Public Utilities Commission of v. FERC

CourtCourt of Appeals for the Seventh Circuit
DecidedAugust 6, 2009
Docket08-2239
StatusPublished

This text of Public Utilities Commission of v. FERC (Public Utilities Commission of v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Public Utilities Commission of v. FERC, (7th Cir. 2009).

Opinion

In the

United States Court of Appeals For the Seventh Circuit

Nos. 08-1306, 08-1780, 08-2071, 08-2124, 08-2239

ILLINOIS C OMMERCE C OMMISSION, et al., Petitioners, v.

F EDERAL E NERGY R EGULATORY C OMMISSION, et al.,

Respondents.

Petitions to Review Orders of the Federal Energy Regulatory Commission.

A RGUED A PRIL 13, 2009—D ECIDED A UGUST 6, 2009

Before C UDAHY, P OSNER, and T INDER, Circuit Judges. P OSNER, Circuit Judge. We have before us challenges to a decision by the Federal Energy Regulatory Commission concerning the reasonableness of rates for the transmission of electricity over facilities owned by utilities that belong to a Regional Transmission Organization (that is, a power pool) called PJM Interconnection. PJM Interconnection, L.L.C., 119 F.E.R.C. ¶ 61,063 (2007), rehearing denied, 122 F.E.R.C. ¶ 61,082 (2008); see 16 U.S.C. § 824e; Atlantic City Electric Co. v. FERC, 295 F.3d 1, 10 (D.C. Cir. 2002). (“PJM” 2 Nos. 08-1306, 08-1780, 08-2071, 08-2124, 08-2239

stands for “Pennsylvania-New Jersey-Maryland,” but the full name is not used any more.) “RTOs are voluntary associations in which each of the owners of transmission lines that comprise an integrated regional grid cedes to the RTO complete operational control over its transmis- sion lines.” Richard J. Pierce, Jr., “Regional Transmission Organizations: Federal Limitations Needed for Tort Liability,” 23 Energy L.J. 63, 64 (2002); see also Regional Transmission Organizations, 65 Fed. Reg. 810-01, 2000 WL 4557 (FERC Jan. 6, 2000); Morgan Stanley Capital Group Inc. v. Public Utility District No. 1, 128 S. Ct. 2733, 2741 (2008). PJM’s region stretches east and south from the Chicago area, primarily to western Michigan and eastern Indiana, Ohio, Pennsylvania, New Jersey, Delaware, Maryland, the District of Columbia, and Virginia. PJM Interconnection, L.L.C., supra, p. 3, see FPL Energy Marcus Hook, L.P. v. FERC, 430 F.3d 441, 442-43 (D.C. Cir. 2005). The region is home to more than 50 million consumers of electricity. Two issues are presented. The first, raised by American Electric Power Service Corporation and the Public Utilities Commission of Ohio (participation by state commissions in rate proceedings before FERC is au- thorized by 16 U.S.C. § 825g(a); see also § 825l(a)), involves the pricing of electricity transmitted from the Midwest to the East through Ohio. PJM wants that transmission to be priced on the basis of the cost to American Electric of transmitting one more unit of electricity, that is, the marginal cost; and FERC agrees. Such a price excludes the cost that the company incurred when it built the transmission facilities. That cost—which American Nos. 08-1306, 08-1780, 08-2071, 08-2124, 08-2239 3

Electric wants to be permitted to reflect in its rates—is what economists call a “sunk” cost, that is, a cost that has already been incurred. So while its financial burden can be shifted (from American Electric to the eastern utili- ties), the cost itself cannot be shifted, and therefore shifting the financial burden created by the cost from one set of shoulders to another will have no direct effect on service or investment. Had FERC decided that American Electric would not be permitted to charge a price that covered the cost of building a new transmission facility or upgrading an existing one, its decision would have affected the alloca- tion of resources and not just of money. It would have deterred the building of new facilities that benefited customers outside American Electric’s service area, be- cause building them would become an unprofitable venture. FERC emphasizes, however, that the company’s existing facilities, which are all that are involved in this case, were built before 2001 when PJM became a Regional Transmission Organization, and were intended to serve American Electric’s customers only. So even if the facilities had not been fully paid for, there would be no economic basis for shifting any part of their costs to other members, because American Electric did not expect when it built the facilities that any part of their cost would be defrayed by anyone besides its customers. PJM and FERC have made clear that American Electric will be allowed to charge a price that covers its costs for transmission to other utilities over new or upgraded facilities. 4 Nos. 08-1306, 08-1780, 08-2071, 08-2124, 08-2239

American Electric points out that some of its existing facilities are not fully depreciated. But it can continue to depreciate them over their remaining useful life in order to create an accounting reserve or obtain a tax benefit. And when it builds a new facility it will be allowed, as we said, to recover the full costs of that facility in its prices. The company may be trying to extract a monopoly price for the use of its facilities. It stands between western sellers of electricity and their eastern customers and would like to extract a toll for giving the former passage to the latter, a toll that has no relation to its costs of render- ing that service. It charged its customers for the costs of building its existing facilities and recovered those costs fully and now wants to recover them all over again from another group of consumers. And it’s not as if American Electric were being required to provide trans- mission to the east at zero price. It is permitted to charge for the service—just not to include in the charge its sunk costs. The second issue relates to the financing of new trans- mission facilities. Here the Ohio commission joins its Illinois counterpart, representing the interests of the midwestern utilities in PJM’s region, in objecting to PJM’s proposed method, approved by FERC, for pricing new transmission facilities that have a capacity of 500 kilovolts or more. Heretofore all new facilities in PJM’s region have been financed by contributions from the region’s electrical utilities calculated on the basis of the benefits that each utility receives from the facilities. This will continue to be the rule for facilities with capacities of Nos. 08-1306, 08-1780, 08-2071, 08-2124, 08-2239 5

less than 500 kV. But for the higher-voltage facilities FERC has decided that all the utilities in PJM’s region should contribute pro rata; that is, their rates should be raised by a uniform amount sufficient to defray the facili- ties’ costs. FERC’s stated reasons are that some of PJM’s members entered into similar pro rata sharing agreements with each other more than forty years ago and would like to follow that precedent, that figuring out who benefits from a new transmission facility and by how much is very difficult and so generates litigation, and that every- one benefits from high-capacity transmission facilities because they increase the reliability of the entire net- work. Despite the stakes in the dispute—the new policy might, for example, force Commonwealth Edison to contribute hundreds of millions of dollars to an above-500 kV eastern project called “Project Mountaineer,” when it would not have had to pay a dime under the benefits- based system applicable to lower-voltage transmission facilities—no data are referred to in FERC’s two opinions (the original opinion and the opinion on rehearing). No lawsuits are mentioned. No specifics concerning difficul- ties in assessing benefits are offered. No particulars are presented concerning the contribution that very high- voltage facilities are likely to make to the reliability of PJM’s network.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alcoa Inc. v. Federal Energy Regulatory Commission
564 F.3d 1342 (D.C. Circuit, 2009)
Boston Edison Co. v. FERC
441 F.3d 10 (First Circuit, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
Public Utilities Commission of v. FERC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/public-utilities-commission-of-v-ferc-ca7-2009.