Pyco Supply Co. Inc. v. American Centennial Ins. Co.

354 S.E.2d 360, 85 N.C. App. 114, 1987 N.C. App. LEXIS 2565
CourtCourt of Appeals of North Carolina
DecidedApril 7, 1987
Docket8617SC684
StatusPublished
Cited by5 cases

This text of 354 S.E.2d 360 (Pyco Supply Co. Inc. v. American Centennial Ins. Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pyco Supply Co. Inc. v. American Centennial Ins. Co., 354 S.E.2d 360, 85 N.C. App. 114, 1987 N.C. App. LEXIS 2565 (N.C. Ct. App. 1987).

Opinions

[115]*115GREENE, Judge.

This is an appeal from a summary judgment for plaintiff on a construction payment bond. The pleadings and affidavits before the trial court tended to show that, on or about 28 September 1982, the Town of Pilot Mountain, North Carolina let four contracts for the construction of water pipeline improvements. Carolina Road Builders, Inc. (hereinafter, “CRB”) won three of the four contracts. As required under N.C. Gen. Stat. Sec. 44A-25 et seq. (1984), CRB gave three payment bonds respectively covering each of the three water project contracts. American Centennial Insurance Company (hereinafter, “American” or “defendant”) executed all three payment bonds as surety for payment of labor and materials furnished in connection with CRB’s three contracts. Each of the three payment bonds was separately numbered. Each bond covered one water project contract, which contracts were denominated “Water Line Improvements Contracts” and numbered “One,” “Two,” and “Four,” respectively.

On 2 November 1984, plaintiff brought suit against American on one of its bonds. In its original complaint, plaintiff alleged it had furnished certain materials to CRB between November 1982 and January 1984 “in connection with a contract for construction and completion of water line improvements for the Town of Pilot Mountain, North Carolina.” Plaintiff noted and attached to its original complaint a copy of “Water Line Improvements Contract No. Two.” It likewise attached the specific payment bond given by American in connection with Contract No. Two. American answered in part that plaintiffs action on this bond (hereinafter, “Bond No. Two”) was barred by limitations since all work had ceased under Contract No. Two on 24 June 1983. American argued that Bond No. Two itself provided suit must commence within one year from the date work ceased. American subsequently moved for summary judgment.

On 24 October 1985, plaintiff moved to amend its original complaint. It alleged in part that Pilot Mountain had furnished it the incorrect bond and contract and that the materials for which it remained unpaid were furnished in connection with CRB’s work under Contract No. Four. CRB’s affidavit showed its work under Contract No. Four was completed on 7 March 1984, less than one year before plaintiffs original complaint, but more than one year [116]*116before plaintiffs motion to amend its complaint. The trial court granted plaintiffs motion to amend its original complaint to state a claim under Bond No. Four and granted summary judgment for defendant on plaintiffs original action on Bond No. Two. Defendant’s answer to plaintiffs amended complaint included a plea of statutory limitation under N.C. Gen. Stat. Sec. 44A-28(b). Both parties moved for summary judgment on plaintiffs amended complaint. The trial court granted summary judgment for plaintiff in the amount of $14,305.77. Defendant appeals.

The issues before this Court are: 1) whether the one-year period set forth by N.C. Gen. Stat. Sec. 44A-28(b) is a procedural statute of limitation or a substantive statute of repose; 2) whether plaintiffs amended complaint relates back to the date of plaintiffs original complaint under N.C.R. Civ. P. 15(c); and 3) whether plaintiffs amended complaint commenced action upon Bond No. Four within one year of “final settlement” under Section 44A-28(b).

I

We note at the outset the trial court awarded damages against defendant in its summary judgment. Therefore, the trial court’s judgment is final and appealable. Beck v. American Bankers Life Ass. Co., 36 N.C. App. 218, 243 S.E. 2d 414 (1978).

We first determine the correct limitation period. Bond No. Four provided:

That no suit or action shall be commenced hereunder by any claimant . . . after the expiration of one (1) year following the date on which Principal ceased work on said Contract, it being understood, however, that if any limitation embodied in the Bond is prohibited by any law controlling the construction hereof, such limitation shall be deemed to be amended so as to be equal to the minimum period of limitation permitted by such law. [Emphasis added.]

In all cases of public construction for which a payment bond is required under N.C. Gen. Stat. Sec. 44A-26, the provisions of the “Model Payment and Performance Bond Act,” N.C. Gen. Stat. Sec. 44A-25 et seq., are conclusively presumed to be written into every such bond. N.C. Gen. Stat. Sec. 44A-30(b). Section 44A-30(a) of the Act states that no contract between a contracting body, [117]*117contractor or surety may reduce the period of time for commencing action under Section 44A-28(b). Section 44A-28(b) provides:

No action on a payment bond shall be commenced after the expiration of the longer period of one year from the day on which the last of the labor was performed or material was furnished by the claimant, or one year from the day on which final settlement was made with the contractor. [Emphasis added.]

The contractual provisions of Bond No. Four seek to shorten the limitation period to the minimum allowed under Section 44A-28(b). Since the statute instead provides for the longer period, we disregard the contractual limits set out in Bond No. Four to the extent they would reduce the limitation period allowed under Section 44A-28(b).

The trial judge allowed plaintiff to amend its original complaint to allege a claim under Bond No. Four and relate the amendment back to the date of plaintiffs original pleading under N.C. Civ. P. 15(c). However, defendant contends commencing suit on Bond No. Four within the one-year period provided in Section 44A-28(b) is an absolute condition precedent to its alleged liability to plaintiff. Defendant therefore argues its liability on Bond No. Four had expired and could not be revived by plaintiffs procedural amendment. Plaintiff contends the limitation period merely limits plaintiffs remedy and is thus subject to Rule 15(c) as any other statute of limitation. In order to determine the propriety of the trial court’s allowing the amendment’s relation back, we first consider whether Section 44A-28(b) is a substantive statute of repose or merely a procedural statute of limitation.

Our Supreme Court has recently discussed the distinction between statutes of repose and statutes of limitation:

Statutes of limitation are generally seen as running from the time of injury, or discovery of the injury in cases where that is difficult to detect. They serve to limit the time within which an action may be commenced after the cause of action has accrued. Statutes of repose, on the other hand, create time limitations which are not measured from the date of injury. These time limitations often run from defendant’s last act giving rise to the claim or from substantial completion of some service rendered by defendant.

[118]*118Trustees of Rowan Tech. College v. J. Hyatt Hammond Assoc., Inc., 313 N.C. 230, 234 n.3, 328 S.E. 2d 274, 276-77 n.3 (1985). In Black v. Littlejohn, 312 N.C. 626, 633, 325 S.E. 2d 469, 474-75 (1985), the Court stated:

Unlike an ordinary statute of limitations which begins running upon accrual of the claim . . ., the period contained in the statute of repose begins when a specific event occurs, regardless of whether a cause of action has accrued or whether any injury has resulted. . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cencomp, Inc. v. Webcon, Inc.
579 S.E.2d 482 (Court of Appeals of North Carolina, 2003)
Tipton & Young Construction Co. v. Blue Ridge Structure Co.
446 S.E.2d 603 (Court of Appeals of North Carolina, 1994)
Town of Pineville v. Atkinson/Dyer/Watson Architects, P.A.
442 S.E.2d 73 (Court of Appeals of North Carolina, 1994)
Pyco Supply Co. v. American Centennial Insurance
364 S.E.2d 380 (Supreme Court of North Carolina, 1988)
Pyco Supply Co. Inc. v. American Centennial Ins. Co.
354 S.E.2d 360 (Court of Appeals of North Carolina, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
354 S.E.2d 360, 85 N.C. App. 114, 1987 N.C. App. LEXIS 2565, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pyco-supply-co-inc-v-american-centennial-ins-co-ncctapp-1987.