Quanta Services, Inc. v. Zachary Bolling

CourtIntermediate Court of Appeals of West Virginia
DecidedMay 1, 2023
Docket22-ica-244
StatusPublished

This text of Quanta Services, Inc. v. Zachary Bolling (Quanta Services, Inc. v. Zachary Bolling) is published on Counsel Stack Legal Research, covering Intermediate Court of Appeals of West Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Quanta Services, Inc. v. Zachary Bolling, (W. Va. Ct. App. 2023).

Opinion

IN THE INTERMEDIATE COURT OF APPEALS OF WEST VIRGINIA

FILED QUANTA SERVICES, INC. May 1, 2023 Employer Below, Petitioner EDYTHE NASH GAISER, CLERK INTERMEDIATE COURT OF APPEALS OF WEST VIRGINIA vs.) No. 22-ICA-244 (JCN: 2021018967)

ZACHARY BOLLING Claimant Below, Respondent

MEMORANDUM DECISION

Petitioner Quanta Services, Inc. (“Quanta Services”) appeals the order of the Worker’s Compensation Board of Review (“Board”) dated October 3, 2022, that reversed the claim administrator’s order dated May 19, 2021. Respondent Zachary Bolling filed a timely response.1 Quanta Services did not file a reply. The issue on appeal is whether the Board erred in reversing the claim administrator, holding the claim compensable for electrical shock and sequelae of electrical shock, and remanding the claim back to the claim administrator to address temporary total disability (“TTD”) and other benefits.

This Court has jurisdiction over this appeal pursuant to West Virginia Code § 51- 11-4 (2022). After considering the parties’ briefs and oral argument, the record on appeal, and the applicable law, this Court finds no substantial question of law and no prejudicial error. For these reasons, a memorandum decision affirming the Board’s order is appropriate under Rule 21 of the Rules of Appellate Procedure.2

On March 10, 2021, Mr. Bolling, a groundman for Quanta Services, was working with a crew repairing an electrical transmission line tower. The crew was in the process of lowering the electrical transmission (“power”) line from the tower so that it could eventually be disconnected. One worker was in the bucket of the truck at the top of the tower, while Mr. Bolling and three other workers were on the ground at the bottom of the tower. The power line was grounded to the tower structure and was tested for voltage which gave a reading of zero volts. The ground wire to the tower was not long enough for the

1 Petitioner is represented by Daniel G. Murdock, Esq. Respondent is represented by Kelly Elswick-Hall, Esq. 2 The Court acknowledges that this matter was presented for oral argument on February 28, 2023, pursuant to Rule 19 of the Rules of Appellate Procedure.

1 power line to be lowered all the way to the ground, so a new ground wire was attached from the power line to a new grounding rod driven into the ground, and the ground to the structure was removed. There is a dispute about the depth the grounding rod was driven into the ground.

Mr. Bolling and the three other workers below, including his immediate foreman, Freddie Ray Boggs, took hold of the power line and were maneuvering it into position in order to attach a grip to the power line to anchor the line to a bulldozer. According to Mr. Boggs, Mr. Bolling was the closest worker to the grounding rod and was holding both the power line and a rigging cable with a large grip attached to it, which was connected to a steel choker on the nearby dozer. Mr. Bolling was the only crewmember who was holding both the power line and the rigging cable. According to Mr. Boggs, and Jason Bryant, a crewmember, one of the crew told Mr. Bolling to let go of the power line, but he could not; he tensed up and collapsed on the ground.

Mr. Bolling lost consciousness and was not breathing. One of his co-workers began CPR while Mr. Boggs ran to the truck and got the automated external defibrillator (“AED”), which is kept on these worksites due to the risk of electric shock and cardiac arrest. The AED was placed on Mr. Bolling’s chest and detected that he needed a shock, so a shock was deployed. Mr. Bolling began to take very shallow breaths and gasps of air but remained unconscious. Mr. Bolling was then transported by helicopter to Charleston Area Medical Center (“CAMC”).

Later that day, Mr. Boggs returned to the site to secure the power line the crew was working on. When he grabbed the power line that was still attached to the grounding rod, Mr. Boggs was shocked. The power line was then tested and showed 600 volts of power, even though it was still connected to the same grounding rod.3 After this incident, the crew moved the grounding rod to the base of the structure, which was determined to be a lower impedance path to the ground, and the crew was able to get a 0v reading on the conductor at that time and prior to the start of work the next day.

The next day, on March 11, 2021, an incident investigation report was completed by AEP Transmission, indicating that Mr. Bolling and his work crew were tasked with moving a 345kv conductor which had been de-energized and grounded. There were three crew members, two were holding onto the conductor while a third was tasked with installing a grip. Approximately thirty seconds into assisting with the catching of the

3 Mr. Boggs told the AEP representative on site, Josh Fisher, that someone needed to call the hospital and inform medical personnel that Mr. Bolling may have been shocked. However, nobody called the hospital to inform them, and it was not until sometime after multiple diagnostic tests were completed, trying to identify the root cause of Mr. Bolling’s episode, that it was revealed he might have been shocked.

2 conductor, one crewmember (Mr. Bolling) began to show symptoms of a seizure. Later that day, it was discovered that although the power line was supposedly grounded, there was a measurable amount of induced voltage (500v-600v) on the grounded conductor where the crew had been working. Nevertheless, although the report concluded that Mr. Bolling could have been negatively affected by the presence of induced voltage on the conductor, that it was unlikely, as there were at least two other crew members in contact with the conductor a few feet away who were not affected.

From March 10, 2021, to March 16, 2021, Mr. Bolling was examined by numerous medical personnel. During this time period, it was unclear what caused Mr. Bolling to experience his episode on the date of injury, since it was believed that the power line was grounded and Mr. Bolling could not have sustained an electric shock. Neither Mr. Bolling nor his medical providers were aware that shortly after Mr. Bolling’s episode, it was discovered that the power line was still energized and there was actual potential for an electrical shock.4 Numerous doctors stated that they believed it was seizure like and could have been caused by the medications he was taking at the time. Notably, on March 13, 2021, Mr. Bolling was seen by Carl Musser, Jr., M.D., a cardiac electrophysiologist. Dr. Musser at that time stated that “[p]atient’s syncope very concerning for primary arrythmia issue as I do not believe he was electrocuted.” Further, Dr. Musser’s assessment stated, “[h]istory and symptoms are suggestive of possible seizure activity, especially given that bystanders noticed that he was shaking and foaming at the mouth. Again, neither Mr. Bolling nor his medical providers were aware of the real potential for an electric shock until after Mr. Bolling returned to work in April 2021, when he was advised by a co-worker that voltage had been discovered on the line hours after his episode. Once Dr. Musser learned about that voltage on the line, he determined that Mr. Bolling had suffered an electrical shock on the day of the incident.

By order dated May 19, 2021, the claim administrator denied Mr. Bolling’s claim on the basis that he did not suffer an injury in the course of and resulting from his employment. On October 27, 2021, Mrs. Bolling signed an affidavit, and on December 21, 2021, she was deposed. She stated, among other things, that after regaining consciousness, Mr. Bolling indicated “that he was shocked and felt it go into his left finger and he had his left elbow on the line.” Notably, Mrs. Bolling also stated that she continued to text Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gary E. Hammons v. W. Va. Ofc. of Insurance Comm./A & R Transport, etc.
775 S.E.2d 458 (West Virginia Supreme Court, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
Quanta Services, Inc. v. Zachary Bolling, Counsel Stack Legal Research, https://law.counselstack.com/opinion/quanta-services-inc-v-zachary-bolling-wvactapp-2023.