Quam Construction Co., Inc. v. City of Redfield

770 F.3d 706, 2014 U.S. App. LEXIS 20136, 2014 WL 5334781
CourtCourt of Appeals for the Eighth Circuit
DecidedOctober 21, 2014
Docket14-1037
StatusPublished
Cited by3 cases

This text of 770 F.3d 706 (Quam Construction Co., Inc. v. City of Redfield) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Quam Construction Co., Inc. v. City of Redfield, 770 F.3d 706, 2014 U.S. App. LEXIS 20136, 2014 WL 5334781 (8th Cir. 2014).

Opinion

KELLY, Circuit Judge.

Quam Construction Co., Inc. (Quam) appeals from the district court’s order denying its motion to compel arbitration for contract disputes between Quam and the City of Redfield, South Dakota (the City). Because the parties’ contract does not mandate arbitration, we affirm the judgment.

I. Background

The City and Quam entered into a construction contract that included, among other things, the installation of pipes at the job site. After issues arose regarding the subsurface ground conditions where the pipes were to be installed, the parties disagreed about Quam’s obligations under the contract. The parties attempted mediation in accordance with their contract. Mediation failed, and Quam served the City with a demand for arbitration. The City refused to arbitrate. Quam then petitioned the district court to compel arbitration under 9 U.S.C. § 4 and moved to compel the City to arbitrate. The district court 1 denied Quam’s motion, and Quam appealed. This court has jurisdiction on appeal under 9 U.S.C. § 16(a)(1)(B) and 28 U.S.C. § 1294(1).

II. Discussion

“We review de novo the district court’s denial of a motion to compel arbitration based on contract interpretation.” Indus. Wire Prods., Inc. v. Costco Wholesale Corp., 576 F.3d 516, 520 (8th Cir.2009) (quotation omitted). “If the district court’s order concerning arbitrability is based on factual findings, we review such findings for clear error.” Lyster v. Ryan’s Family Steak Houses, Inc., 239 F.3d 943, 945 (8th Cir.2001). “A dispute must be submitted to arbitration if there is a valid agreement to arbitrate and the dispute falls within the scope of that agreement.” Id. The issue in this case lies with the first step — determining whether there is a valid agreement mandating arbitration if a dispute arises that cannot otherwise be resolved.

*708 “[Arbitration is a matter of contract and a party cannot be required to submit to arbitration any dispute which he has not agreed so to submit.” AT & T Techs., Inc. v. Commc’ns Workers of Am., 475 U.S. 643, 648, 106 S.Ct. 1415, 89 L.Ed.2d 648 (1986) (quotation omitted). “Unless the parties clearly and unmistakably provide otherwise, the question of whether the parties agreed to arbitrate is to be decided by the court, not the arbitrator.” Id. at 649, 106 S.Ct. 1415. “State contract law governs whether an arbitration- agreement is valid.” Lyster, 239 F.3d at 946. Under South Dakota law, “[a] contract is to be examined as a whole and all provisions read together to construe the contract’s meaning.” City of Watertown v. Dakota, Minn. & E.R. Co., 551 N.W.2d 571, 575 (S.D.1996).

Paragraph 26(a) of the parties’ contract states as follows:

Any controversy or claim arising out of or related to the contract, or the breach thereof, shall first be submitted to the American Arbitration Association Mediation Department. A mutually agreed upon qualified alternative dispute organization may be used.
Mediation shall continue (1) until resolution of the dispute or (2) until the mediator notifies the parties that it is unlikely that the dispute will be resolved through mediation.
Arbitration: If the dispute is not resolved through mediation, the parties may submit the controversy or claim to Arbitration. If the parties agree to arbitration, the following will apply:
The Contractor shall not cause a delay of the work because of the pendency of arbitration proceedings, except with the written permission of the Engineer, and then only until the arbitrators shall have an opportunity to determine whether or not the work shall continue until they decide the matters in dispute.
The demand for arbitration shall be delivered in writing to the Engineer and the adverse party, either personally or by registered mail to the last known address of each, within ten days of the receipt of the Engineer’s decision, and in no case after final payment has been accepted except as otherwise expressly stipulated in the Contract Documents. If the Engineer fails to make a decision within a reasonable time, a demand for arbitration may be made as if his decision had been rendered against the demanding party.

(Emphasis added). Paragraph 26(b) details requirements for the selection of the arbitrator and the power of the arbitrator or arbitrators to enter a binding decision. The end of paragraph 26(b) reads: “If there be one arbitrator, his decision be [sic] binding. If three, the decision of any two shall be binding in respect to both the matters submitted to and the procedure followed during the arbitration. Such decision shall be a condition precedent to any right of legal action.” (Emphasis added). Paragraph 26(c) articulates the arbitration procedure.

The City asserts that this case is simple: Because the contract explicitly states “if the parties agree to arbitrate,” arbitration is not mandatory. According to the City, this language expressly means that both parties must agree before any dispute proceeds to arbitration. Under South Dakota law, “[a]n agreement to agree does not fix an enforceable obligation. It is indefinite, vague, and uncertain. An agreement must be sufficiently definite to enable a court to give it an exact meaning.” Estate of Fisher v. Fisher, 645 N.W.2d 841, 847 (S.D.2002) (quotation omitted). The language in this contract “if the parties agree to arbitrate *709 suggests the obligation under South Dakota law is uncertain, and thus unenforceable.

Quam, on the other hand, stresses that under South Dakota law, “[a]n interpretation which gives a reasonable and effective meaning to all the terms [of a contract] is preferred to an interpretation which leaves a part unreasonable or of no effect.” Nelson v. Schellpfejfer, 656 N.W.2d 740, 744 (S.D.2003). Quam points to the contract language specifying that the arbitrator’s decision is a “condition precedent to any right of legal action” to support its argument that arbitration is mandatory under the contract. “A condition precedent is a fact or event which the parties intend must exist or take place before there is a right to performance [under the contract].” Weitzel v. Sioux Valley Heart Partners, 714 N.W.2d 884, 895 (S.D.2006) (quotation omitted).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
770 F.3d 706, 2014 U.S. App. LEXIS 20136, 2014 WL 5334781, Counsel Stack Legal Research, https://law.counselstack.com/opinion/quam-construction-co-inc-v-city-of-redfield-ca8-2014.