R. C. Stanhope, Inc. v. Roanoke Construction Company and Fidelity & Deposit Company of Maryland, and Lockwood Brothers, Inc., Third-Party

539 F.2d 992, 1976 U.S. App. LEXIS 11736
CourtCourt of Appeals for the Third Circuit
DecidedApril 19, 1976
Docket75-1804
StatusPublished
Cited by1 cases

This text of 539 F.2d 992 (R. C. Stanhope, Inc. v. Roanoke Construction Company and Fidelity & Deposit Company of Maryland, and Lockwood Brothers, Inc., Third-Party) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R. C. Stanhope, Inc. v. Roanoke Construction Company and Fidelity & Deposit Company of Maryland, and Lockwood Brothers, Inc., Third-Party, 539 F.2d 992, 1976 U.S. App. LEXIS 11736 (3d Cir. 1976).

Opinions

CRAVEN, Circuit Judge.

Stanhope sued Roanoke and its surety, Fidelity and Deposit Company of Maryland, in the Virginia state courts seeking recovery on Roanoke’s payment bond with the City of Richmond. Roanoke and Fidelity removed the case to federal court, with jurisdiction based upon diversity of citizenship. On the basis of stipulated or undisputed facts, the district court awarded summary judgment in favor of Stanhope in the amount of $28,110.76 plus costs. We affirm.

I.

On February 8, 1973, Roanoke contracted with the City of Richmond to construct a [993]*993storm sewer. Roanoke then procured from Fidelity a payment bond as required by Virginia statutes.1

On June 1, 1973, Roanoke subcontracted with Lockwood to perform certain jobs in the construction of the sewer. Significantly, Roanoke, as the general contractor, did not require that Lockwood post a subcontractor’s bond as required by Virginia law.2 Under the terms of the subcontract, Lockwood was to install steel “sheet pilings” along the length of a 1,100-foot ditch so that Roanoke could install the sewer drainpipe.

Lockwood did not own the steel sheet pilings used in performing the subcontract, but instead rented them from the plaintiff Stanhope. During the construction of the sewer, Lockwood fell behind in its rental payments to Stanhope, and when the project was completed, Lockwood failed to return the rented sheet piling. Lockwood, now bankrupt, has conceded that Stanhope has a valid claim against it both for delinquent rental charges, and for the value of the missing sheet piling, totaling approximately $27,000. It is clear that the sheet piling was removed from the ditch, as contemplated, and that it was not incorporated into the final job.

Stanhope, unable to recover against Lockwood, filed suit against Roanoke and Fidelity pursuant to § 11-23 of the Code of Virginia.3 This statute requires general construction contractors with any public agency to furnish the agency first, a performance bond solely for the protection of the public agency, and second, a payment bond for the protection of subcontractors, and for persons who perform labor and furnish materials to the general contractor. Roanoke furnished the City of Richmond with both the performance and payment bonds, with Fidelity as surety. This same statute, however, requires that the general contractor obtain from any subcontractor payment bonds for the protection of those who perform labor or furnish materials “in the prosecution of the work provided for in the subcontract.”4 Roanoke failed to do so. The statute clearly sets forth the consequences:

In the event a contractor fails to require from a subcontractor the bond provided for herein, any person who has and fulfills contracts directly with such subcon[994]*994tractor for performing labor and furnishing materials in the prosecution of the work provided for in the subcontract shall have a direct right of action against the obligors and sureties on the payment bond required of the contractor . . .5

The only issue on appeal is whether Stan-hope can bring itself within the language of the statute, i. e., do rental charges and the value of missing rental equipment constitute “materials furnished” within the meaning of § 11-23 of the Code of Virginia?

II.

What is meant by “materials furnished” as used in § 11-23? The phrase is not defined in the Code of Virginia, and has never been precisely defined by the Supreme Court of Virginia. Roanoke and Fidelity strongly contend that rental charges for materials used by a subcontractor and the value of unreturned rented equipment is not included in the definition of “materials furnished.” This position, however, overlooks two opinions of the Supreme Court of Virginia which support Stanhope’s position to the contrary. The district court found these cases persuasive, and we agree.

In New Amsterdam Casualty Co. v. More-trench Corp., 184 Va. 318, 35 S.E.2d 74 (1945), the Supreme Court of Virginia was required to construe contractual language in a payment bond virtually identical to that which appears in § 11-23. The facts in the Moretrench case were likewise quite similar to those presently before us. In Moretrench, the court held that rental charges for equipment leased to the general contractor did constitute “materials furnished” within the terms of the bond. The court further held that the value of missing leased equipment was within the coverage of the bond as constituting “materials furnished” in completing the contract. While Moretrench involved a bonding contract and the present appeal involves a statute, the bonding requirements are expressed in virtually identical terms. We are unconvinced that the Virginia Supreme Court would construe the same language differently solely because it appears in a statute rather than a contract, especially where the very purpose of the statute is to cover the failure to require a payment bond.

In Thomas Somerville Co. v. Broyhill, 200 Va. 358, 105 S.E.2d 824 (1958), again on similar facts, the Virginia Supreme Court held that § 11-23 entitles one who has furnished materials to a subcontractor to recover against the general contractor’s required payment bond. The court held:

Materialmen and subcontractors who furnish supplies or work for the principal who has contracted with the public agency mentioned in that section for the construction of the public buildings and improvements are unable to perfect mechanic’s liens against the property for their protection. They cannot avail themselves of the provisions of §§ 43-7 and 43-9, Code 1950, for liens cannot be perfected against the public buildings and other improvements. Section 11-28 is remedial in character, its language broad and inclusive, and obviously it was enacted to afford protection to materialmen and subcontractors. It must be liberally construed in their favor.
It is made manifest by this language that the intent of the statute is to protect those who furnish supplies, material and labor in and about the construction of the public buildings and improvements mentioned in the act, whether they be furnished to the principal contractor or to a subcontractor; of this a general contractor and his surety must take cognizance. They may readily protect themselves against the shortcomings of subcontractors by requiring bonds of the latter. [Emphasis added].

We reiterate the admonition of Somerville: Roanoke could easily have avoided this litigation simply by requiring a payment bond from its subcontractor. And Roanoke’s surety, Fidelity, is warned by the [995]*995statute of potential extension of its liability by reason of Roanoke’s failure to do so. The decision of the district court granting summary judgment in favor of Stanhope will be

AFFIRMED.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
539 F.2d 992, 1976 U.S. App. LEXIS 11736, Counsel Stack Legal Research, https://law.counselstack.com/opinion/r-c-stanhope-inc-v-roanoke-construction-company-and-fidelity-deposit-ca3-1976.