Public Utilities Commission of Conn. v. Federal Power Commission

205 F.2d 116, 1953 U.S. App. LEXIS 2563, 1953 WL 79299
CourtCourt of Appeals for the Third Circuit
DecidedJune 15, 1953
Docket10898
StatusPublished
Cited by8 cases

This text of 205 F.2d 116 (Public Utilities Commission of Conn. v. Federal Power Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Public Utilities Commission of Conn. v. Federal Power Commission, 205 F.2d 116, 1953 U.S. App. LEXIS 2563, 1953 WL 79299 (3d Cir. 1953).

Opinion

STALEY, Circuit Judge.

Asserting that it is aggrieved, the Public Utilities Commission of the State of Connecticut is here seeking review, under section 19(b) of the Natural Gas Act, 1 of an order of the Federal Power Commission. The case is a manifestation of the growing pains being felt upon the introduction of natural gas into the New England area.

On September 9, 1949, Transcontinental Pipe Line Corporation applied to the respondent Commission in Docket No. G-1277 for a certificate of public convenience and necessity authorizing it to construct and operate 35.5 miles of 24-inch line from a point in northern New Jersey to a point near Greenwich, Connecticut. Through these facilities, Transcontinental proposed to sell 100,000 Mcf of natural gas per day to Northeastern Gas Transmission Company.

In Docket No. G-1267, Northeastern applied for a certificate authorizing, among other things, construction and operation of 144 miles of 20-inch line from a point near Pittsfield, Massachusetts, extending in an easterly direction to a point near Boston and 100 miles of 16-inch line from a point near Greenwich to a point near Springfield, Massachusetts.

In Docket No. G-1248, Tennessee Gas Transmission Company, parent of Northeastern, requested authority, among other things, to increase the capacity of its pipeline system, to extend its line from its then terminal near Buffalo to a point of connection with Northeastern’s proposed line near Pittsfield, Massachusetts, and to sell to Northeastern 156,000 Mcf of natural gas per day. 2

The matters described above were set down for a consolidated hearing, after which the Commission issued its Opinion No. 202 and order of November 8, 1950. So far as relevant here, that order granted a certificate authorizing Transcontinental’s construction and operation of the 35.5 miles of line from northern New Jersey to a point near Greenwich, Connecticut, upon condition that it sell and deliver to Northeastern not more than 64,000 Mcf of natural gas *118 per day. That order also authorized Northeastern to construct its proposed lines in order to serve the various New England states, Connecticut being one of them. Tennessee was certificated to construct its proposed extension from Buffalo to Pittsfield, Massachusetts, and to supply 156,000 Mcf per day to Northeastern to enable the latter to supply its extended facilities. Nobody here finds fault with any of the phases of this order.

Tennessee completed its extension and made its first delivery to Northeastern in September of 1951. After some difficulties, Northeastern completed its new lines and delivered natural gas into the pipes of the Connecticut Power Company, Torrington Division, in August of 1952 — about one year later than anticipated. Following its authorization, Transcontinental contracted with Northeastern on March 15, 1951, to sell the latter 64,000 Mcf per day, deliveries to begin by September 1, 1951. The parties’ hopes, however, did not materialize. Transcontinental encountered financing and procurement trouble. In June of 1951, it discovered that the cost of its proposed lateral to New England would exceed the original estimate by about six and one-half million dollars. Its president said that, for this reason, it was unable to raise the funds to build the proposed extension. Moreover, Transcontinental did not have pipe available and was faced with litigation in attempting to acquire a site for a compressor station at Rye, New York. This situation was explained to Northeastern, which company stated that it would be unable to accept deliveries of gas until about September of 1952. Transcontinental then advised Northeastern that it had terminated the contract of March 15, 1951, but proffered new contractual arrangements looking to deliveries in September of 1953. Northeastern then advised Transcontinental that it considered that Transcontinental had breached the contract, and it declined to enter into further agreements with Transcontinental.

Being apprised of these facts, the Commission on December 7, 1951, reopened Docket No. G-1277 to determine what disposition should be made of the unused 64,000 Mcf of Transcontinental’s authorized capacity. On February 19, 1952, Transcontinental filed a petition requesting modification of the order of November 8, 1950, by rescission of the authority granted it to construct the 35.5 miles of pipe line to Greenwich and to sell 64,000 Mcf to Northeastern. The latter answered, stating that it had no objection to the granting of the petition.

The Commission consolidated proceedings on Transcontinental’s petition with those on reopened Docket No. G-1277. Petitioner was allowed to intervene after the date for timely intervention.

Hearings were held and thereafter the Commission issued its order of June 19, 1952. ■ That order is the one to be reviewed here. It amended the order of November 8, 1950, by revoking Transcontinental’s authority to construct the lateral to Greenwich and to sell 64,000 Mcf to Northeastern. Simultaneously, the Commission granted a certificate to Tennessee, pursuant to its petition in Docket No. G-1573, authorizing sale by it to Northeastern of 64,000 Mcf per day, in addition to the 156,000 authorized by the order of November 8, 1950. Although the order under attack allowed Transcontinental to drop out of the picture, the 64,000 Mcf which it was to supply was ordered to be supplied by Tennessee. Consequently, the ch:. enged order did not affect the quantity of natural gas to be furnished to Northeastern and, through the latter’s facilities, to Connecticut. This preliminary observation serves to highlight petitioner’s principal allegation of aggrievement. Petitioner says that, by the order of November 8, 1950, Connecticut was to get a certain volume of gas through two sources of supply; by the order of June 19, 1952, it gets the same volume of gas but through only one source of supply; therefore, instead of receiving natural gas from the reserves of both Transcontinental and Tennessee, its supply is dependent on the reserves of Tennessee alone. Furthermore, should a break occur in Tennessee’s line, Connecticut will be without gas, whereas, if it were served by two lines, as-originally ordered, the deficit caused by a break in one *119 line could be picked up by the other until the break was repaired.

We are met at the outset by a robust attack upon petitioner’s standing to prosecute this review. Both respondents argue with much force that petitioner is not a party aggrieved within section 19(b) of the Natural Gas Act. 3 We think there are other issues dispositive of this case, and, therefore, we will pass over this “complicated specialty of federal jurisdiction.” U. S. ex rel. Chapman v. Federal Power Commission, 1953, 345 U.S. 153, 156, 73 S.Ct. 609, 612. We will assume for the purposes of this case, without deciding, that petitioner is a party aggrieved and, thus, has standing to challenge this order.

Petitioner’s main contention here is that the order under review is fatally defective for its failure to contain the necessary findings.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
205 F.2d 116, 1953 U.S. App. LEXIS 2563, 1953 WL 79299, Counsel Stack Legal Research, https://law.counselstack.com/opinion/public-utilities-commission-of-conn-v-federal-power-commission-ca3-1953.