Michigan Consol. Gas Co. v. Federal Power Commission (Two Cases)

203 F.2d 895, 99 P.U.R. (N.S.) 263, 1953 U.S. App. LEXIS 3444
CourtCourt of Appeals for the Third Circuit
DecidedApril 30, 1953
Docket10589, 10783
StatusPublished
Cited by14 cases

This text of 203 F.2d 895 (Michigan Consol. Gas Co. v. Federal Power Commission (Two Cases)) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Michigan Consol. Gas Co. v. Federal Power Commission (Two Cases), 203 F.2d 895, 99 P.U.R. (N.S.) 263, 1953 U.S. App. LEXIS 3444 (3d Cir. 1953).

Opinion

MARIS, Circuit Judge.

Michigan Consolidated Gas Company in these consolidated petitions for review asks this court to set aside two orders issued by the Federal Power Commission in consolidated proceedings involving Panhandle Eastern Pipe Line Company in which proceedings Michigan- Consolidated was permitted by the Commission to intervene. The orders under attack prescribed Panhandle’s obligation to deliver natural gas to Michigan Consolidated at Detroit and limited its obligation to 125,000 Mcf per day, the amount then currently being delivered, although Michigan Consolidated had claimed the right to receive an additional 75,000 Mcf per day of natural gas from the additional capacity which Panhandle had acquired with the approval of the Commission. -

Panhandle Eastern Pipe Line Company produces and purchases natural gas in the Panhandle and Hugoton fields of Texas, Oklahoma and Kansas. It also owns and operates "a pipeline system extending through Oklahoma, Kansas, Missouri, Illinois, Indiana and Ohio to northern termini in Michigan and is engaged in the transportation and sale of natural gas in interstate commerce to distributing utilities, located along its pipeline system and directly to industries and others for their own use. Panhandle is a natural gas company within the meaning of the-Natural Gas Act, 15 U.S. C.A. § 717 et seq.

In January, 1950, Panhandle filed an application with the Commission for a certificate of public convenience and necessity under Section 7(c) of the Act authorizing the construction and operation of additional pipeline and compressor facilities whereby it could receive, transport and deliver 250.000 Mcf per day of additional natural gas to be obtained from Trunkline Gas Supply Company upon completion of the pipeline of the latter extending from the gulf coast of Texas to a point of connection with the Panhandle system near Tuscola, Illinois. The application also requested authority for Panhandle to construct and operate certain appurtenant facilities to permit Panhandle as a part of its expansion program to deliver -and sell an additional 50.000 Mcf per day of gas from its own supplies.

*897 Following hearings the Commission on May 4, 1950, issued a certificate of public convenience and necessity to Panhandle for the principal pipeline facilities requested. Further hearings were scheduled with respect to other issues involved in the proceedings, including the proper form of tariff, the rate level to be applicable to Panhandle after the introduction of Trunkline gas, and the question of a fair, reasonable and equitable distribution among present and prospective customers of the volume of natural gas which would be available upon completion of the authorized Trunkline and Panhandle facilities.

The Commission, following further hearings, issued its Opinion No. 214 on June 13, 1951 finding that the rate schedules contained in Panhandle’s then existing contracts with its utility customers were not uniform with respect to service and volumetric obligations, and prescribing a tariff containing new rate schedules and related forms of service agreements to' become applicable to the operations of Panhandle after the introduction of the Trunkline gas into its system. The rates thus prescribed were “rates which are sometimes referred to as ‘rolled-in’, whereby the cost of Trunkline gas is included along with Panhandle’s other costs; in other words, for all customers these rates should be based upon the total cost of Panhandle for rendering natural gas service.” On August 17, 1951 Panhandle filed with the Commission a tariff in the form prescribed by Opinion No. 214 and the accompanying order. Upon applications for rehearing the Commission after further hearings issued its Opinion No. 214-A and accompanying order on August 23, 1951, directing that certain minor modifications and revisions be made in the form of the tariff. Thereafter Panhandle amended its proposed tariff to comply with Opinion No. 214-A, except as to one matter not presently pertinent.

The Commission’s Opinion No. 214 provided that during the following period of thirty days Panhandle and its customers would be given the opportunity to negotiate contracts under the new form of tariff and to file them as exhibits with the Commission; that customers who did not negotiate such contracts were to file as exhibits with the Commission within ten days thereafter sworn statements of the amounts of natural gas which they would be willing to purchase from Panhandle under the form of service agreement contained in the tariff, and that thereafter the Commission .would consider and determine the remaining issues in the proceedings including the issue of the equitable distribution of gas among Panhandle’s customers. Accordingly during the course of the hearings which were resumed July 23, 1951 Panhandle filed as exhibits newly executed service agreements which it had entered into with all but eight of the resale interstate customers which it served. The latter customers filed as exhibits sworn statements specifying the volumes of gas desired which statements were modified and supplemented at the hearing by testimony and statements of counsel. Among the latter customers was Michigan Consolidated, which filed a statement specifying 200,000 Mcf per day at Detroit and 2,000 Mcf per day at Ann Arbor as its desired volume.

On August 31, 1951 the Commission issued its Opinion No. 218, later modified by Opinion No. 218-A issued October 15, 1951, in which the Commission determined Panhandle’s designed capacity to be 850,000 Mcf 1 per day and found that such capacity would be insufficient to meet the firm requirements of Panhandle’s customers during the winter of 1951-1952. It, therefore, allocated the capacity of Panhandle’s system among its customers, prescribing the minimum daily volumes which Panhandle would be required to deliver to each customer on days when the total requirements of all customers exceeded 850,000 Mcf. The orders accompanying these opinions directed Panhandle to operate its pipeline system and to make deliveries of gas to its customers in accordance with the terms of the opinions during the period in question pending the effectiveness of a new tariff and service agreements executed thereunder.

*898 In Opinion No. 218 the Commission stated:

“Michigan Consolidated Gas Company has shown a willingness to contract for 202,000 Mcf, or 75,000 Mcf more than its existing contract volume heretofore approved by the Commis- • sion. Panhandle has applied for permission to abandon some 37,500 Mcf of this service at the end of 1951. Subject to further order when the abandonment proceeding, after being heard, is before the Commission, it is determined that the 1951-1952 peak delivery allowable is 127,000 Mcf.”

Thus by Opinion No. 218 and its accompanying order the Commission denied Michigan Consolidated’s- request for 75,000 Mcf of Panhandle’s additional capacity and limited it for the winter of 1951-1952 to its existing contract volume. It is this order which Michigan Consolidated seeks to have set aside as to it by its petition for review filed to No. 10,589.

Panhandle’s proposed tariff was not made effective by the Commission upon the introduction of Trunkline gas into the Panhandle system as requested by Panhandle. Instead the tariff was.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Chanute, Kan. v. Williams Natural Gas Co.
678 F. Supp. 1517 (D. Kansas, 1988)
Michigan Consolidated Gas Company, a Corporation v. Federal Power Commission, Panhandle Eastern Pipe Line Company, Michigan Gas Utilities Company, Central Illinois Light Company, Michigan Gas Storage Company, City of Indianapolis, Indiana, Northern Indiana Fuel& Light Co., Southeastern Michigan Gas Co., Citizens Gas Fuel Company, Missouri Power& Light Company, Missouri Public Service Company, Central Illinois Public Service Company, Illinois Power Company, Illinois Commerce Commission, Missouri Public Service Commission, Public Service Commission of Indiana, Indiana Gas & Water Company, Inc., Intervenors. Michigan Wisconsin Pipe Line Company, a Corporation v. Federal Power Commission, Panhandle Eastern Pipe Line Company, Missouri Public Service Company, Central Illinois Public Service Company, Intervenors. American Louisiana Pipe Line Company, a Corporation v. Federal Power Commission, Panhandle Eastern Pipe Line Company, Missouri Public Service Company, Central Illinois Public Service Company, Intervenors. County of Wayne, Michigan, a Municipal Corporation and Body Politic v. Federal Power Commission, Panhandle Eastern Pipe Line Company, Intervenor. Milwaukee Gas Light Company, a Corporation v. Federal Power Commission, Panhandle Fastern Pipe Line Company, Intervenor. Wisconsin Fuel and Light Company v. Federal Power Commission, Panhandle Eastern Pipe Line Company, Intervenor. Natural Gas Distributors, Inc., a Corporation v. Federal Power Commission, Panhandle Eastern Pipe Line Company, Intervenor. State of Wisconsin and Public Service Commission of Wisconsin v. Federal Power Commission, Panhandle Eastern Pipe Line Company, Intervenor. City of Detroit, Mich., a Municipal Corporation v. Federal Power Commission, Panhandle Eastern Pipe Line Company, Intervenor. Wisconsin Public Service Corporation v. Federal Power Commission, Panhandle Eastern Pipe Line Company, Intervenor. Michigan Consolidated Gas Company, a Corporation v. Federal Power Commission, Panhandle Eastern Pipe Line Company, Central Illinois Light Company, Michigan Gas Utilities Company, Battle Creekgas Company, Michigan Gas Storage Company, Missouri Power & Light Company,missouri Publicservice Company, Illinois Power Company, Illinois Commerce Commission, Missouripublic Service Commission, Indiana Gas & Water Company, Inc., Intervenors
283 F.2d 204 (D.C. Circuit, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
203 F.2d 895, 99 P.U.R. (N.S.) 263, 1953 U.S. App. LEXIS 3444, Counsel Stack Legal Research, https://law.counselstack.com/opinion/michigan-consol-gas-co-v-federal-power-commission-two-cases-ca3-1953.