Louisiana Nevada Transit Co. v. Marathon Oil Co.

770 F. Supp. 325, 1991 WL 155684
CourtDistrict Court, W.D. Louisiana
DecidedJuly 17, 1991
DocketCiv. A. 89-2824
StatusPublished
Cited by5 cases

This text of 770 F. Supp. 325 (Louisiana Nevada Transit Co. v. Marathon Oil Co.) is published on Counsel Stack Legal Research, covering District Court, W.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Louisiana Nevada Transit Co. v. Marathon Oil Co., 770 F. Supp. 325, 1991 WL 155684 (W.D. La. 1991).

Opinion

MEMORANDUM RULING

STAGG, District Judge.

The parties have filed cross motions for summary judgment. Louisiana Nevada Transit (“LNT”) seeks to permanently enjoin Marathon Oil Company (“Marathon”) from terminating the Gas Sales Agreement. Marathon’s counterclaim asks for a declaratory judgment that the Gas Sales Agreement terminated on January 4, 1990, by exercise of an option to terminate. Marathon’s motion for summary judgment does not address its other asserted grounds for termination of the contract, nor does it address damages for wrongfully obtained preliminary injunctive relief. For the reasons given below, LNT’s motion for summary judgment is DENIED, and Marathon’s motion for partial summary judgment is GRANTED.

I. THE FACTS

On July 1, 1940, oil and gas producers in the Cotton Valley Field, located in northern Louisiana and southern Arkansas, entered into the Cotton Valley Unitization and Pressure Maintenance Agreement. This Agreement created a large, unitized area for production of gas and constituent liquid hydrocarbons and established the Cotton Valley Operators Committee (“CVOC”) to act on behalf of the owners of oil and gas leases in the unitized area.

Prior to unitization, LNT, which operates an interstate gas transmission system, purchased gas from the Cotton Valley Field pursuant to a 1938 contract with Oliphant Oil Corporation. The Gas Sales Agreement, dated October 24, 1940, between CVOC and LNT, cancelled and superseded the Oliphant Contract. As subsequently amended, this 1940 Contract (the “Contract”) is the subject of this lawsuit.

On April 9, 1976, CVOC and Marathon signed an operating contract which made Marathon the unit operator of the CVOC properties. This agreement gave Marathon the right to act as agent for the lease owners.

*327 The final amendment to the Contract on the issues of quantity and termination are as follows:

Article 1: Buyer agrees to buy from Seller the first 10 million cubic feet of gas per calendar month for its gas requirements for so long a period as buyer shall have a market for such amount. This provision shall not, however, be construed as a minimum take provision, that is to say, the Buyer shall be obligated to pay for only such as it actually receives, subject, however, to the provisions of the paragraph immediately following.
Should Buyer fail, neglect, or refuse to take and pay for, or pay for if not taken, at least 30 million cubic feet of gas from seller during any consecutive 90-day period during the life of this contract, then the Seller may, at its option, elect to terminate this contract by giving to Buyer 60 days’ notice, in writing, of its intention so to do.

From March through September of 1989, there were twenty-two consecutive 90-day periods in which LNT failed to take and pay for the minimum requirements under the contract. In fact, there were numerous consecutive days when LNT took no Cotton Valley gas at all. More specifically, for 90-day periods ending on June 5-17, 1989 (“the June period”) and September 14-22, 1989 (“the September period”), LNT failed to take and pay for, or pay for if not taken, at least 30 MMCF of gas. By letter dated November 3, 1989, Marathon exercised CVOC’s option to terminate the Contract, stating that such termination would become effective on January 4, 1991.

On November 14, 1990, LNT attempted to pay for the gas not taken during both the June and September periods by including such amount with the payment for gas taken during September. Although Marathon attempted to stop the check before it went through its bank, it was unable to do so and, instead, sent LNT a refund for the amount in excess of that actually delivered.

On December 8, 1989, LNT commenced this action seeking a permanent injunction enjoining Marathon from terminating the Contract. On December 11, 1989, LNT moved the court for a temporary restraining order and a preliminary injunction to prevent Marathon from terminating deliveries under the Contract during the pend-ency of this action. Despite being given notice and an opportunity for a hearing, Marathon elected not to oppose that motion. On December 18, 1989, this court signed an order prohibiting Marathon from terminating deliveries under the Contract, until the disposition of LNT’s motion for permanent injunction. Along with its answer to the complaint, Marathon filed a counterclaim against LNT, seeking a declaratory judgment that the Contract terminated and seeking damages for wrongful issuance of the injunction order of December 18, 1989.

II. STANDARD OF REVIEW

Federal Rule of Civil Procedure 56(c) provides that summary judgment is appropriate where the “pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law.” Both parties agree that the underlying facts are undisputed. The dispute is essentially whether or not an option ever arose for CVOC to terminate the Contract and, if so, whether Marathon properly and timely exercised this option. The court need only interpret the disputed provisions of the Contract and to determine the consequences of the factual circumstances as they relate to the contract thus interpreted. Summary judgment is, therefore, appropriate.

III. MARATHON’S MOTION FOR PARTIAL SUMMARY JUDGMENT

Although jurisdiction in this case is based on diversity, federal law controls whether a court may properly render a declaratory judgment. National Railroad Passenger Corporation v. Consolidated Rail Corporation, 670 F.Supp. 424, 429 n. 7 (D.D.C.1987), vacated on other grounds, 892 F.2d 1066 (D.C.Cir.1990). Neverthe *328 less, Louisiana law will apply to the underlying substantive issues.

Under the Declaratory Judgment Act, 28 U.S.C. § 2201, declaratory relief is appropriate where there is a substantial controversy of sufficient immediacy and reality between parties having adverse legal interests. Maryland Casualty Company v. Pacific Coal & Oil Company, 312 U.S. 270, 273, 61 S.Ct. 510, 512, 85 L.Ed. 826 (1941). The court finds that a substantial controversy exists between these parties which is both immediate and real.

Marathon contends that, based upon the plain language of Article 1 of the Contract, an option to terminate the Contract arose when LNT failed to take and pay for, or pay for if not taken, the minimum requirement under the Contract. Both parties agree that Article 1 creates no obligation on the part of LNT other than to pay for gas taken during the 90-day period.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jabr v. Rapides Parish School Board Ex Rel. Metoyer
171 F. Supp. 2d 653 (W.D. Louisiana, 2001)
AUTOMOBILE INS. CO. OF HARTFORD, CONN. v. Curran
994 F. Supp. 324 (E.D. Pennsylvania, 1998)
Providence Journal Co. v. Travelers Indemnity Co.
938 F. Supp. 1066 (D. Rhode Island, 1996)
Britamco Underwriters, Inc. v. C.J.H., Inc.
845 F. Supp. 1090 (E.D. Pennsylvania, 1994)
La-Nevada Transit Company v. Marathon Oil Company
985 F.2d 797 (Fifth Circuit, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
770 F. Supp. 325, 1991 WL 155684, Counsel Stack Legal Research, https://law.counselstack.com/opinion/louisiana-nevada-transit-co-v-marathon-oil-co-lawd-1991.