Queen Creek Summit, LLC v. Davis

201 P.3d 537, 219 Ariz. 576, 2008 Ariz. App. LEXIS 164
CourtCourt of Appeals of Arizona
DecidedOctober 30, 2008
Docket1 CA-SA 08-0205
StatusPublished
Cited by4 cases

This text of 201 P.3d 537 (Queen Creek Summit, LLC v. Davis) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Queen Creek Summit, LLC v. Davis, 201 P.3d 537, 219 Ariz. 576, 2008 Ariz. App. LEXIS 164 (Ark. Ct. App. 2008).

Opinion

OPINION

BARKER, Judge.

¶ 1 Queen Creek Summit, L.L.C. and the other petitioners (collectively, “QCS”) seek special action review of the superior court’s denial of their motion for judgment as a matter of law and grant of the Town of Gilbert’s (“Gilbert”) Application for Immediate Possession. The superior court found that QCS failed to meet its burden of proving that Gilbert had improperly concluded that the public good of locating its pipeline through the middle of Canyon State Academy outweighed the private injury to QCS. For the reasons set forth below, we affirm.

Facts and Procedural Background

¶2 Canyon State Academy is an all-male residential treatment facility and school located in Queen Creek, Arizona, at the intersection of Rittenhouse Road and Hawes *578 Road. On March 26, 2008, Gilbert instituted proceedings against Queen Creek Summit, LLC, the record landowner of the property where the academy is located, among others, to condemn a pipeline easement through the property. Gilbert also applied for an order to be let into possession of the property. Gilbert instituted these proceedings in connection with a public water works project to run a thirteen-mile pipeline from the Central Arizona Project (“CAP”) Canal to the South Water Treatment Plant.

¶ 3 Gilbert proposed to locate an east-to-west pipeline easement due north of QCS’s athletic fields, running through its horse pasture. It would run parallel to and abut an existing fifty-foot wide Bureau of Reclamation (“BOR”) easement on the property, essentially appending twenty feet to that easement. The BOR easement prohibits QCS from building any structures within the easement.

¶ 4 For the great majority of affected landowners, Gilbert was able to construct the pipeline along the periphery of their properties. Gilbert sited non-periphery easements on four other parcels owned by various government agencies. QCS’s property is the only private property where the pipeline would bisect the parcel of land.

¶ 5 Prior to the hearing on the possession order, QCS deposed Daniel J. Spitza, P.E., the principal engineer in charge of the project team designing and constructing the pipeline. QCS questioned Spitza extensively on Gilbert’s Corridor Evaluation Report, a study that analyzed two potential routes for the pipeline: (1) Ocotillo Road and (2) Queen Creek/Pima Road. The report provided a general overview of the monetary and non-monetary impacts involved in routing the line along each of these paths. In its final conclusions and recommendations, the report recommended the route along Queen Creek/ Pima Road but specifically noted that “[t]he corridor alignment around the Canyon State Academy ... will be further evaluated during the project’s design phase to determine the most feasible alignment in this area.”

¶ 6 In the deposition, Spitza testified that although Gilbert initially contemplated the proposed route in mid-2006, the report specifically left open the alignment details as to QCS’s property because of the need for more evaluation and a final determination. At the hearing, he asserted that the report was not intended to delineate where the pipeline would be located on anyone’s property.

¶ 7 In both the deposition and at the hearing, Spitza confirmed that although Gilbert provided a comprehensive evaluation of the monetary and nonmonetary impacts as to the Queen Creek Road corridor (affecting 139 parcels) versus the Ocotillo Road corridor (affecting 216 parcels), the team did not perform a similar evaluation of the different options for siting the pipeline either around or through QCS’s single parcel. Spitza Dep. 68:17-71:7, May 23, 2008; H’rg Tr. 70, June 13, 2008; Corridor Evaluation Report 3, 4. 1 However, Spitza testified that he recommended the current pipeline alignment to Gilbert only after several discussions with representatives of QCS, reviewing the different alignment options and coming to a consensus that the current alignment proposed was the preferred option of the representatives. Spitza Dep. 48:4-13, 55:2-13, 61:7-12, 84:9-13, 91:4-6; H’rg Tr. 49-51, June 13, 2008; Hr’g Tr. 12-13, June 24, 2008. Spitza identified John Motley and Barbara Ross as the representatives of QCS with whom he had conferred. 2 Spitza Dep. 48:4-8. Gilbert stipulated that it did not obtain consent from Ski Broman, the 100% owner of Queen Creek Summit, LLC, to construct the pipeline along the proposed route.

¶8 At the hearing, Spitza testified about the difficulties of siting the pipeline along the periphery of QCS’s property. He stated that siting the pipeline along QCS’s northern border would cost, at least, an additional *579 $850,000 and would be complicated by the Town of Queen Creek’s plan to realign Hawes Road. Hr’g Tr. 32-34, June 24, 2008. He dismissed siting the pipeline along the western and southern borders of QCS’s property because of additional costs related to “a number of existing utilities and easements” and restricted space for construction. Hr’g Tr. 39-40, June 13, 2008. He also rejected building on the existing Queen Creek Road right-of-way running through QCS’s property because QCS had constructed a number of buildings within that easement. Id. 48.

¶ 9 QCS introduced evidence that Canyon State Academy intended to expand its facilities to accommodate more students, including a field house arena built over the BOR easement and possibly built over the location for the proposed pipeline. Hr’g Tr. 42-50, 57, June 24, 2008. Rite of Passage, the long-term lessee of the property, planned to fund these expansions. Id. 47. A representative from Rite of Passage testified that he expected BOR to abandon its easement at some point in the future when it was no longer in use. Id. On cross examination, the representative admitted that he knew as early as August 2006 about Gilbert’s proposal to construct the pipeline across the property and that, as of June 2008, no construction plans had been filed with the Town of Queen Creek for approval. Id. 51-53, 57, 62.

¶ 10 On July 1, 2008, the trial court granted Gilbert’s application for the possession order and denied QCS’s motion for judgment as a matter of law. In its ruling, the court found that QCS had not met its burden to show on balance that the proposed route is “unnecessarily injurious.” The trial court subsequently granted an order of immediate possession on July 31, 2008.

¶ 11 This special action was filed on September 5, 2008, along with a motion to stay the trial court’s order of immediate possession. We declined the request for stay on September 8, 2008, and now address the propriety of the possession order. Special action review is appropriate in this case because there is no equally plain, speedy, or adequate remedy by appeal. Ariz.Rev.Stat. (“A.R.S”) § 12-120.21(A)(4) (2003); Ariz. R.P. Spec. Act. 1(a); Or sett/Columbia Ltd. P’ship v. Superior Court, 207 Ariz. 130, 132, ¶ 6, 83 P.3d 608, 610 (App.2004) (accepting special action review of an order of immediate possession, as “Orsett’s only adequate remedy is through special action”).

Discussion

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Schnurr v. Banner
Court of Appeals of Arizona, 2025
State v. foothills/hanke
Court of Appeals of Arizona, 2023
Dabrowski v. Bartlett
442 P.3d 811 (Court of Appeals of Arizona, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
201 P.3d 537, 219 Ariz. 576, 2008 Ariz. App. LEXIS 164, Counsel Stack Legal Research, https://law.counselstack.com/opinion/queen-creek-summit-llc-v-davis-arizctapp-2008.