974 transaction.

*592 Taking as the first issue the sufficiency of the telegram put into evidence as the writing to satisfy the requirements of the Statute of Frauds, we find none of the parties strongly arguing its adequacy. Most of the briefing concerns itself with reasons in support of the nonapplication of the Statute of Frauds. Our examination of the case and the exhibits confirms that, under our law, satisfaction of the requirements of the Statute of Frauds was not demonstrated.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Boulger v. Wells Fargo
Vermont Superior Court, 2024
Ruggieri-Lam v. Oliver Block, LLC
120 F. Supp. 3d 400 (D. Vermont, 2015)
Lussier v. North Troy Engineering Co.
544 A.2d 1173 (Supreme Court of Vermont, 1988)
Contractor's Crane Service, Inc. v. Vermont Whey Abatement Authority
519 A.2d 1166 (Supreme Court of Vermont, 1986)
Sullivan v. R. E. Bean Construction Co.
515 A.2d 1063 (Supreme Court of Vermont, 1986)
Frank W. Whitcomb Construction Corp. v. Cedar Construction Co.
459 A.2d 985 (Supreme Court of Vermont, 1983)
Pike Industries, Inc. v. Middlebury Associates
436 A.2d 725 (Supreme Court of Vermont, 1981)
RE Bean Const. v. MIDDLEBURY, ETC.
428 A.2d 306 (Supreme Court of Vermont, 1980)
Lee v. State
338 So. 2d 395 (Mississippi Supreme Court, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
398 A.2d 280, 136 Vt. 588, 1979 Vt. LEXIS 921, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pike-industries-inc-v-middlebury-associates-vt-1979.