Pyburn v. Popich Marine Construction, Inc.

186 So. 2d 674, 1966 La. App. LEXIS 5148
CourtLouisiana Court of Appeal
DecidedMay 16, 1966
DocketNo. 1936
StatusPublished
Cited by3 cases

This text of 186 So. 2d 674 (Pyburn v. Popich Marine Construction, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pyburn v. Popich Marine Construction, Inc., 186 So. 2d 674, 1966 La. App. LEXIS 5148 (La. Ct. App. 1966).

Opinion

HALL, Judge.

This is a suit brought by DeWitt L. Py-burn and Leo M. Odom, d/b/a Pyburn & Odom, Consulting Engineers, in which they seek to recover the sum of $7,171.68 plus interest, costs and attorney’s fees allegedly due them for professional engineering fees, services, and work done and materials furnished in connection wtih the construction of the Sunshine Bridge over the Mississippi River near Donaldsonville. Made defendants are Popich Marine Construction, Inc.; Steers-Morrison-Keller (a joint venture); and American Employers’ Insurance Company.

That plaintiffs rendered the services to Popich Marine Construction, Inc. and the liability of that corporation therefor is undisputed.

Plaintiffs sought to hold Steers-Morrison-Keller and American Employers’ Insurance Company liable in solido with Pop-ich under and by virtue of the provisions ■of the Public Contracts Statute, LSA-R.S. 38:2241 et seq.

After suit was filed Popich Marine Construction, Inc. was placed in bankruptcy and on the day of the trial plaintiffs dismissed their suit against Popich without prejudice and proceeded against the other two defendants.

Following the trial judgment was rendered in favor of plaintiffs and against Steers-Morrison-Keller and American Employers’ Insurance Company in solido for the full amount of plaintiffs’ claim, plus interest, costs and 10% attorney’s fees. Steers-Morrison-Keller and American Employers’ Insurance Company appealed.

The record reveals the following undisputed facts:

Steers-Morrison-Keller was the prime contractor for the construction of the substructure of the bridge. American Employers’ Insurance Company was the surety on the prime ■ contractor’s bond. Part of the work called for by the prime contract was the fabrication of three willow mats and the placing thereof on the river bottom to prevent scouring around the piers. Steers-Morrison-Keller sub-contracted this part of the work to Popich Marine Construction, Inc. Popich was required to sink each of the three large (approximately 28CK x 45CK) willow mats and to secure same on the river bottom prior to the placing by the prime contractor of the pier caissons, and for this reason each mat had to be constructed by Popich with a hole in the center thereof in order to permit the caissons to be sunk through the mats and into the mud of the river bottom. In view of the river currents the most difficult and exacting part of the work undertaken by Popich was to sink the mats so that when they were secured on the bottom of the river the holes in the mats would be in the exact position fixed by the plans and specifications for the location of the bridge piers. This part of the job required engineering services.

On May 21, 1962 representatives of Pop-ich visited plaintiffs’ office in Baton Rouge and requested plaintiffs to perform the engineering services required in sinking the mats. Thereafter, on May 28, Mr. Higgs of [676]*676plaintiffs’ firm met with representatives of Popich and representatives of Steers-Morrison-Keller at the prime contractor’s office in Donaldsonville for the purpose of discussing the exact nature of the services to be performed by plaintiffs. Following this meeting plaintiffs “developed a plan for the sinking of the mats and a plan for providing surveys and necessary actions for locating the mat in its correct position.” Initial recommendations were given to Pop-ich on June 4, 1962 and on June 14, 1962 detailed drawings were submitted. The resulting agreement between Popich and plaintiffs was formalized in a “purchase order” issued by Popich Marine Construction, Inc. to Pyburn & Odom dated August IS, 1962 setting forth a schedule of charges to be made by Pyburn & Odom to Popich as follows:

$125.00 Per Diem — Each Principal
Actual Cost Expenses — Travel
Actual Cost Office (reproductions, telephone, etc.)
$15.00 per day plus .15 per Transportation: Survey Wagon
mile
.10 per mile. Passenger Cars
Cost plus 100% Assist. Engr’s., Survey Crews, draftsmen
$75.00 per day Fathometer:
or $225.00 per week
Actual Cost. Mise. Field Equip. & Special Field Supplies

Pyburn & Odom’s work consisted in making soundings and doing other preliminary survey work on the job site. Thereafter they developed a system for lowering the mats and in connection therewith made estimates of the current forces, the amount of ballast rock required, the type of rigging and the size of the lines and cables required, and how the equipment would be rigged so that adjustments in the positions of the mats could be made during the lowering process. These calculations and plans were made in plaintiffs’ office in Baton Rouge.

The actual lowering of each of the three mats to the river bottom was accomplished in the following manner under the plans and system developed by Pyburn & Odom: Each mat was floated out on the river surrounded by barges to which it was attached by ropes. The position of the mat and barges in the river was held and controlled by a cable running to a winch located on a barge which was securely anchored some distance upstream. The barges surrounding the mats were operated by Popich’s crews. Pyburn & Odom constructed and manned with its own crew a control tower situated on a barge positioned in the center hole in the mat. From this tower steel wires were run to various surveyed points on the mats so that by means of a plumb line and sightings to various fixed points on shore the exact position of the mat as it was sunk by stages (by means of rock ballast) was at all times known to Pyburn & Odom’s engineers. It was their duty to give directions so that precise adjustment of the mat’s position as it was gradually sunk could be made by means of the winch on the barge anchored upstream. Their job was completed as soon as all three mats were secured on the river bottom with the mat holes in proper position for the pier caissons to pass through.

Not having been paid for their services plaintiffs recorded a sworn statement of their claim under the provisions of the Public Contract Statute, LSA-R.S. 38:2241 et seq., gave due notice of the filing thereof as required by law, and on November 19, 1962 made formal demand for payment of their claim by means of certified mail addressed to each of the defendants. When [677]*677payment was not forthcoming plaintiffs filed this suit on January 9, 1963.

Plaintiffs had no direct contractual relationship with the prime contractor, Steers-Morrison-Keller, and their right of recovery against the prime contractor and its surety is dependent upon the provisions of the Public Contracts Law.

We quote with approval the following excerpts from the learned Trial Judge’s written “Reasons for Judgment”:

“The plaintiffs contend that they had a written contract with Popich to do certain work; that, therefore, they are subcontractors of the subcontractor, Popich, and as such entitled under the statute to recover the amount of their claim in full, relying principally upon the case of Chil-ders v. City of Monroe [10 La.App. 701], 122 So. 135.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Woodrow Wilson Construction Co. v. James A. Teague Rental Equipment, Inc.
598 So. 2d 1228 (Louisiana Court of Appeal, 1992)
Harvey Canal Towing Co., Inc. v. Gulf South Dredging Co., Inc.
345 So. 2d 567 (Louisiana Court of Appeal, 1977)
Coating Specialists, Inc. v. Pat Caffey Contractor, Inc.
194 So. 2d 380 (Louisiana Court of Appeal, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
186 So. 2d 674, 1966 La. App. LEXIS 5148, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pyburn-v-popich-marine-construction-inc-lactapp-1966.