Public Service Commission v. Panda-Brandywine, L.P.

825 A.2d 462, 375 Md. 185, 2003 Md. LEXIS 315
CourtCourt of Appeals of Maryland
DecidedJune 10, 2003
Docket92, Sept. Term, 2002
StatusPublished
Cited by18 cases

This text of 825 A.2d 462 (Public Service Commission v. Panda-Brandywine, L.P.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Public Service Commission v. Panda-Brandywine, L.P., 825 A.2d 462, 375 Md. 185, 2003 Md. LEXIS 315 (Md. 2003).

Opinion

WILNER, Judge.

This case arises from the maelstrom accompanying the restructuring of the electric industry in Maryland. Although it is an appeal by the Maryland Public Service Commission (PSC) from a judgment of the Circuit Court for Montgomery County reversing one of its administrative decisions, the prin *188 cipal parties in interest are Potomac Electric Power Company (PEPCO), Panda-Brandywine, L.P. (Panda), and Southern Energy, Inc. (SEI). The issue presented to the PSC was whether certain provisions in an Asset Purchase and Sale Agreement (APSA) between PEPCO and SEI caused that agreement to contravene an anti-assignment clause in an earlier power purchase agreement (PPA) that PEPCO had with Panda.

The PSC entered an order declaring that the APSA did not violate the anti-assignment provision of the PPA and that Panda’s consent to the APSA was therefore not required. The Circuit Court, in an action by Panda for judicial review of the PSC order, disagreed with the PSC’s conclusion that there was no violation of the anti-assignment provision. It found that the disputed provisions in the APSA did constitute an assignment of rights and obligations under the PPA and that, absent Panda’s consent, it was impermissible.

The Court of Special Appeals, upon the PSC’s and PEPCO’s appeal, agreed that those provisions — Schedule 2.4 of the APSA — constituted an assignment or delegation in contravention of the PPA. It concluded, however, that the PSC has the authority, on public policy grounds, to “validate transactions that violate anti-assignment provisions that would entitle the complaining party to assert a cause of action under Maryland contract law,” and it directed that the case be remanded to the PSC for a determination whether, on purely public policy grounds, the APSA should be validated notwithstanding the anti-assignment violation.

We granted cross-petitions for certiorari to review the judgment of the Court of Special Appeals. We agree with the intermediate appellate court, and the Circuit Court, that Schedule 2.4 of the APSA violates the anti-assignment provisions of the PPA. We shall vacate, however, that part of the judgment directing a remand to the PSC. The issue of whether the PSC has any authority to validate the APSA on public policy grounds was not raised in the administrative *189 proceeding and should not have been injected into the case by the Court of Special Appeals.

BACKGROUND

PEPCO is an electric utility serving the metropolitan Washington, D.C. area. Panda is a “qualified facility” (QF) under the Public Utility Regulatory Policies Act of 1978 (PURPA) (16 U.S.C. § 2601 et seq.). It has that status because it is a “qualifying cogeneration facility” that produces electricity and steam or other useful energy for industrial, commercial, cooling, or heating processes and because it conforms with regulations promulgated by the Federal Energy Regulatory Commission (FERC). See 16 U.S.C. § 796(18)(B).

As part of its effort to provide for increased conservation of electric energy and increased efficiency in the use of facilities and resources by electric utilities, Congress directed in § 210 of PURPA (16 U.S.C. § 824a-3) that FERC adopt regulations to encourage cogeneration production and specified that those regulations require electric utilities to purchase electric energy from qualified facilities. Dutifully, FERC adopted such regulations. See 18 CFR § 292.303, requiring electric utilities to purchase any energy and capacity made available from a QF either directly or indirectly to the utility. 1 The regulations require the utility to make any interconnections with a QF that are necessary to accomplish the purchase. Id. § 292.303(c)(1).

In August, 1991, PEPCO and Panda entered into a PPA calling for (1) the construction by Panda of a new 230-megawatt cogenerating power plant in Prince George’s County, (2) connection of the facility to PEPCO’s high voltage transmission system by transmission facilities to be built by Panda but later transferred without cost to PEPCO, and (3) *190 upon commencement of the commercial operation of the plant, for PEPCO to purchase the power generated by that plant for a period of 25 years. The plant was built at a cost of $215 million, financed mostly through loans.

The PPA is 113 pages in length, single-spaced, and is both detailed and complex. In it, PEPCO was given substantial authority to review, influence, and, in some instances, determine important aspects of both the construction and operation of the Panda facility. Among other things, PEPCO had the right: (1) to review the design of the facility and monitor its construction, start-up, testing, and operation (§ 7.1(e)); (2) to review and approve certain performance standards for the generators (§ 7.1(g)); and (3) to review and approve Panda’s selection of the operator of the facility and the terms and conditions of any operation and maintenance agreement entered'into by Panda with respect to the facility (§ 8.1(e)). In addition, PEPCO had the right to appoint one of the two members of an operating committee charged with developing policies and procedures regarding operations, maintenance, outage and capability reporting, accounting, and record keeping, except that PEPCO reserved sole discretion over procedures pertaining to the interconnection of the facility to the PEPCO system and the operation of the facility in a parallel mode with the PEPCO system (§§ 8.10 and 7.1(h)). It had an option to purchase Panda’s interest in the facility at fair market value in the event Panda desired to sell and had not received a bona fide offer, and it had a right of first refusal to purchase an interest in Panda itself (§§ 18.1 and 18.3).

The plant was to have a Dependable Capacity of 230 megawatts, which was divided, for operational purposes, into two categories — a Limited Dispatch Portion of 90 megawatts and a Dispatchable Portion of 140 megawatts. Under the initial agreement, PEPCO was obliged to purchase the entire Dependable Capacity of the facility (§ 5.1), but it had substantial control over when during the day or week the Dispatchable Portion was to be delivered and some control over when the Limited Dispatch Portion was to be delivered (§ 8.3).

*191 Section 19.1 of the PPA provided, with certain exceptions not relevant here, that “[n]either this Agreement, nor any of the rights or obligations hereunder, may be assigned, transferred, or delegated by either Party, without the express prior written consent of the other Party, which consent shall not be unreasonably withheld....

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lyles v. Santander Consumer USA
Court of Appeals of Maryland, 2025
In Matter of Petition of Featherfall Restoration
Court of Appeals of Maryland, 2025
Petition of Featherfall Restoration
Court of Special Appeals of Maryland, 2024
Maryland Office of People's Counsel v. Maryland Public Service Commission
127 A.3d 582 (Court of Special Appeals of Maryland, 2015)
Water Applications & Systems Corp. v. Bituminous Casualty Corp.
2013 IL App (1st) 120983 (Appellate Court of Illinois, 2013)
In Re Bogdan
414 F.3d 507 (Fourth Circuit, 2005)
Logan v. JKV Real Estate Services (In re Bogdan)
414 F.3d 507 (Fourth Circuit, 2005)
Della Ratta v. Larkin
856 A.2d 643 (Court of Appeals of Maryland, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
825 A.2d 462, 375 Md. 185, 2003 Md. LEXIS 315, Counsel Stack Legal Research, https://law.counselstack.com/opinion/public-service-commission-v-panda-brandywine-lp-md-2003.