Publicker Chemical Corp., Liquid Specialists, Inc., Intervenor-Appellee v. Belcher Oil Company

792 F.2d 482, 1986 U.S. App. LEXIS 26211
CourtCourt of Appeals for the Fifth Circuit
DecidedJune 18, 1986
Docket85-3356
StatusPublished
Cited by11 cases

This text of 792 F.2d 482 (Publicker Chemical Corp., Liquid Specialists, Inc., Intervenor-Appellee v. Belcher Oil Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Publicker Chemical Corp., Liquid Specialists, Inc., Intervenor-Appellee v. Belcher Oil Company, 792 F.2d 482, 1986 U.S. App. LEXIS 26211 (5th Cir. 1986).

Opinion

OPINION

WISDOM, Circuit Judge:

The Louisiana law of obligations governs this diversity action for breach of contract. Belcher Oil Company seized upon a dispute over $5,000 as a means of escaping an undesirable $5 million contract with Publicker Chemical Corporation. The district court entered judgment against Belcher. We affirm.

I.

Publicker owns petroleum storage facilities in Gretna, Louisiana. In January 1982 Publicker agreed to store Belcher’s petroleum products at the Gretna facility for a period of seven years. As required by the contract, Publicker renovated its storage tanks at a cost of more than $1.2 million. Each month Belcher paid Publicker a “base fee” of $65,617.89 in addition to a charge for “blending” the petroleum products averaging $2,611 per month. Liquid Specialists, Inc. earned a commission for bringing the parties together and conducting some of the negotiations.

Belcher payed Publicker 36 cents for each barrel of petroleum products it stored at Gretna. When the contract was signed, petroleum “terminalling” charges averaged between 50 and 75 cents per barrel. By early 1984, however, demand for petroleum storage facilities had collapsed. As a result, storage charges dropped to less than 20 cents per barrel. Belcher stood to gain as much as $2.5 million if it could escape its long-term contract with Publicker.

In July 1983 Belcher asked Publicker to run “agitators” installed in the storage tanks whenever the tanks were filled above the six-foot level. The contract does not mention agitation, although Belcher told Publicker during the contract negotiations that its products might require agitation as often as ten times each month. Continuous agitation is not a standard industry practice.

Continuous operation of the agitators increased Publicker’s use of electricity. Publicker attempted to recoup the additional cost by offsetting it against a fuel cost adjustment credit Publicker owed to Belch-er. Publicker deducted $4,845.30 for agitation costs from July through December 1983.

In a letter dated March 14, 1984, Belcher advised Publicker that it considered Publicker in default of paragraph 4.06 of the contract, set out in full in the margin. 1 Publicker’s senior vice president requested a meeting with Belcher representatives to discuss agitation costs in a letter dated March 22. Belcher officials agreed to meet on April 19. On April 18, Belcher officials informed Publicker that they considered the contract terminated under the provisions of Article XIII of the contract. 2

*485 Belcher’s actions refute any intention to resolve the dispute over agitation costs. In March of 1984, before meeting with Publicker officials, Belcher contacted one of Publicker’s competitors to discuss a new storage contract. At the same time Belch-er ordered its manager to sell off reserves stored at the Gretna facility.

By May 1 Belcher had withdrawn all of its oil from Publicker’s tanks. Publicker’s efforts to find other customers have not been successful.

Publicker sued Belcher for breach of contract. On cross-motions for summary judgment, the district court held that Belcher breached the contract. After hearing evidence on the amount of damages, the court entered judgment for $3,095,589.27, including $244,523 awarded to intervenor Liquid Specialists, Inc. as the balance of its commission. The defendant appeals.

II.

Publicker contends that it did not breach the contract. In the alternative, if offsetting agitation costs did breach the contract, Publicker contends that Belcher was not entitled to terminate the contract. We reject the first contention but accept the second.

A.

Publicker contends that it did not breach the contract because: 1) the doctrine of compensation justifies deduction of the agitation expenses; 2) the clause forbidding offsets applies only to Belcher; and 3) the offset clause does not apply to the fuel cost adjustment.

The civil law doctrine of compensation does not justify the offset. That doctrine, as stated in the Civil Code, provides: “When two persons are indebted to each other, there takes place between them a compensation that extinguishes both the debts”. 3 The doctrine applies only to uncontested debts, however. “A contested debt ... is not a liquidated one; and cannot be set off, unless he who claims to set it off, has the proof in his hands, and be ready to prove it promptly and summarily 4 Belcher contested its liability for the increased agitation charges in letters dated November 23, 1983 and March 14, 1984. Although the district court ultimately rejected Belcher’s arguments that the agitation charges were covered by the “base fee” it paid to Publicker, those arguments were sufficient to create a genuine contest. 5

Contrary to Publicker’s assertion, Article IV is not limited to amounts owed to Publicker by Belcher. Paragraph 4.05 provides in part:

To the extent that PUBLICKER’S actual fuel costs are above or below this level, BELCHER will pay for or benefit from such cost differentials. Fuel cost adjustments will be made on a Quarterly basis.

Publicker, as well as Belcher, was bound by the offset clause. The fuel cost adjustment is discussed in a letter dated May 6, 1983. 6 Because the letter refers to the same subject matter as paragraph 4.05, we regard the letter as an amendment to that *486 paragraph and not as an entirely new contractual provision outside Article IV.

We therefore conclude that Publicker breached its obligation under paragraph 4.05 of the contract by offsetting agitation costs against the fuel adjustment credit.

B.

Not every breach of a contract is grounds for dissolution of the contract under Louisiana law. Louisiana courts have discretion to determine “whether the performance not rendered by [one party] was the cause 7 of [the other party’s] obligation, in which case the dissolution [of the contract] must be granted, or whether the failure in the [one party’s] performance is not so grave as to have deterred [the other party] from entering the contract, had he foreseen it, in which case he will be granted damages or a proportional reduction of his own performance”. 8 Accordingly we have held that “breach of an ancillary obligation will neither of itself excuse the other party from performing nor give sufficient justification for legal dissolution of the contract”. 9

The purpose of the contract between Publicker and Belcher was the storage of petroleum products. Publicker’s primary obligation under the contract was to provide adequate storage tanks for Belcher’s products. Belcher’s primary obligation was to pay Publicker the fees and charges specified in the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
792 F.2d 482, 1986 U.S. App. LEXIS 26211, Counsel Stack Legal Research, https://law.counselstack.com/opinion/publicker-chemical-corp-liquid-specialists-inc-intervenor-appellee-v-ca5-1986.