Puget Sound Bridge & Dredging Co. v. Frye

252 P. 546, 142 Wash. 166, 1927 Wash. LEXIS 1040
CourtWashington Supreme Court
DecidedJanuary 25, 1927
DocketNo. 20170. Department One.
StatusPublished
Cited by23 cases

This text of 252 P. 546 (Puget Sound Bridge & Dredging Co. v. Frye) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Puget Sound Bridge & Dredging Co. v. Frye, 252 P. 546, 142 Wash. 166, 1927 Wash. LEXIS 1040 (Wash. 1927).

Opinion

Fullerton, J.

This is an appeal from a judgment entered upon an award made in an arbitration proceeding.

On August 3, 1923, the appellant, Charles H. Frye, being then the owner of certain tideland lots and blocks situated in the city of Seattle, entered into a contract with the respondent, Puget Sound Bridge & Dredging Company, by the terms of which the respondent agreed to fill the lots and blocks, together with the adjoining streets, with earth by hydraulic sluicing to stipulated levels. For the service, the appellant agreed to pay the respondent “twenty-three and one-half cent's (23%) per cubic yard for all earth placed in the fill . . . .,” and to make the payments from time to time as the work progressed, according to estimates *168 made by tbe engineer in charge. The respondent immediately entered upon the performance of the work, and in the early part of the year 1925, claimed to have completed it, and claimed that there was a balance due it upon the contract. Changes had been made in the original plans and specifications during the progress of the work by the mutual agreement of the parties, and these, with other matters, gave rise to differences between the parties as to the questions whether the work had been performed according to the terms of the contract with the subsequent modifications, and whether there was any balance owing to the respondent. To settle these differences, the parties agreed to submit them to the arbitration of one R. H. Thomson. They thereupon entered into the following agreement:

“It is agreed by Charles H. Frye, party of the first part, and Puget Sound Bridge & Dredging Company, a Nevada corporation, party of the second part, as f ollows:
“(1.) The parties hereto entered into a certain written agreement, a copy of which is hereto annexed, whereby first party employed second party to fill by hydraulic sluicing certain portions of the Seattle Tide Lands described in said contract. Second party entered upon the performance of said work and claims that it has completed said contract (as amended by certain subsequent agreements) and is entitled to a certain balance of compensation therefor. First party disputes said claims and asserts certain counter-claims against second party arising out of alleged delays and improper and negligent performance of said work by second party.
“ (2.) The parties hereto-hereby agree to submit all of their disputes arising out of the making and performance of the aforesaid contract, and any subsequent agreements relating to said work to R. H. Thomson as arbitrator. It is agreed that, within fifteen (15) days after the signing of this agreement, *169 second party shall serve on first party and file with said R. H. Thomson a written statement of its claim as to the amount of its fill and the compensation it is entitled to for said fill as to each of the descriptions of property set out in the contract annexed hereto, or any modification thereof, together with the total balance it claims now to be due from said Charles H. Frye. Within fifteen (15) days thereafter first party shall serve on second party and file with said R. H. Thomson his claim as to the particulars in which second party has failed to fulfill the terms of the aforesaid written agreement and any subsequent agreements between the parties relating thereto, together with any claims he may have against second party for damages on account of delay in the performance of said work, failure to perform said work in accordance with the aforesaid agreements, negligence in the performance of said work, or other counterclaims or claims of damage arising out of the making and performance, or failure to perform, said contracts, or arising out of second party’s work on adjoining portions of said tide lands.
“(3.) After the expiration of the time herein allowed for the filing of statements of the parties, and at a time to be fixed by agreement of the parties, or by said arbitrator in the absence of such agreement, said arbitrator shall proceed to hear such evidence as shall be submitted by the parties hereto and take such steps as he may desire to investigate and determine the respective claims of the parties, and shall render his award in writing in accordance with the statutes of the state of Washington. The parties hereto shall each pay one-half of the charges of said arbitrator and shall be bound by his award as provided by the laws of the state of Washington.
“Dated at Seattle, Washington, this 7th day of February, 1925.
Charles H. Frye
“Attest:
Puget Sound Bridge & Dredging Company
“ Raymond J. Hoff,
“Secretary. (Seal.)
“By Roy E. Miller, Vice President.”

*170 The arbitrator took the statutory oath as such and thereafter proceeded to hear and determine the matters submitted to him, at which hearing the parties appeared in person and by counsel. At the conclusion of the hearing, the arbitrator made the following findings and conclusions:

“January 18th, 1926.
“Findings of Arbitrator
“In the matter of the cause of Puget Sound Bridge and Dredging Company vs. C. H. Frye, being claims for material and labor furnished in making fills upon block 226, block 228, block 242, block 251, block 277, and a tract in.block 243, all in Seattle Tide Lands, said fill having been made in the years 1923 and 1924.
“Having carefully studied the contract under which this work was done, and having heard and noted the testimony taken with reference to each claim upon the part of the plaintiff and each counter-claim on the part of the defendant, and having heard the arguments and carefully read the transcript of the stenographic notes of the arguments made by the attorneys on both sides, together with the briefs of attorneys covering certain points, and having given due consideration to all the facts bearing upon the case, the arbitrator finds:
“That upon its claim the plaintiff is entitled to recover for delivery of earth under the contract as shown between levels of the original ground and surface at the time of joint measurement by Fischer and Stuver, and for subsidence in the subsoil occasioned by the weight of the fill, a total of two hundred twenty-nine thousand three hundred eighty (229,380) cubic yards, which, at the contract price of twenty three and one-half cents (23%) per cubic yard, amounts to fifty-three thousand, nine hundred four dollars and thirty cents.
$53,904 30
“Also for undisputed incidentals in the sum of two thousand eighty-four dollars and forty-six cents........... 2,084 46
“Making a total sum of fifty-five thousand nine hundred eighty-eight dollars and seventy-six cents....... $55,988 76
*171

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mehmet Serkan Ketenci, V. Aino Kaarina Ketenci
Court of Appeals of Washington, 2024
Rimov v. Schultz
162 Wash. App. 274 (Court of Appeals of Washington, 2011)
Optimer International, Inc. v. RP Bellevue, LLC
151 Wash. App. 954 (Court of Appeals of Washington, 2009)
Optimer Intern, Inc. v. Rp Bellevue, LLC
214 P.3d 954 (Court of Appeals of Washington, 2009)
Godfrey v. Hartford Casualty Insurance
142 Wash. 2d 885 (Washington Supreme Court, 2001)
Godfrey v. Hartford Cas. Ins. Co.
16 P.3d 617 (Washington Supreme Court, 2001)
In Re the Parentage of Smith-Bartlett
976 P.2d 173 (Court of Appeals of Washington, 1999)
Davidson v. Hensen
135 Wash. 2d 112 (Washington Supreme Court, 1998)
Equity Group, Inc. v. Hidden
943 P.2d 1167 (Court of Appeals of Washington, 1997)
Boyd v. Davis
897 P.2d 1239 (Washington Supreme Court, 1995)
Department of Social & Health Services v. State Personnel Board
812 P.2d 500 (Court of Appeals of Washington, 1991)
Westmark Properties, Inc. v. McGuire
766 P.2d 1146 (Court of Appeals of Washington, 1989)
Keen v. IFG Leasing Co.
622 P.2d 861 (Court of Appeals of Washington, 1981)
Northern State Construction Co. v. Banchero
386 P.2d 625 (Washington Supreme Court, 1963)
Greyhound Corp. v. Division 1384 of Amalgamated Ass'n
271 P.2d 689 (Washington Supreme Court, 1954)
State v. McCollum
136 P.2d 165 (Washington Supreme Court, 1943)
Gord v. F. S. Harmon & Co.
61 P.2d 1294 (Washington Supreme Court, 1936)
Deppen v. E. A. Conkling Box Co.
19 Ohio N.P. (n.s.) 153 (Ohio Superior Court, Cincinnati, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
252 P. 546, 142 Wash. 166, 1927 Wash. LEXIS 1040, Counsel Stack Legal Research, https://law.counselstack.com/opinion/puget-sound-bridge-dredging-co-v-frye-wash-1927.