Public Warehousing Company, K.S.C.

Armed Services Board of Contract Appeals·Decided November 8, 2016·No. ASBCA No. 58088·Published

Opinion

I ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Public Warehousing Company, K.S.C. ) ASBCA No. 58088 ) Under Contract No. SPM300-05-D-3128 )

APPEARANCES FOR THE APPELLANT: Michael R. Charness, Esq. Bryan T. Bunting, Esq. Elizabeth Krabill Mcintyre, Esq. Vinson & Elkins, L.L.P Washington, DC

APPEARANCES FOR THE GOVERNMENT: Daniel K. Poling, Esq. DLA Chief Trial Attorney John F. Basiak, Jr., Esq. Keith J. Feigenbaum, Esq. Kari L. Scheck, Esq. DLA Troop Support Philadelphia, PA

OPINION BY ADMINISTRATIVE JUDGE O'CONNELL ON THE GOVERNMENT'S MOTION FOR LEAVE TO AMEND

The government has filed a motion seeking leave to amend its answer to plead affirmative defenses of fraud in the inducement, first material breach, sovereign acts doctrine, political question doctrine, assumption of risk, and failure to mitigate. We grant the motion.

STATEMENT OF FACTS FOR PURPOSES OF THE MOTION

I. Public Warehousing Company, K.S.C. (PWC) performed the subsistence prime vendor contract referenced above, which required it to deliver food, beverages and related items to military units and other authorized customers in Iraq (comp!.~ 6; gov't SOF ~ 3).

2. PWC transported the food and other items on trucks that traveled in convoys. It contends that, starting in December 2007, U.S. military personnel required it to provide extra semi-truck tractors ("bobtails") on the convoys; the bobtails were used to recover appellant's assets as well as the assets of other contractors. (Comp!.~~ 12, 16-17) Appellant contends that it had no choice but to comply because the government would not have allowed its trucks in the convoy (id. ~~ 17-18). 3. On 24 October 2011, PWC submitted a certified claim to the contracting officer seeking about $7.5 million.

4. In its proposed fraud in the inducement defense, the government contends that PWC obtained the contract by submitting artificially low prices in its proposal that rose significantly after award (proposed amended answer at 12-13 ). The government seeks to add four first material breach defenses, namely: systemic overcharging by not purchasing from requested/preferred vendors; manipulation and inflation of delivered price through the use of the company Interchange Port Services; manipulation and inflation of delivered price by concealing discounts and allowances; and failure to pass on rebates and discounts (id. at 13-18). The government also seeks to add affirmative defenses based on the sovereign acts and political question doctrines, as well as assumption of risk, and failure to mitigate (id. at 18-20).

5. In November 2009, a grand jury in the Northern District of Georgia issued an indictment against PWC for various fraud offenses arising from the contract at issue. That case is still pending. The government's proposed fraud in the inducement and first material breach affirmative defenses appear to be based on the allegations in the indictment (gov't reply, ex. 1). For example, count one of the indictment alleges a scheme to obtain the contract by submitting artificially low prices in PWC's proposal with the recognition that the prices were not realistic (id. at 12-20), which is similar to the government's proposed first affirmative defense in this appeal.

6. Appellant filed this appeal on 20 April 2012. The Defense Logistics Agency (DLA) filed its answer on 13 July 2012. DLA was aware of the indictment at the time it filed its answer (gov't reply at 9).

DECISION

Under Board Rule 6( d), we "may permit either party to amend its pleading upon conditions fair to both parties." In exercising our discretion under this rule, the Board has looked to Rule 15 of the Federal Rules of Civil Procedure. FED. R. CIV. P. 15(a)(2) provides that "[t]he court should freely grant leave when justice so requires."

In Foman v. Davis, 371 U.S. 178, 182 (1962), the Supreme Court held that:

In the absence of any apparent or declared reason - such as undue delay, bad faith or dilatory motive on the part of the movant, repeated failure to cure deficiencies by amendments previously allowed, undue prejudice to the opposing party by virtue of allowance of the amendment, futility of amendment, etc. - the leave sought should, as the rules require, be "freely given."

2 In this motion, the primary questions are whether there has been undue delay on the part of the government and whether appellant has been prejudiced. Because appellant filed this appeal more than two years after the indictment, the government could have raised these affirmative defenses in its July 2012 answer. Thus, there has been a delay of over four years. By way of excuse, the government offers two reasons. First, there have been several other appeals involving DLA and PWC that have required a great deal of work by DLA attorneys in recent years (gov't mot. at 9-11). Second, it contends that until the Court of Appeals for the Federal Circuit issued its decision in Laguna Construction Co. v. Carter, 828 F.3d 1364 (Fed. Cir. 2016), the law with respect to first material breach was unsettled and that it filed its motion to amend roughly six weeks after the Federal Circuit issued that decision. DLA contends that it was not in a position to file the affirmative defenses until either Laguna or the criminal case had been resolved. (Gov't reply at 9)

While we believe that DLA could have acted more quickly to seek leave to plead these affirmative defenses, an examination of the entire record of litigation between DLA and PWC on this contract leads us to conclude that PWC has not been prejudiced by any delay. The record demonstrates that the government's interest in preventing appeals at the Board from interfering with the criminal case and, consequently, using that as a basis to stay or dismiss appeals on the same contract, has long been known, as follows:

• In Public Warehousing Co., K.S.C., ASBCA No. 56116, 08-1BCAii33,787, we granted a government motion to stay to allow the Department of Justice to complete the criminal investigation. In that decision we found that "[i]t is clear to us ... that PWC's primary purpose in wishing to proceed with the appeal is to use the Board's decision to influence the direction of the on-going investigations, and to help its position in potential settlement discussions." Id. at 167,229.

• In The Public Warehousing Co., ASBCA No. 56022, 13 BCA ii 35,201, the government moved to dismiss or to place limitations on depositions after PWC was found to be live streaming the contracting officer's deposition to PWC's criminal counsel, who apparently were sending questions for appellate counsel to ask the contracting officer. The Board denied the motion to dismiss but placed limits on the depositions going forward.

• In Public Warehousing Co., K.S.C., ASBCA No. 58078, 14-1BCAii35,574, we dismissed without prejudice an appeal by PWC after the United States Attorney for the Northern District of Georgia requested that DLA seek dismissal due to his concern that proceeding with that appeal would compromise and interfere with the ongoing criminal case.

• Finally, in PWC's appeal docketed as ASBCA No. 59020, the government amended its answer as a matter of right on 22 July 2016 to assert affirmative defenses of fraud in the inducement and first material breach. 3 I I In Laguna Construction Co., ASBCA No.

Free access — add to your briefcase to read the full text and ask questions with AI

Public Warehousing Company, K.S.C., (asbca 2016).

Public Warehousing Company, K.S.C. (Public Warehousing Company, K.S.C.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Foman v. Davis
371 U.S. 178 (Supreme Court, 1962)
Laguna Construction Company v. Defense
828 F.3d 1364 (Federal Circuit, 2016)